High Court Kerala High Court

Joyilal vs Krishnankutty on 5 November, 2008

Kerala High Court
Joyilal vs Krishnankutty on 5 November, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

RSA.No. 1068 of 2008()


1. JOYILAL, W/O.SASIDHARAN, AGED 53 YEARS,
                      ...  Petitioner

                        Vs



1. KRISHNANKUTTY, S/O.RAMALINGAM,
                       ...       Respondent

                For Petitioner  :SRI.V.S.BABU GIREESAN

                For Respondent  : No Appearance

The Hon'ble MR. Justice V.RAMKUMAR

 Dated :05/11/2008

 O R D E R
                       V. RAMKUMAR, J.
                    = = = = = = = = = = = = =
                      R.S.A.No.1068 of 2008
                   = = = = = = = = = = = = = =
           Dated this the 5th  day of November, 2008

                            JUDGMENT

The plaintiff in O.S.No.177 of 1996 on the file of the

Munsiff’s Court, Attingal is the appellant in this Second Appeal.

The said suit was one for prohibitory and mandatory injunction

against the construction carried on by the defendant in the plaint

B Schedule Property shown as admeasuring 1.766 cents

allegedly in violation of the Building Rules as well as the Kerala

Panchayat Raj Act, 1994.

2. The case of the plaintiff can be summarised as follows:-

The plaintiff is the owner in possession of the plaint A

Schedule Property admeasuring 15 cents comprised in Survey

No.1782/1 of Pulimath village in Cherayinkeezhu Taluk. The

plaint B Schedule Property belonging to the dependant lies on

the western boundary of the plaint A Schedule Property. The

total extent of plaint B Schedule Property is 1.766 cents

comprising in Survey No.1782/3. To the further west of the

plaint B Schedule Property is the M.C.road. The defendant has

R.S.ANo.1068 of 2008
2

started the construction of a terraced building in the plaint B

Schedule Property. For the construction of pillars, the defendant

had removed earth after encroaching into the plaint A Schedule

Property for about 1.85 meters. The construction of the pillars

on the western side is against the provisions of the Kerala

Panchayat Raj Act in not leaving sufficient open space from the

M.C.Road. The construction is carried out in violation of the

provisions of the Kerala Panchayat Raj Act and the Building

Rules. Hence the suit.

3. The suit was resisted by the defendant contending, inter

alia, as follows:-

The case of the plaintiff that the defendant is in possession

of only 1.766 cents of land is not correct. This defendant had

purchased 4 cents of land as evidenced by Ext.B1 registered sale

deed dated 16.8.1977. Ever since then, this defendant is in

possession and enjoyment of the said property. This defendant

has already started the construction work after obtaining

permission from the Panchayat authorities. The plaint allegation

that the defendant has violated the Building Rules and the

provisions of the Kerala Panchayat Raj Act is not correct. This

defendant has left sufficient open space as required by the Rules.

R.S.ANo.1068 of 2008
3

This defendant has not encroached into the plaint A Schedule

Property. The plaintiff did not raise any objection when this

defendant removed the earth from the Plaint B Schedule

Property. The property of the plaintiff was formerly a paddy

field which was raised by him years back. There was a thodu

between the plaint A and B Schedule properties. The plaintiff

had filled up the said thodu and had levelled the remaining

paddy field. The boundary between the plaint A and B Schedule

was the said thodu which is not in existence now. This defendant

had obtained permission from Pulimath Panchayat. The said

panchayat is a necessary party to the suit which has to be

dismissed.

