Bombay High Court High Court

Maharashtra Housing And Area vs Pessumal Pamandas Menghrajani on 6 November, 2009

Bombay High Court
Maharashtra Housing And Area vs Pessumal Pamandas Menghrajani on 6 November, 2009
Bench: P. B. Majmudar, R. C. Chavan
                                      1

    Lgc




                                                                           
           IN THE HIGH COURT OF JUDICATURE AT BOMBAY
              ORDINARY ORIGINAL CIVIL JURISDIC/TION




                                                   
                         APPEAL NO.343 OF 2009
                                   IN
                          SUIT NO.3902 OF 1992




                                                  
    1.  Maharashtra Housing and Area                  ]
         Development Authority, Griha Nirman          ]
         Bhavan, Bandra(East), Mumbai-400051          ] 




                                         
                                                      ]
    2.  The Deputy Chief Executive (Works)
                             ig                       ]
          Mumbai Housing and Area Development         ]
          Board, Griha Nirman Bhavan,                 ]
          Bandra (East), Mumbai - 400 051             ]
                           
                                                      ]
    3.   The Executive Engineer, Housing              ]
          Bandra Division, Mumbai Housing             ]
          Area Development Board, Griha Nirman        ]......  Appellants
            


          Bhavan, Bandra(East), Mumbai-400051         ]Org.Defendants
         



                        Versus

    Pessumal Pamandas Menghrajani                     ]





    carrying on business and Civil Engineers and      ]
    Government Contractors, in the firm name          ]
    and style of Jeevan Construction as Sole          ]
    Proprietor thereof and having his office at       ] Respondent

4/54, Daulat Nagar, Thane(East)-400 603 ]Org.Plaintiff

Mr.P G Lad, AGP, for the appellants.

Mr.Pessumal Pamandas Menghrajani – respondent- present in person.

::: Downloaded on – 09/06/2013 15:16:24 :::
2

CORAM : P.B.MAJMUDAR &

R.C.CHAVAN, JJ
DATED : NOVEMBER 06, 2009

ORAL JUDGMENT : (PER R.C.CHAVAN, J.)

1. This appeal is directed against the Judgment dated 22nd

August, 2008, delivered by a learned Single Judge of this Court

whereby the learned Single Judge decreed the respondent/plaintiff’s

suit for payment of interest over the amount which was denied to the

respondent/plaintiff by the appellants.

2. The facts, which are material for deciding this Appeal, are

as under :-

The appellants had engaged the services of the

respondent/plaintiff as a Contractor for carrying out certain civil

works. On 28/1/1987 a work order to that effect was issued. The

said work was completed on 28/2/1988. The respondent/plaintiff

raised certain claims in respect of additional material used and

additional works like use of brick bats in place of bricks, use of

::: Downloaded on – 09/06/2013 15:16:24 :::
3

pumps for de-watering etc. The claims which the respondent/plaintiff

had raised from time to time were not entertained by the appellants-

Authorities. Eventually on 26/10/1990 the Deputy Chief Engineer of

the appellants held that the plaintiff was entitled to sum of Rs.

1,45,764/- as against the various claims of the plaintiff amounting to

Rs.1,50,535.35. Out of these amounts, a sum of Rs.1,20,000/- was

paid to the plaintiff on 3/12/1991 and further sum of Rs.25,764/-

was paid thereafter on 11/3/1992.

3. Since the plaintiff was kept out of the amounts due, after

issuing the notice under Section 173 of the Maharashtra Housing and

Area Development Act, 1976, the plaintiff filed the suit for recovery of

the amount of interest at the rate of 21% per annum on the amounts

denied to the plaintiff from time to time, which came to Rs.

1,31,345.90 on the date of the suit. The plaintiff claimed further

interest at the rate of 21% per annum on this sum from the date of

the suit till realization.

::: Downloaded on – 09/06/2013 15:16:24 :::
4

4. By a Written Statement, the appellants/Defendants denied

the liability to pay such interest, though they admitted that they had

paid the sum of Rs.1,45,764/- as against the claim of the plaintiff to

the tune of Rs.1,50,535.35 after the disputes were raised by the

plaintiff. It was contended that the contract which the appellants had

entered into with the plaintiff did not contain any clause for payment

of any interest. They also raised various other contentions like the

suit being not tenable etc.

