High Court Kerala High Court

Geo-Tech Construction Company … vs Kerala State Construction … on 11 April, 2008

Kerala High Court
Geo-Tech Construction Company … vs Kerala State Construction … on 11 April, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 29878 of 2002(F)


1. GEO-TECH CONSTRUCTION COMPANY PVT.LTD.,
                      ...  Petitioner

                        Vs



1. KERALA STATE CONSTRUCTION CORPORATION,
                       ...       Respondent

2. GENERAL MANAGER,

                For Petitioner  :SRI.M.K.DAMODARAN (SR.)

                For Respondent  :SRI.M.V.THAMBAN

The Hon'ble MR. Justice P.N.RAVINDRAN

 Dated :11/04/2008

 O R D E R
                        P.N.Ravindran, J.
                      =============
                     O.P.No.29878 of 2002
                     ===============

            Dated this the 11th day of April, 2008.

                           JUDGMENT

The petitioner is a company incorporated under the

Companies Act, 1956.

2. In the year 1998, the State Government decided to make

Sultan Canal having a length of 3.85 kms, which connects

Kuppam river in the south and Palakode river in the north,

navigable. The work envisaged dredging of the entire length of

the canal and side protection for a length of 1100 mts. using RCC

piles and slabs. By G.O.(Rt)No.16/98/CSIND dated 6.8.1998, the

State Government granted revised administrative sanction for the

work and entrusted the work to the Kerala State Construction

Corporation, hereinafter referred to as the “Corporation” for

short, with permission to get the work executed through sub

contractors. The Corporation thereupon entered into an

agreement dated 2.9.1998 with the Superintending Engineer,

Irrigation Circle, Kozhikode. The site of the work was handed

OP 29878/02 -: 2 :-

over to the Corporation on 24.9.1998 and the work had to be

completed within five months therefrom. The Corporation sub-

contracted the work to the petitioner.

3. While the work was in progress, it was found necessary

to carry out some additional works and the Chief Engineer

sanctioned a revised estimate of Rs.3,25,73,061/- vide order

dated 30.7.2004. As the Corporation could not complete the

work in time, the Superintending Engineer, Irrigation Circle,

Kozhikode granted extension of time upto 15.5.2000 imposing a

fine of Rs.1,30,333/-. In the meanwhile the State Government

decided to take up Phase II of the work of improving the Sultan

Canal and by G.O.(Rt) No.3/2000/CSIND dated 27.1.2000 the

State Government granted administrative sanction for the said

work. Thereupon Phase II of the work was awarded to the

Corporation. The Corporation sub-contracted the said work also

to the petitioner.

4. The petitioner has in this original petition contended that

it has completed the work in both the phases and that as per

Ext.P6 bill prepared by the officers of the Corporation Rs.50.55

lakhs is due to it in respect of Phase I and Rs.23.76 lakhs is due

OP 29878/02 -: 3 :-

to it in respect of Phase II. The petitioner has also claimed

interest on the said amounts at 18% per annum. The petitioner

relies on Ext.P11 certificate dated 31.1.2006 issued by the

Superintending Engineer, Irrigation Circle, Kozhikode wherein the

said officer had certified that Phase I of the work awarded to the

Corporation as per the agreement dated 2.9.1998 has been

carried out according to the specifications and completed

satisfactorily. Ext.P11 further states that no noticeable defects

were found during inspection. The petitioner also relies on

Ext.P12 certificate dated 24.3.2001 issued by the Regional

Manager of the Corporation at Kannur to the effect that the work

awarded to the petitioner has been completed within the agreed

time of completion. The grievance put forward by the petitioner

in this original petition is that though the work awarded to it by

the Corporation has been completed, the money due and payable

for the work done has not been disbursed. The petitioner has in

this original petition prayed for the following reliefs:

“i. Issue a writ of mandamus or other

appropriate writ order or direction directing

respondents to pay to the petitioner the amounts due

OP 29878/02 -: 4 :-

under Ext.P1 to P4 and demanded under Ext.P6

forthwith along with interest at the rate of 18% per

annum from the date of Exts.P1 to P4.

ii) Issue a writ of mandamus or other

appropriate writ order or direction directing

respondents not to effect any payment to any

contractor without first paying the dues of the

petitioner covered by Exts.P1 to P4 and demanded

under Ext.P6.”

