High Court Kerala High Court

P.Rajan vs K.S.E Board on 7 November, 2008

Kerala High Court
P.Rajan vs K.S.E Board on 7 November, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 33400 of 2000(A)



1. P.RAJAN
                      ...  Petitioner

                        Vs

1. K.S.E BOARD
                       ...       Respondent

                For Petitioner  :SRI.P.B.SAHASRANAMAN

                For Respondent  :SRI.N.D.PREMACHANDRAN, SC, KSEB

The Hon'ble MR. Justice S.SIRI JAGAN

 Dated :07/11/2008

 O R D E R
                        S. SIRI JAGAN, J.
                ------------------------------------
                    O.P.No.33400 OF 2000
              ----------------------------------------
             Dated this the 7th day of November, 2008

                           JUDGMENT

The petitioner challenges disciplinary proceedings initiated

against him, after retirement, for recovery of loss caused to the

Kerala State Electricity Board on account of negligence of the

petitioner in his duties. The allegation was that while the

petitioner was working as Sub – Engineer at 110 KV Sub Station,

Chevayoor, Kozhikode, for the period from 9/90 to 11/96, he

failed to take note of the multiplication factor of 5 applicable to

the meter of a particular consumer for calculating the energy

charges, as a result of which the board suffered a loss of

Rs.3,14,514/-. The contention of the petitioner is that he was

not working in that particular station for the entire period, but

was working only from 12/90 to 5/96. He would further submit

that against proceedings for recovery of the amount from the

consumer, the consumer had filed O.S. No.130/1997 before Sub

Court, Kozhikode, in which the demand against the consumer

was set aside on the ground of limitation. According to the

O.P.No.33400/2000 2

petitioner, that was because the Board did not contest the case

properly. He points out that in the decision of Southern

India Marine Products Co. V. K.S.E.B [1995(2) KLT 167],

this Court has held that for recovery of electricity charges, the

Limitation Act is not applicable. According to the petitioner, if

the Board has brought this decision to the notice of the Court,

the Board would not have suffered the loss which is sought to

be recovered from the petitioner and therefore the petitioner

cannot be made liable for the same.

2. With the help of a counter affidavit, the Board would

dispute the contentions of the petitioner. According to them, it

is not disputed that the multiplication factor was applicable and

not taken into account for deciding the electricity charges due

from the consumer. They would point out that the

multiplication factor has been recorded in the billing calculation

register, which ought to have been perused by the petitioner

before meter readings were reckoned for the purpose of

calculation of energy charges. It is pointed out that for the

purpose of recovery from the petitioner only the period from

12/92 to 5/96 during which the petitioner was working in the

Sub Station only was taken into account. According to them,

O.P.No.33400/2000 3

by Ext.P5, only 40% of the loss has been ordered to be

recovered from the petitioner, that too subject to the decision

of the appeal filed by the Board against the decree in the suit

filed by the consumer, which appeal is stated to be pending as

A.S.No.459/99 before this Court.

3. I have considered the contentions of the parties in

this writ petition.

4. As pointed out by the learned counsel for the Board,

the fact that the multiplication factor of the particular meter

ought to have been but has not been taken into account for

the purpose of calculating energy charges is not in dispute. In

Ext.P5, which is the final order passed in the disciplinary

proceedings for the purpose of recovery of loss from the

petitioner, only the period from 12/92 to 5/96 has been taken

into account. Further only 40% of the loss has been ordered

to be recovered from the petitioner which also has further been

made subject to the result of this original petition. Although,

the petitioner would raise a contention that it was because of

the fault of his predecessor in office since the multiplication

factor had not been mentioned in the billing calculation

register, there is no averment to that effect in Ext.P4 reply

O.P.No.33400/2000 4

filed by the petitioner. That being so, it is clear that the

petitioner was negligent in his duties in so far as before

calculating energy charges due from the consumer in question,

the petitioner did not note the multiplication factor, which was

recorded in the billing calculation register and apply the same

for the purpose of billing the consumer. As such, clearly the

petitioner was negligent in his duties. Therefore, I do not find

any merit in the challenge against the impugned orders.

Accordingly, the original petition is dismissed. However,

as stated in Ext.P5, I also make it clear that this would subject

to the final decision in the A.S. and if ultimately, the appeal is

decided in favour of the Board and the board is able to recover

the money from the consumer, the amounts recovered from

the petitioner would be refunded.

S. SIRI JAGAN, JUDGE

Acd

O.P.No.33400/2000 5