5. On these pleadings, three issues were struck by the learned

Single Judge namely as to whether the plaintiff proves that the due

and payable amounts were delayed for a long time from the due dates

by the defendants, whether the plaintiff was entitled to the interest on

the delayed payment from the defendants, and whether the plaintiff

was entitled to payment of Rs.1,31,345.90 with interest thereon @

21% p.a. from the date of suit till judgment. The learned Single

Judge answered the first two issues in the affirmative and ordered

payment of Rs.1,31,345.90 with interest @ 12% p.a. from the date of

::: Downloaded on – 09/06/2013 15:16:24 :::
5

suit till realisation, after considering the evidence tendered. The oral

evidence comprises of only the testimony of the plaintiff. The

appellants had not chosen to tender any oral evidence before the

Court. Aggrieved by the judgment, the appellants are before this

Court.

6. We have heard the learned AGP Shri P G Lad for the

appellants/Defendants and the respondent/plaintiff who is present in

person. The first point that arises for our consideration is, whether

the learned Single Judge rightly held that amounts due and payable

were withheld by the appellants without any justification. The learned

AGP even questioned the entitlement of the respondent/plaintiff to

the amounts already paid. It is submitted by the learned AGP that the

Deputy Chief Engineer came to the conclusion of awarding amounts

claimed by the plaintiff by liberally considering the plaintiff’s claim,

though the same was required tobe rejected.It would be improper and

impermissible to re-open the question of entitlement of the plaintiff to

the amounts for various additional items of work carried out by him,

::: Downloaded on – 09/06/2013 15:16:24 :::
6

since the appellants/Defendants had already paid those amounts. The

elaborate order passed by the Deputy Chief Engineer on 26/10/1990,

which has been considered by the learned Single Judge, shows that

the Deputy Chief Engineer had found that the authorities were wrong

in denying to the plaintiff’s various amounts which he had claimed.

The learned Single Judge has quoted in Para 48, the observation of

the Deputy Chief Engineer that

“…… this entire case is not dealt properly since
beginning in spite of numerous/constant

communication from the Agency and no timely
action from the Board which has resulted into

embarrassing position and this is liable for creating
incident of contractual complications.”

In the face of this it is not open to the appellants to re-agitate

the question of respondent’s entitlement to the amounts claimed.

7. The learned AGP submitted that there was no delay in

payment of amounts to the plaintiff, since the amounts had to be first

ascertained by an “adjudication” by the Deputy Chief Officer

::: Downloaded on – 09/06/2013 15:16:24 :::
7

(Engineer), which was concluded only on 26/10/1990. The amounts

found due were promptly paid thereafter. This contention has to be

rejected for two reasons. Firstly, the plaintiff had been raising his

claims right since the work was executed in 1988. “Decision” by the

Deputy Chief Engineer of the appellants, to whom the claims were

presumably referable under the contract, cannot be equated to an

independent adjudication, over which parties may not have any

control. The appellant has not been able to show what prevented the

Deputy Chief Engineer to promptly decide the claim in 1988 itself. If

when the appellant’s own authorities chose to sit over the matter for

over two years, the appellant cannot take benefit of delay in decision

making. And, ironically, even after the decision, the appellant took

more than one year to pay the amounts which even according to the

appellant’s Deputy Chief Engineer, the plaintiff was entitled to.

8. The appellant cannot take advantage of administrative

procedural delays since it was an internal matter of the appellants for

which the respondent/plaintiff could not be made to suffer. We

::: Downloaded on – 09/06/2013 15:16:24 :::
8

therefore hold that the learned Single Judge has rightly concluded

that the amounts due and payable were withheld without

justification.

