High Court Kerala High Court

The Managing Director vs K.S.E.Board on 18 February, 2009

Kerala High Court
The Managing Director vs K.S.E.Board on 18 February, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 7047 of 2001(L)



1. THE MANAGING DIRECTOR
                      ...  Petitioner

                        Vs

1. K.S.E.BOARD
                       ...       Respondent

                For Petitioner  :SRI.P.V.JYOTHI PRASAD

                For Respondent  :SRI.A.SUDHI VASUDEVAN, SC, KSEB

The Hon'ble MR. Justice HARUN-UL-RASHID

 Dated :18/02/2009

 O R D E R
                       HARUN-UL-RASHID,J.
                 ---------------------------
                      O.P.NO.7047 OF 2001
                ----------------------------
           DATED THIS THE 18TH DAY OF FEBRUARY, 2009

                             JUDGMENT

Petitioner is the Managing Director of a tea factory at

Mananthavady and is the consumer of electrical energy for the said

factory. On 16/9/2000 the Anti Power Theft Squad conducted a

site inspection and detected that the power meter is recording only

1/3rd of the actual power drawn from the mains due to wrong

electrical connection of CT meters resulted in reverse running in

one phase and the existence of unauthorised additional load of 44

KW over and above the authorised load of 130 KW. On the basis

of the inspection report, which is produced as Ext.P2, the consumer

was re-assessed with effect from 12/97 for partial recording and 3

times rate on fixed charge and proportionate current charge was

charged for unauthorised additional load (UAL). Ext.P3 is the bill

in which the grand total shows Rs.8,04,741/- out of that fixed

charge is Rs.27,720/-. Petitioner challenged Ext.P3 bill in an

-2-
O.P.No.7047/2001

appeal filed before the Appellate Authority. The Appellate

Authority by proceedings dated 8/2/2001 dismissed the appeal.

2. The learned counsel for the petitioner raised all the

contentions placed before the Appellate Authority. According to

the learned counsel, Regulation 42(d) of the Conditions of

Supply of Electrical Energy provides for re-assessment for six

months and there is no reason for adopting the period from 12/97,

a total period of 32 months. The learned counsel also brought to

this Court’s attention the decision of the Supreme Court in

Belwal Spinning Mills Ltd. v. U.P. State Electricity Board

(AIR 1997 SC 2793), the unreported decision of the learned

Single Judge of this Court dated 23/11/2005 in O.P.No.191/98

and the decision of the Division Bench of this Court in Nirmala

Metal Industries v. K.S.E.B. (2006 (3) KLT 465). Learned

counsel submitted that re-assessment has to be done based on the

aforesaid decisions and it has to be limited to six months.

3. The learned Standing Counsel for the K.S.E. Board

contended that CT connection in Y phase was reversed and there

-3-
O.P.No.7047/2001

was unauthorised additional load of 44 KW during inspection.

The period of re-assessment is taken as 12/97, as there was

sudden drop in recorded consumption from the said date. The

recorded consumption for 10/97 was 21098 Kwh, 11/97 was

23020 KWh and 12/97 was 8782 KWh, which is approximately

1/3 of earlier consumption. It is also brought to this Court’s

attention the recorded consumption subsequent to the site

inspection conducted by the Anti Power Theft Squad. It shows

that the recorded consumption for the month of November, 2000

is 30,280 and for the month of December, 2000, is 36,962 kwh.

The Appellate Authority did not accept the contention of the

appellant that Section 26(6) is applicable and therefore the

maximum amount that can be realised is only for a period of six

months prior to the date of inspection. The Appellate Authority

held that Section 26(6) is applicable only in case of faulty meters

where the reassessment is done based on approximation or

overcharging. In such cases Section 26(6) will attract and the

period has to be limited to six months. According to the

-4-
O.P.No.7047/2001

Appellate Authority, in the instant case, it is entirely different and

that similar issue has been settled by the judgment of the Apex

Court and the High Court. In the judgment in O.P.No.191/98

referred to above, it was stated that on inspection, it was found

that there was some defect in the electric connections inside the

meter consequent to which the meter was recording only 1/3 of

the actual energy consumed. In that case a bill for short

assessment for consumption of electrical energy for the period

stated therein was issued demanding charges for the balance 2/3

energy as payable by the petitioner therein.

4. This Court relying on the decision reported in Belwal

Spinning Mills’s case (1997 SC 2793) discussed the issue and

observed that there is absolutely no allegation of fraud or mal-

practice on the part of the consumer, that the reduced recording

was caused due to the wrong connection inside the meter. The

meter recorded on l/3 of the actual consumption. The facts of the

said case and the facts of the present case are more or less

similar. In this case also the the consumer has not done any mal-

-5-
O.P.No.7047/2001

practice or fraud for the purpose of showing reduced

consumption of energy. Since the Y phase connection is

reversed, 1/3 of the actual consumption was recorded. In the

Supreme Court case also, there was a defective connection

whereby the original meter was registering only 76.6% less than

the actual use. The Court held that Section 26(6) of the Indian

Electricity Act is attracted and therefore, the right of the K.S.E.

Board to demand arrears is limited to a period of past six months.

In this case also applying Section 26(6) of the Indian Electricity

Act, the matter has to be referred to the Chief Electrical

Inspector, as in the said case. It was held that the K.S.E. Board is

entitled to demand arrears only for a period of past six months for

the reason that the recorded consumption is 1/3 of the actual

consumption.

5. Ext.P3 bill was issued for realisation of the amount for

the loss caused to the Board for the reason that Y phase

connection is reversed and for unauthorised additional load to the

extent of 44 KWh under Regulation 42(d) of the Conditions of

-6-
O.P.No.7047/2001

Supply of Electrical Energy. The petitioner is liable to pay the

amounts assessed by the Board for unauthorised additional load

of 44 Kwh in addition to the demand for payment of arrears for

the past six months from the date of detection. Respondents are

entitled to demand only the amount as stated above.

6. In the result, Exts.P3 and P4 are quashed. There will

be a direction to the respondents to re-work the arrears and issue

a fresh bill to the petitioner within a period of two months from

the date of receipt of a copy of this judgment. The amount

already deposited in compliance of the interim order passed by

this Court shall be adjusted.

Original Petition is disposed of as above.

HARUN-UL-RASHID,
Judge.

kcv.