4. On the side of the plaintiff Exts.A1 to A4 were marked.

Four witnesses were examined as PWs.1to 4 of whom PW1 is the

husband of the plaintiff. On the side of the defendant Exts.B1 to

B4 were marked and DWs. 1 and 2 were examined of whom DW1

is the defendant himself. The learned Munsiff, after trial, as

per judgment and decree dated 18.8.2000, dismissed the suit

holding, inter alia, that since the Building Rules were not

applicable to the Pulimath Panchayat at the time of the starting

of the construction, the allegation of the plaintiff that the

R.S.ANo.1068 of 2008
4

defendant had violated the Building Rules is not sustainable, that

going by the Commissioner’s report and plan prepared with the

assistance of the surveyor and the evidence of the Advocate

Commissioner as well as that of the Surveyor it was not safe to

accept the report of the Commissioner to the effect that the

distance between the western pillars of the construction and the

retaining wall at the eastern extremity of M.C.Road was 3.1

meters. However, the trial court found that notwithstanding the

apparent contradiction between the evidence of the surveyor and

the report of the Commissioner, except filing her objection to the

report and plan, the plaintiff did not apply for remitting the

same to the Commissioner, nor did she apply for an additional

report and plan. In that view of the matter the trial court

dismissed the suit holding that the plaintiff had failed to prove

that the defendant had violated the Building Rules or the

provisions in the Kerala Panchayat Raj Act. On appeal preferred

by the plaintiff as A.S.No.60/2000, the lower appellate court also

concurred with the conclusions reached by the trial court and

dismissed the appeal as per the judgment and decree dated

27.10.2007. Hence this Second Appeal.

5. The learned counsel for the appellant/plaintiff reiterated

R.S.ANo.1068 of 2008
5

the contentions of the plaintiff. He made the following further

submissions before me:-

Both the courts have come to the conclusion that Exts.C2

report and C2(a) plan cannot be fully relied on in the light of the

apparent contradictions between the distance shown therein and

the testimony of the surveyor examined as PW3. If so, it was not

open to the courts to blame the plaintiff for not filing an

application for remitting the report and plan or for applying for

an additional report since there is no such requirement under

Rules 10,12 and 14 of Order XXVI C.P.C. On the concurrent

finding that the report and plan of the Commissioner could not

be fully relied on, the court itself should have suo motu set aside

the report and plan and remitted the same to the Commissioner.

The courts below went wrong in casting the burden on the

plaintiff.

6. I am afraid that I cannot agree with the above

submissions. Firstly, the plaintiff came to the court alleging that

the Building Rules were violated by not leaving sufficient space

at the boundary between the plaint A Schedule property of the

plaintiff and the plaint B Schedule property situated to the west

of the plaint A schedule property. Both the courts below have

R.S.ANo.1068 of 2008
6

held that since the Building Rules were not applicable to the said

building where the construction is carried out, the plaintiff could

not complain of not giving sufficient space at the boundary.

Moreover, the Commissioner noted that a space of 1metre has

been left between the eastern pillar of the construction and the

eastern extremity of the Plaint B Schedule Property. The

defendant has a specific case that the boundary between plaint A

and B schedule properties was a thodu and the plaint A schedule

property which was a paddy field was filled up by the plaintiff

who had also levelled the thodu. The said case of the defendant

appears to be true. The Commissioner has specifically noted

that there was no temporary boundary between A and B

schedule properties. The distance of one meter has been seen

left from the eastern pillar to the extremity of the plaint B

Schedule Property. Eventhough the Building Rules are not

applicable, sufficient space has been left on the eastern side of

the plaint schedule property and the plaintiff cannot be heard to

complain that no space was left.

7. Now coming to the western side of the construction, it is

seen that there is a triangular plot in between the plaint B

Schedule property and the M.C.Road. So, the plaint B Schedule

R.S.ANo.1068 of 2008
7

property is not technically abutting the M.C.Road which is on the

west. Eventhough Exts.C2(a) plan C2 report were prepared with

the assistance of the Taluk surveyor, the Taluk Surveyor when

examined as PW3 would take exception to which was noted by

the Advocate Commissioner. Having subscribed his signature to

Ext.C2(a) plan, it was not open to PW3 to depose at variance

from what has been shown in Ext.C2(a) plan. Even if implicit

faith could be attributed to the testimony of PW3 as has been

done still sufficient space has been left on the western side of

the construction on the plaint B Schedule Property. C2(a) plan

does not show any encroachment into the road puramboke as

well. Whether the vacant space leaves 3.1 meters as noted by

the Commissioner or a lesser space as asserted by PW3, Taluk

Surveyor, the fact remains that sufficient space has been left on

the western side of the construction in between the construction

and the triangular plot abutting of the M.C.Road. It is

essentially for the panchayat which has permitted the defendant

to put up the construction to take exception to the violation, if

any, of the provisions of the Kerala Panchayat Raj Act. It is

pertinent in this connection to note that the defendant had

specifically raised a contention in the written statement that the

R.S.ANo.1068 of 2008
8

Panchayat is a necessary party to the suit. In spite of raising

such a contention, the plaintiff did not think it necessary to

implead the Panchayat as an additional defendant. The plaintiff

cannot now come forward with a plea that there is infraction of

the provisions of the Kerala Panchayat Raj Act. I see no good

ground to interfere with the Judgments concurrently passed by

the courts below.

No questions of law, much less any substantial question of

law arises for consideration in this second appeal. The

questions of law formulated in the memorandum of appeal do not

arise for consideration in this second appeal which is accordingly

dismissed in limine.

Dated this the 5th day of November, 2008.

V. RAMKUMAR, JUDGE

sj