9. This takes us to next question as to whether this delay

entitled the plaintiff to claim interest from the date of completion of

work till payment was actually made. The learned AGP Shri Lad

appearing for the appellants submitted that the plaintiff had admitted

in his cross examination that there was no term in the contract

providing for payment of any interest to the plaintiff, and therefore,

there was no contractual foundation for the claim of the plaintiff in

respect of interest. He further submitted that the interest could not

have been paid even under the Interest Act since the sum was not

ascertained till the adjudication, i.e. till 26/10/1990, on which date

the Deputy Chief Engineer decided that the sum of Rs.1,45,764/- was

payable to the plaintiff. Therefore, he submitted that first, since the

sums claimed by the plaintiff were not ascertained, and secondly,

since there was no adjudication ascertaining the sums claimed, there

::: Downloaded on – 09/06/2013 15:16:24 :::
9

was no liability to pay interest. He also submitted that the judicial

pronouncements on this question, right from the Privy Council, would

rule out the payment of interest to the plaintiff.

10. For this purpose he relied upon the judgment of the Privy

Council in the case of Maine and New Brunswick Electrical Power

Co. Ltd. v/s. Alice M Hart, reported in AIR 1929 Privy Council 185.

In that case, the Board considered the question of paying the interest

and observed in the last penultimate para of the judgment as under:-

“Hart conveyed the property purchased to the
defendants. He received from the defendants the

stock to be transferred to him, and he accepted

from the defendants, as under the contract he was
bound to do, covenants under seal to perform

certain obligations of a continuing character
involving the payment from time to time of sums of
money. Upon the stock having been allotted or
transferred to Hart and the covenants having been

executed, Hart had received all the consideration
moving from the defendants to him under the
contract. The plaintiff, as Hart’s successor-in-tilte,

::: Downloaded on – 09/06/2013 15:16:24 :::
10

cannot, and as appears from her statement of

claim, does not sue upon the contract, which is
fully executed : she sues upon the covenants. Those

covenants must be construed according to the
ordinary rules of construction : and if so construed,

they do not give the plaintiff interest, she cannot
claim interest unless it is given to her at common
law or under statute. There is no place in the

matter for the exercise of equitable jurisdiction

and, therefore, no rule of equity in regard to
interest can have any application.”

11. In the same year, the Judicial Commissioner at Nagpur in

the matter of P P Deo v/s. Narayan and others, reported in AIR

1929 Nagpur 170 held that considering the provisions of Interest Act,

it was not correct to say that the Courts have power to award interest

in all cases where money due is withheld. As the discussion to follow

would unfold, the claim in the suit is for compensation for the loss

caused due to delayed payment, and “interest” is only a measure to

compute the loss. Viewed thus, in our view, the judgments would be

unhelpful.

::: Downloaded on – 09/06/2013 15:16:24 :::
11

12. Relying on the judgment of the Supreme Court in the case

of Thawardas Pherumal and anr. v/s Union of India reported in

AIR 1955 SC 468, the learned AGP Shri Lad submitted that interest

would not be payable as of rule unless certain conditions referred to

by the Supreme Court in Para 30 of the said judgment were fulfilled.

In para 30 of the Judgment, the Supreme Court held as under :-

“The Interest Act, 1939 applies, as interest is not
otherwise payable by law in this kind of case (see —

`B N Ry. Co. v. Ruttanji Ramji’, AIR 1938 PC 67
(J), but even if it be assumed that an arbitrator is a

“Court” within the meaning of that Act, (a fact that
by no means appears to be the case), the following

among other conditions must be fulfilled before
interest can be awarded under the Act :

               (1)          there must be a debt or a sum certain,
               (2)          it must be payable at a certain time or  
                            otherwise;





               (3)          these debts or sums must be payable by  
                            virtue   of   some   written   contract   at   a  
                            certain time;




                                                                 ::: Downloaded on - 09/06/2013 15:16:24 :::
                                             12

                 (4)         There   must   have   been   a   demand   in  




                                                                                     
                             writing   stating   that   interest   will   be  
                             demanded from the date of the demand.




                                                             
                 Not   one   of   these   elements   is   present,   so   the 




                                                            

arbitrator erred in law in thinking that he had the
power to allow interest simply because he thought
the demand was reasonable.”

13.

Therefore according to the learned AGP, in this case, since

sums claimed were not ascertained till the adjudications were

completed on 26/10/1990, there is absolutely no question of payment

of any interest. This contention is fallacious. It is not that the plaintiff

had set his claims to any nebulous amounts. He had quantified his

claim on each items right from the beginning and his first salvo to the

appellants itself would show that he had claimed certain amounts.

