Chattisgarh High Court High Court

M/S Shadani Builders vs M/S Begraj Agrawal on 2 March, 2009

Chattisgarh High Court
M/S Shadani Builders vs M/S Begraj Agrawal on 2 March, 2009
       

  

  

 
 
             HIGH COURT OF CHATTISGARH AT BILASPUR      


               Arbitration Appeal No.25 of 2007

                    1.         M/s   Shadani   Builders
                                                      ...Petitioners


                            Versus

                       1.       M/s    Begraj   Agrawal

                        2.       Justice   Shri   C P    Sen
                                                     ...Respondents

!      Shri  S.K. Dubey, Sr. Advocate with Dr. Shailesh  Ahuja,
      counsel for the appellant.


^      Shri  B.P.  Sharma  with  Shri K.  Sharma,  counsel  for
      respondent No.1.


         Honble Shri Dhirendra Mishra & Honble Shri D R Deshmukh JJ

    Dated:02/03/2009

:    Judgement





                           O R D E R

(Passed on 2nd March, 2009)

The following order of the Court was passed by
Dhirendra Mishra, J.

1. This arbitration appeal under Section 37 (1)(b) of the

Arbitration and Conciliation Act, 1996 (for short `the Act,

1996′) is directed against the order dated 30th June 2007

passed in Civil (Arbitration) Case No.9-A/2007 whereby learned

District Judge, Raipur has rejected the application of the

appellant under Section 34 of the Act, 1996 for setting aside

award dated 3-10-99 passed by the sole arbitrator.

2. The case of the appellant, in brief, is that the

appellant is a firm registered under the Partnership Act. The

partners of the firm owned and possessed lands situated at

village Boriya Kala, Tehsil and District Raipur. Thok Kirana

Vyapari Sangh, Gudiyari, Raipur entered into an agreement to

purchase shops to be constructed on the above described land

on the individual agreement. The rate of each shop was fixed

at Rs.2,50,000/-. A sum of Rs.50,000/- was payable during the

construction period and balance of Rs.2 lakhs with interest in

60 monthly installments commencing from the date of handing

over possession.

3. The appellant and respondent No.1 entered into an

agreement for construction of 500 shops at the rate of Rs.140

per sq. ft.. The shops were to be constructed within 18

months. They entered into another agreement for construction

of road. The dispute arose between the petitioner and the

construction agency regarding construction and payment.

Initially the dispute was resolved and accordingly, the terms

of agreement were modified, however, dispute persisted. On

the basis of report lodged by respondent No.1 proceedings

under Section 145 and 146 of the Code of Criminal Procedure

(for short `the Code’) were drawn and the Sub Divisional

Magistrate, vide order dated 24-10-96, attached 280 under

construction shops and construction materials in Criminal case

No.25/96. The construction materials under attachment were

handed over in the interim custody of one Lalit Kumar

Singhania.

4. Two separate criminal revisions preferred by the

appellant as well as one Ram Awatar Agrawal against the order

of attachment and interim custody were dismissed by learned

Sessions Judge vide order dated 6-12-96. The petition under

Section 482 of the Cr.P.C. preferred by the partner of the

appellant firm was allowed by the High Court of Madhya Pradesh

vide order dated 17-7-97 and criminal proceedings under

Sections 145 and 146 of the Code were quashed with a finding

that respondent No.1 had no right to remain in possession and

the proceedings were abuse of the process of the Court.

Consequently, the shops and the materials were released to the

appellant.

5. The appellant served respondent No.1 with a notice

demanding damages of Rs.2,08,12,430/-. Respondent No.1 denied

liability. Since agreement dated 19-12-94 provided for

settlement of the dispute between the parties through

arbitration by 2 arbitrators, one to be appointed by each of

the parties, the appellant served respondent No.1 with a

notice appointing Justice K.L. Israni, retired Judge of the

High Court of Madhya Pradesh as Arbitrator of the appellant

and called upon the respondent to appoint arbitrator. On

their failure, the appellant approached the High Court of

Madhya Pradesh under Section 11 of the Act, 1996 for

appointment of Arbitrator.

6. In the meanwhile, one Ram Awatar Agrawal filed SLP (Cr)

No.2111/97 in the Supreme Court for quashing of the

proceedings under Section 146 of the Code. The Supreme Court

vide order dated 4-8-97 directed the parties to maintain

status quo in respect of possession of subject property. The

Supreme Court was also apprised that petition under Section 11

of the Act, 1996 is pending in the High Court for appointment

of arbitrators. However, on the basis of consent of the

parties (Ram Awatar Agrawal and Yudhishtirlal) that they shall

abide by decision of arbitrator the Supreme Court vide order

dated 12-12-97 disposed of the petition with following

direction:-

“We direct that such reference be made
to Mr. Justice C.P. Sen. The learned
arbitrator would give his award as early
as practicable, preferably within four
weeks from the date of entering into
reference. It will be open to the
arbitrator to give appropriate interim
direction. The parties have agreed to
abide by such directions of the
arbitrator. Pending the arbitration
proceedings, the Shadani Builders who is
respondent No.2, will maintain status
quo in respect of 150 shops and will not
remove materials, plant, machinery and
equipments from the site. The impugned
judgment/order of the High Court stands
set-aside and the proceedings under
section 145 Cr.P.C. also stand disposed
of. The appeal is accordingly disposed
off.”

