High Court Kerala High Court

E.V.M.Fuels (P) Ltd vs Guruvayoor Municipality on 2 July, 2008

Kerala High Court
E.V.M.Fuels (P) Ltd vs Guruvayoor Municipality on 2 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 12437 of 2008(E)


1. E.V.M.FUELS (P) LTD, REGISTERED OFFICE,
                      ...  Petitioner

                        Vs



1. GURUVAYOOR MUNICIPALITY, REP.BY ITS
                       ...       Respondent

                For Petitioner  :SRI.RENJITH THAMPAN

                For Respondent  :SRI.K.K.CHANDRAN PILLAI

The Hon'ble MR. Justice ANTONY DOMINIC

 Dated :02/07/2008

 O R D E R
                         ANTONY DOMINIC, J.

              --------------------------------------------------------

                        W.P.(C) 12437 of 2008

              --------------------------------------------------------

                          Dated: JULY 2, 2008

                                 JUDGMENT

The prayer sought for in this writ petition is to direct the

respondent to accept the completion report as regards the

building constructed pursuant to Exts.P2 and P3 and to number

the same.

2. It is stated that on the strength of Ext.R1(a) exemption

order passed by the Government of Kerala exercising its powers

under the Kerala Building Rules, 1994, on 23.10.1997 Ext.P2

building permit was granted to the predecessor-in-interest of the

petitioner. Petitioner submits that on the strength of Ext.P2

permit, a special residential building consisting of apartments,

having a total plinth area of 28000 square feet was to be

constructed and completed by 22.10.2000. It is stated that his

predecessor could not complete the construction in all respects

within the time allowed and therefore had sought extension of

the time specified in the permit twice. The extensions sought for

were granted and the extended period was upto 22.10.2006.

Ext.P3 is the last order of extension and endorsements on

WP(C) 12437/08 2

Ext.P2 also show the extensions granted to the predecessor-in-

interest of the petitioner.

3. According to the petitioner, on the strength of Ext.P2

and within the extended period, the entire civil work including

plastering of the building was completed, and what remained to

be done is fixing of Belgium glass on the front portion of the

building. Petitioner submits that in the meanwhile, on account

of financial crisis, his predecessor-in-interest had sold the

property to the petitioner, in as is where is condition, with effect

from 21.7.2006. According to the petitioner, on completion of

the work as above, he applied to the Municipality for numbering

the building and the Municipality replied stating that only if the

permit is current, the building in question could be numbered.

4. Thereupon, the petitioner had applied to the

Municipality for extension of period of the building permit. In

the meanwhile, Kerala Municipality Building Rules 1984 were

replaced by the Kerala Municipality Building Rules 1999. The

application made by the petitioner for extension was forwarded

by the Municipality to the Government under the cover of Ext.P4

dated 10.4.2007. In this communication of the Municipality

also it is mentioned that most the work in terms of the permit

WP(C) 12437/08 3

was already completed. However, on receipt of Ext.P4, the

Government replied by Ext.P5 stating that in terms of the 1999

Rules, it was not practical to extend the period of the permit.

On that basis the Municipality was directed to treat the

petitioner’s application as one filed under the 1999 Rules and

take action as if it is a fresh application. Accordingly, the

Municipality considered the application of the petitioner as a

fresh one in the light of the 1999 Rules, ignoring Ext.R1(a)

exemption. On such examination the Municipality found several

violations of the 1999 Rules and on that basis, by Ext.P6

informed the petitioner that his application cannot be

considered. It is on receipt of Ext.P6 that this writ petition was

filed by the petitioner seeking a direction to the Municipality to

accept the completion report and number the building.

5. Learned counsel for the petitioner mainly contends that

since even according to the Municipality, a substantial portion of

the work was completed, the petitioner should be allowed to

make use of the building as otherwise the building having 28000

sq. ft. of plinth area cannot be made use of at all and will be a

total waste of money and effort. It is also his contention that

Ext.P2 having been granted under the 1984 Rules, the extension

WP(C) 12437/08 4

sought for by him, should also be considered in the light of the

said rule and not the 1999 Rules.

6. The Municipality on its part had filed a counter affidavit.

According to the Municipality, on every respect the construction

is in violation of the Rules. They would say that the very permit

was granted on the strength of an order of exemption and that

now as the petitioner’s application is to be considered in the light

of the 1999 Rules, compliance with those Rules is an essential

pre-requisite. The Municipality, therefore, would submit that

its stand that the application cannot be considered is legal and

correct.

7. The contention of the petitioner that the entire civil

works including plastering was completed before the expiry of

the extended period of the permit is also denied by the

Municipality. The Municipality submits that the transfer in

favour of the petitioner was not intimated to it either by the

petitioner’s predecessor-in-interest or by the petitioner himself

and that without any permit petitioner continued the work

leading to the issue of stop memo and, on its disobedience, a

police complaint as well.

8. From the facts noticed above it is evident that as at

WP(C) 12437/08 5

present, the building having a plinth area of 2800 sq. ft. has been

completed either by the predecessor-in-interest or the petitioner

himself on the strength of Ext.P2 building permit. The fact that

the construction was undertaken on the basis of Ext.P2 and was

allowed to continue until 22.10.2006 on which date the extended

period of the permit expired is also not disputed. It is also to be

noticed that the Municipality has not initiated any coercive

action against the structure constructed by the petitioner. As

already noticed, even according to the Municipality, a substantial

portion of the work was completed as is mentioned by it in

Ext.P4 letter issued on 10.4.2007. Now, therefore, a workable

solution will have to be found out to make use of the building,

permitting the petitioner to complete the remaining part of the

work and make use of the same. I feel, the only option is to

permit the petitioner to complete the work and accept the

completion certificate and issue occupancy certificate on that

basis after completing necessary formalities.

9. Since, according to the petitioner, the building in

question has been completed and what remains is only fixing of

Belgium glasses, I feel the ends of justice require that the writ

petition shall be disposed of with the following directions:-

WP(C) 12437/08 6

i. The Respondent Municipality shall inspect the building

in question and ascertain as to whether the construction

undertaken is in compliance with Ext.P2 permit.

ii. If the construction undertaken by the petitioner thus

far is found to be in compliance with Ext.P2 permit, the

petitioner will be permitted to complete the remaining

works without in any manner departing from Ext.P2 or

increasing the built up area of the building in question.

iii. Once the remaining work is completed as above,

petitioner will submit the completion certificate to the

Municipality.

iv. On receipt of the completion certificate as above, the

Municipality shall again inspect the building and after

completing necessary formalities, issue occupancy

certificate to the petitioner.

Writ petition is disposed of as above.

ANTONY DOMINIC
JUDGE

mt/-