Whether this claim was acceptable to the appellants’ authorities

would not be determinative of question whether the sum was

ascertained or not. A reference to the Deputy Chief Engineer’s order

dated 26/10/1990 would itself show that claims for specific sums had

::: Downloaded on – 09/06/2013 15:16:24 :::
13

been raised and had been considered by him. The respondent had

filed a copy of letter dated 12/10/1988 written by him, (Article No.5,

referred to in Q.No.88 in plaintiff’s cross-examination for appellant

taken on 4/10/2007). This letter not only specifies the amount

claimed, but also raises specific demand of interest at 21% p.a. from

27.5.1988 i.e. after leaving a three months grace period after

completion of work on 28.2.1988. Thus the requirements mentioned

in the case of Thawardas are complied.

14. In her erudite judgment, the learned Single Judge has

carefully considered this aspect and has held that the interest is not

only payable if the contract so provides or statute so provides, but also

under the Common Law. In this context, the learned Single Judge has

considered the provisions of Section 3 of the Interest Act and has

found that the interest could have been ordered to be paid since

written notice claiming the amount had been given and in spite of this

notice the amounts claimed were not paid. It would not have been

proper to deny interest to the respondent/plaintiff on the amount

::: Downloaded on – 09/06/2013 15:16:24 :::
14

which he had claimed to have borrowed for completing the work of

the appellants. As early as on 28.12.1988, the plaintiff had, by his

letter, claimed interest as compensation. It may be seen that even the

appellant’s Q.No.61 in the cross examination of the plaintiff on

19/12/2007would show that interest was claimed as compensation.

Therefore, since the respondent/plaintiff had incurred expenditure

when the work was completed on 28/2/1988, he would be entitled to

be compensated for interest, he was required to pay from 28/5/1988

i.e. after the three months of the grace period. The plaintiff’s evidence

in this regard was not rebutted since appellant did not choose to

tender any evidence. In view of this, there is no substance in the

contention of the learned AGP that the learned Single Judge erred in

awarding the interest, which was in the nature of compensation for

the interest which plaintiff was required to pay on amounts borrowed

from his bank.

15. This takes us to the next submission of the learned AGP

that the learned Single Judge erred in awarding the interest at 12%

::: Downloaded on – 09/06/2013 15:16:24 :::
15

per annum as there was no warrant and no evidence for arriving at

such a rate. The learned AGP may be right in submitting that there

was no witness examined by the plaintiff from his Bank to prove that

he had been paying interest on the amount borrowed. But a letter

from bank, Article 25, produced by him before the Court has been

considered by the learned Single Judge in Para 68 of the judgment,

which shows that plaintiff was paying interest at 17.34% p.a. on the

credit facilities availed by him. Apart from that award of interest at

12% per annum, on the amounts which had been denied to the

plaintiff, could not be called erroneous, considering the prevailing

rate of the interest in the market. This was in the nature of

compensation for the loss caused, either by being required to actually

incur this expense by paying interest to his bank or by being denied

the use of these amounts.

16. The learned AGP lastly submitted that the learned Single

Judge has also awarded interest on the decretal amount from the date

of the suit till realization, which amounts to awarding the interest

::: Downloaded on – 09/06/2013 15:16:24 :::
16

over interest and such a compound interest could not have been

granted in a suit for recovery of money. The proposition that interest

would not be awarded on interest is correct. But this is a peculiar case

where the plaintiff has been kept out of the money due and therefore

he incurred a loss which has been compensated by the interest

awarded by the learned Judge. Therefore, award of interest on such

amounts, which are in the nature of compensation, and which the

plaintiff was deprived of, cannot be termed as interest over the

interest. Viewed pragmatically, the plaintiff could be said to have

been awarded damages for the tort of being kept out of the amounts

which were due. Therefore, interest which is awarded from the date

of institution of the suit could be treated as interest on the amount of

compensation to which the plaintiff was entitled on being kept out of

amount due. In view of this, there is no merit in this Appeal which is

accordingly dismissed with costs.

                Sd/-                                                             sd/-





    [R.C.CHAVAN,J]                                               [P.B.MAJMUDAR,J]




                                                               ::: Downloaded on - 09/06/2013 15:16:24 :::