7. The record of the case was forwarded to the sole

arbitrator who entered into reference and directed the parties

to submit their respective statements of claims. Accordingly,

respondent No.1 submitted claim for a sum of Rs.5,59,63,446/-

under various heads, as detailed in paragraph-10 of the memo

of appeal. The appellant contested the claim of respondent

No.1 and submitted that the appellant is entitled to receive

damages due to breach of contract on the part of respondent

No.1. The claims are beyond the scope of reference and are

not arbitrable and the claims are highly exaggerated. The

appellant also claimed Rs.2,98,58,540/- and interest thereon

by way of damages under various heads, as detailed in

paragraph-12 of the memo of appeal. The sole arbitrator vide

his order dated 9th May, 1998 directed the appellant to

furnish bank guarantee for a sum of Rs.1 crore towards

security for the satisfaction of the claim and rejected the

prayer to release the shop.

8. On the basis of pleadings of the respective parties,

statements of claims and counter claims put-forth by the

parties, learned Arbitrator framed various issues.

9. The parties to the proceedings filed affidavit apart from

filing other documents in support of their case and also

examined witnesses before the Tribunal.

10. After elaborately dealing with various clauses of the

original agreement as well as subsequent 3 agreements, it has

been held that the agreements were executed in the presence of

independent persons and it is difficult to believe that the

contractor was coerced in executing subsequent three

agreements under economic duress. Contention of the owner

that subsequent agreement dated 3-10-1995 supersedes the

original contract dated 19-12-1994 has been negated. The

owner committed breach of trust of terms of agreement in not

clearing bills of the contractor fortnightly, which was

essence of the contract. The owner did not have sufficient

funds at all material time. It failed to provide lay out of

site. Accordingly, it has been held that the owner committed

breach of trust of contract by not paying running bills

immediately relating to stoppage of work intermittently.

11. The contractor’s claim towards loss in profit due to

reduction in work and towards overhead expenses has also been

rejected. Dismissing the claim of the owner, learned

Arbitrator held that `the claims of the contractor are allowed

to the extent of Rs.50,13,204/- towards the unpaid bills of

the works executed by it, Rs.64,836/- towards the road work

executed and Rs.7,47,577.50/- towards interest on late payment

of the bills.’ It has been further directed that amount of

Rs.50,88,140/- towards unpaid works shall carry interest @ 18%

per annum from 4-6-1996 to 3-10-1999. The amount of

Rs.58,35,717.50/- shall carry interest @ 18% per annum from 4-

10-1999 till the date of realization. Out of 150 shops under

attachment as per the order of the Supreme Court, 50 shops to

remain under attachment till amount awarded is paid in full by

the owner. The owner shall pay the following costs:-

(i) Towards arbitrators fees paid by the
contractor
Rs.2,35,000.00

(ii) Towards arbitrators travelling
expenses borne by the contractor Rs.8,245.00

(iii) Diet money of 2 witnesses of the
contractor Rs.10,000.00

(iv) Lawyer’s fees Rs.5,00,000.00
_________________
Total Costs:

Rs.7,48,245.00

12. The appellant filed an application under Section 34 of

the Act, 1996 before the District Judge. Respondent No.1

submitted their reply along with preliminary objections.

Learned trial Court on the basis of pleadings of the

respective parties framed 12 issues on 28th June, 2001.

Respondent No.1 also moved an application under Order 14 Rule

2 of the CPC to recast the issue No.11 and decide the same as

preliminary issue. However, prayer was rejected vide order

dated 25-1-2002. Respondent No.1 preferred civil revision

against the above order and the same was disposed of vide

order dated 13-2-2007 with a direction to the trial Court to

decide issue No.11 as preliminary issue. After hearing the

parties, it was further directed to pass judicial order with

regard to striking off issue Nos.1 to 10 framed by the trial

Court and to frame other issues as proposed by the respondent.

