High Court Rajasthan High Court - Jodhpur

M/S Indeera Builders (P) Ltd vs Union Of India & Ors on 19 May, 2009

Rajasthan High Court – Jodhpur
M/S Indeera Builders (P) Ltd vs Union Of India & Ors on 19 May, 2009
                               1

          S.B. Arbitration Application No.59/2007
          M/s. Indeera Builders (petitioner) Ltd.
                             vs
                    Union of India & Ors

DATE OF ORDER: 19.5.2009

              HON'BLE MR. PRAKASH TATIA, J.

Mr. SD Vyas, for the petitioner.

Mr. Kamal Dave, for the respondents. .

Heard learned counsel for the parties.

The contract was entered into between the applicant and

Union of India through Chief Engineer (Construction) North

Western Railway, Jaipur on 23.9.2004. By this contract, the

petitioner was given some work contract and the period of the

contract was 11 months and the work was to be completed by

14th June, 2005. According to the petitioner due to the fault of

the respondent-Railway Department and circumstances beyond

the control of the petitioner, the work period was sought to be

extended upto Dec., 2005, but it was extended only upto

14.8.2005. According tot he petitioner, he was in process of

completing the work, but the contract was terminated on 5th

July, 2005 pre-maturely and, therefore,, the petitioner suffered

loss. The petitioner alleged that the termination of the contract

was absolutely illegal and it should not have been terminated at

the fag end of the completion of the work. Be it as it may be,
2

the dispute arises between the parties as petitioner has sought

claims referred in this petition. The petitioner requested the

respondent to appoint the arbitrator by serving a notice vide

letters dated 9th Sept., 2005, 30th Dec., 2005 and 16th Jan.,

2006. The respondent refused to appoint the arbitrator by

communication dated 21.3.2006, copy of which has been placed

on record as Annex.C. The respondent refused to appoint the

arbitrator on the ground that the respondents examined the

claim of the petitioner and found that most of the claims covered

under excepted matters as described in clause No.63 of the

General Conditions of Contract. Apart from above, it has been

stated that the petitioner left the work incomplete and this work

was terminated at petitioner’s risk and cost, therefore, earnest

money of Rs.50,000/- and security deposit of Rs.2.50 lacs were

forfeited as per clause no.16 of the General Conditions of

Contract. It is also stated that there is no price escalation clause

in this contract, thus your claim no.6 is also beyond the scope of

contract. It is also stated that petitioner failed to execute the

work in stipulated time period, thus, the balance work was

executed from other agency at the risk and cost of the petitioner

including liability for the petitioner of Rs.14,18,992/-.

Learned counsel for the petitioner submits that there is no

dispute that there is arbitration clause and whether the claim

falls under the excepted matters is concerned, that also can be
3

decided by the arbitrator and when respondent themselves

stated that “most of the claims cover under excepted matters”

then admittedly, there are other claims of the petitioner which

were raised before the respondent were not the claims falling

under the “excepted matters”. It is submitted that petitioner is

disputing the respondent’s contention that any of the matter is

falling under the “excepted matters” and, therefore, cannot be

referred to arbitrator. It is also submitted that instead of

referring the dispute to the arbitrator, it appears that

respondents themselves had decided the dispute which they

could not have decided.

Learned counsel for the respondent submitted that the

“excepted matters” cannot be referred to the arbitrator in view

of clause 63 of the General Conditions of the Contract. It is

submitted that even if any arbitrator is appointed then that is

required to be appointed as per clause 64(3)(a)(iii), which

provides that no person other than a gazetted Railway Officer

should act as an Arbitrator/Umpire and if for any reason, that is

not possible, the matter is not to be referred to arbitration at all.

Therefore, only a gazetted Railway Officer can be appointed as

arbitrator.

I considered the submissions of learned counsel for the

parties and perused the facts of the case.

From communication sent by the respondent to the
4

petitioner dated 21.3.2006 even it is clear that there is no

dispute that there is arbitration clause in the contract. Even as

per the respondents there are some of the claims which are not

covered under the alleged “excepted matters” so as to deny the

appointment of arbitrator. It is disputed by the petitioner that

any of the claim falls in the category of “excepted matters” and

whether all claim is falling in the said category of “excepted

matters” can also be decided by the arbitrator. It appears that

respondents by communication dated 21.3.2006 have decided

some of the core issue for which petitioner prayed for

appointment of arbitrator that clearly demonstrate that there is

dispute between the parties in the matter where by the contract

provides for settlement of dispute by the arbitral proceedings.

Since the respondents failed to appoint the arbitrator

within time, therefore, this petition is allowed and the

respondents are directed to appoint the arbitrator within a period

of two months from today by keeping in mind clause 64(3)(a)(iii)

of the General Conditions of Contract Regulations and

Instructions for Tenders and Standard Forms of Contract and the

arbitrator shall decide the matter expeditiously.

(PRAKASH TATIA), J.

c.p.goyal/-