13. Learned District Judge by the impugned order dismissed

the petition of the appellant under Section 34 read with

Section 13 (5) of the Act, 1996 with a following findings:-

“The Supreme Court appointed sole arbitrator
for adjudication of the dispute between the
parties with their consent. The Supreme
Court is competent to pass any order for
adjudication of any dispute in the interest
of justice under Article 142 of the
Constitution of India and the award passed by
the arbitrator can be challenged on any of
the grounds mentioned in Section 34 of the
Act, 1996. Since the appellant has not shown
any ground under Section 34 for setting aside
award, their application under Section 34
read with Section 13 (5) of the Act, 1996 is
rejected.”

14. The appellant has impugned the order of the District

Judge on the ground that the lower Court did not follow

direction passed in revision. It did not decide issue No.11

by giving reasons. The application has been dismissed by a

cryptic and non speaking order.

15. Challenging the composition of Arbitral Tribunal, it was

argued that though the appellant did not raise any objection

before the Arbitral Tribunal, but composition was challenged

under Section 34 of the Act, 1996. Arbitral Tribunal derives

a jurisdiction from the arbitral agreement (Section 7 of the

Act). The appointment of arbitrator should be in consonance

with the provisions of Chapter-III of the Act, where

composition is not in accordance with law, the same can be

challenged under Section 34 of the Act, 1996. Relying on

various judgments of the Hon’ble Supreme Court, it was

vehemently argued that the arbitrator could not be appointed

contrary to the statute, more particularly against a party

which was not before it thereby causing injustice to such

party; where there is inherent lack of jurisdiction in

composition of arbitral tribunal and objections, even if were

not raised before the arbitrator and the parties submitted to

jurisdiction of arbitrator, the dispute can be raised by way

of petition under Section 34 as it is well settled that there

is no estoppel against the statute.

16. Referring to paragraph 47, page 91 and 94 and further

referring to page 108, end of para-49 of the award, it was

argued that the arbitrator after recording a finding that the

respondent received aggregate sum of Rs.3,05,762,37/- deducted

only Rs.2,97,91,231/- on the basis of last bill submitted and

awarded sum of Rs.50,13,204/-. By deducting the actual amount

already paid, the balance would be Rs.42,28,204/- and not

Rs.50,13,204/-.

17. Challenging imposition of interest @ 18% from the date of

dispute, it was argued that it is highly excessive and against

the terms of contract, the same is in violation of Section 31

of the Act, 1996. The Tribunal also ignored that due to

attachment of 150 shops, the appellant was deprived of rental

income, 50 shops are still attached and the appellant is

deprived of rental income from the attached shops. The

arbitrator has awarded interest under the head of loss of

profit and further awarded interest @ 18% from 4-10-99 on the

above amount and thereby awarded interest on interest which is

not permissible. There is no stipulation for charging of

interest at any stage in the agreement. Respondent No.1 has

also been awarded excessive amount towards costs and a sum of

Rs.5 lakhs has been awarded towards counsel fee.

18. On the other hand, Shri B.P. Sharma, learned counsel

appearing for respondent No.1 submitted that from perusal of

the record of the District Judge, it would be evident that the

matter was fixed for final hearing. The parties were given

sufficient opportunity to file their written arguments. Though

the appellant submitted written argument in part, however, the

matter was argued at length on merits by counsel representing

both the parties. In the Act of 1996, the Court’s power to

interfere with the arbitration proceedings has been curtailed

and the emphasis is on minimizing the supervisory role of

Courts in arbitral process. During the proceedings for

setting aside arbitral award, it is not necessary to allow the

parties to lead evidence after framing issues because the

matter is to be adjudicated on the basis of record of the

arbitrator. The respondent herein raised a preliminary

objection before the lower Court that the appellant has taken

benefits of the order passed by the arbitrator and out of 150

shops, which have been ordered to be attached as per the order

of the Hon’ble Supreme Court, 100 shops have been released by

the arbitrator and released shops have been disposed of by the

appellant. Thus, the appellant has taken benefit of award

and, therefore, he cannot be permitted to question validity of

the award. Though this issue has been answered by learned

District Judge against the respondent herein, but the error

apparent in the finding of learned District Judge can be

rectified by exercise of power under Order 41 Rule 33 of the

CPC.

19. Referring to Section 34, it was argued that the award can

be set aside under Section 34 only in the contingency where

the party making application furnishes proof of conditions (i)

to (v) of Section 34 (2)(a) and secondly, when the Court finds

that (1) the subject matter of the dispute is not capable of

settlement by arbitration under the law for the time being in

force or (2) the arbitral award is in conflict with the public

policy of India.

20. From perusal of the entire objection, it would be evident

that no such ground has been taken which comes within the

purview of Section 34 (2)(a) or (b). As per Section 31 (7)

(a) & (b), the arbitrator has jurisdiction to grant interest

as it deems reasonable. Section 7 (b) of the Act recognizes

grant of 18% per annum, therefore, even if the award does not

impose any interest, the person in whose favour the award is

passed shall be entitled to interest @ 18% per annum from the

date of award till the date of payment and thus, imposition of

interest @ 18% will not be against public policy.

21. We have heard learned counsel for the parties. We have

perused the material available on record including the award

passed by the Arbitral Tribunal. We have also perused grounds

taken by the appellant in application under Section 34,

preliminary objections taken by the respondent herein against

the maintainability of the application; the order passed by

this Court in civil revision preferred by the respondent

herein as also the impugned judgment.

22. Learned counsel for the appellant has mainly challenged

the composition of the Arbitral Tribunal. Relying upon

various judgments of the Hon’ble Supreme Court, it was

vehemently argued that the arbitration agreement provided for

reference of dispute to 2 arbitrators, one to be appointed by

each of the parties and, therefore, reference of dispute to

the sole arbitrator is contrary to the arbitration agreement.

By the Special Leave Petition before the Supreme Court,

challenge was made to the order of the High Court of Madhya

Pradesh passed in reference to proceedings under Section 145

and 146 of the Code, monetary claims and counter claims of the

parties was not the subject matter in the SLP, however, the

arbitrator by the impugned award has adjudicated the monetary

claims of the respective parties, which is wholly beyond the

order of reference and outside the jurisdiction and is liable

to be set aside. The parties before the Supreme Court had no

authority to agree upon an arbitrator or to refer the matter

or dispute between the firms to arbitration.

23. On due consideration of the above arguments, we are of

the considered opinion that learned District Judge has rightly

rejected the objection regarding composition of the Arbitral

Tribunal, as the Supreme Court after recording the consent of

the respective parties has referred the dispute to sole

arbitrator for adjudication of the dispute. The appellant at

no point of time challenged the composition of the Arbitral

Tribunal either before the Hon’ble Supreme Court or before the

Arbitral Tribunal during arbitral proceedings. On the

contrary, they participated in the proceedings, denied claims

of respondent No.1 and also submitted counter claim. The

objection in this regard was taken for the first time in

application under Section 34 of the Act, 1996 before the

District Judge, we are of the considered opinion that neither

the District Judge nor this Court can entertain and consider

any objection/challenge to the constitution of Arbitral

Tribunal by the Hon’ble Supreme Court. It is settled law that

Article 142 of the Constitution confers undefined, un-

catalogued and extraordinary power unrestricted by ordinary

laws. The legality, validity and correctness in exercise of

power under Article 142 of the Constitution cannot be

questioned before this Court.

24. The other ground taken by the appellant to challenge the

award is that the award is against the Public Policy.

Referring to para-47 of the Award, it has been argued that

after recording receipt of aggregate sum of Rs.3,05,762,37.00

by respondent No.1, deduction of only Rs.2,97,91,231 was made

on the basis of last bill and accordingly awarded a sum of

Rs.50,13,204/- instead of Rs.42,28,204/-. It has been further

argued that the arbitrator has awarded interest under the head

of loss of profit @ 18% per annum on the amount of

Rs.50,88,140/- towards the unpaid works from 4-6-96 to 3-

10-99 and it has been further directed that the amount so

calculated to carry interest @ 18% per annum from 4-10-99 and

thereby awarded interest on interest, which is not

permissible.

25. Learned counsel for the appellant submitted that the rate

of interest is highly excessive, as a long spell of time has

expired since the date of award. Granting interest @ 18% per

annum is burdensome for the company, therefore, interest

should be suitably reduced.

26. It is true that learned District Judge has not literally

complied with the direction issued by this Court in civil

revision, the suit has been dismissed without adverting to the

objections raised by the appellant against the award even

after deciding issue No.11 against the respondent herein,

however, on the merits of the claim made by the contractor, we

find from the impugned award dated 3rd October, 1999 that the

arbitrator has meticulously examined claims of the contractor

under each separate head. We also find that his claim against

certain heads has been rejected whereas, under the other heads

it has been allowed by a reasoned order. The arbitrator has

arrived at its conclusion on the basis of detailed marshalling

of pleadings and evidence adduced by the respective parties,

though we find that there is some calculation mistake and

discrepancy towards the deduction of the amount received by

the respondent herein, however, the same could be brought to

the notice of the arbitrator himself, who could correct the

said mistake in exercise of power under Section 33 of the Act,

1996. We do not see any reason to interfere on the quantum of

award passed by the learned arbitrator.

27. However, considering the fact that long spell of time has

expired since the date of award, the appellant has been

deprived of the possession of 50 shops since 1999 and also

considering that the rate of interest prevailing in the

country has substantially reduced, further taking into

consideration the peculiar facts and circumstances of the

case, we are of the opinion that interest awarded by the

arbitrator @ 18% per annum for the post award period be

reduced to 9%.

28. Accordingly, the appeal is allowed to the extent

indicated above.

  J U D G E                                 J U D G E