5. In the counter affidavit filed on behalf of respondents 1

and 2 it is contended that the petitioner has not completed the

work and therefore, the work had to be rearranged and got done

through other contractors. It is also submitted that the final

settlement of accounts between the parties can be had only after

the work is completed and the expenditure involved and the loss

sustained by the Corporation are assessed. As regards Phase I of

the work, it is submitted that the petitioner did not complete the

work within the agreed time frame of 152 days from 10.8.1998.

As regards Phase II, it is submitted that the petitioner did not

complete the work before 15.12.2000. The counter affidavit

proceeds to state that the petitioner has committed breach of the

contract and that final settlement of the accounts can be arrived

OP 29878/02 -: 5 :-

at only after the loss sustained by the Corporation for re-

arranging the work through other contractors is estimated and

assessed. The Corporation also contends that this original

petition filed under Article 226 of the Constitution seeking

payment for the work done is not maintainable.

6. When the original petition came up for hearing on

14.3.2004, this Court on noticing that there is conflict between

the counter affidavit filed on behalf of the Corporation and the

completion certificate evidenced by Ext.P12, passed the following

order:

“Secretary to Govt., Dept. of Irrigation,

Trivandrum, is made addl. respondent. Since there

is direct conflict between the counter affidavit filed by

the General Manager of the first respondent, which is

a Govt. Corporation and the completion certificate,

Ext.P12, issued by the Regional Manager, Kannur of

same company, I direct the addl. respondent

(Secretary to Govt.) to conduct enquiry and file a

counter affidavit in this court within ten days from

now stating as to who and what is correct. If the

Secretary finds that there is foul play or manipulation

by any official of the Govt. Corporation, he will order

vigilance enquiry and report the matter to this

OP 29878/02 -: 6 :-

Court.”

7. Pursuant to the said direction, the Director of Inland

Navigation, issued Ext.P13 letter to the General Manager of the

Corporation and the Managing Director of the petitioner

company calling upon them to appear before him on 18.6.2007

for a personal hearing. Ext.P14 discloses that there was also a

joint inspection of the work site on 28.6.2007.

8. As directed by this Court in the order passed on

14.3.2007, referred to above, the Principal Secretary to

Government, Water Resources Department filed an affidavit

dated 6.9.2007 stating that the Chief Technical Examiner has

after conducting an enquiry submitted a report recommending

vigilance enquiry. A copy of the report is produced as Ext.R1(a)

along with the said affidavit. It is also stated that in the light of

the opinion of the Chief Technical Examiner, the Government

have already ordered a vigilance enquiry in the matter and that it

is underway. On an application filed by the petitioner as

I.A.No.3212 of 2008, I had by order passed on 7.3.2008 directed

the third respondent to produce the report submitted by the

Director of Inland Navigation pursuant to the inspection

OP 29878/02 -: 7 :-

conducted by him on 28.6.2007. Though the report submitted by

the Director of Inland Navigation has been placed on record along

with a memo dated 14.3.2008 filed by the learned Government

Pleader Sri.K.Sandesh Raja, the learned Government Pleader

appearing for the third respondent submitted that the

Government have not accepted the said report and that in view

of the report submitted by the Chief Technical Examiner, no

reliance can be placed on the said report.

9. I heard Sri.M.K.Damodaran, the learned senior counsel

appearing for the petitioner, Sri.M.V.Thamban, the learned

counsel appearing for respondents 1 and 2 and Sri.K.Sandesh

Raja, the learned Government Pleader appearing for the third

respondent. Sri.M.K.Damodaran, the learned Senior Counsel

appearing for the petitioner contended with reference to Exts.P11

and P12 and the report submitted by the Director of Inland

Navigation pursuant to the joint inspection held on 28.6.2007

that the work has been completed in all respects and therefore

the Corporation is not justified in withholding payment. The

learned senior counsel for the petitioner submitted that at least

as regards Phase I, the Corporation cannot have any objection for

OP 29878/02 -: 8 :-

the reason that Ext.P11 certificate is issued by the agreement

authority, namely, the Superintending Engineer. The learned

senior counsel submitted that the Superintending Engineer,

Irrigation Circle, Kozhikode has in Ext.P11, certified that Phase I

of the work has been carried out according to the specifications

and has been completed satisfactorily and that no noticeable

defects were found on inspection. The learned Senior Counsel for

the petitioner also relied on the report submitted by the Director

of Inland Navigation to contend that the findings therein entitle

the petitioner to claim the reliefs sought in this original petition.

10. Sri.M.V.Thamban and Sri.K.Sandesh Raja, the learned

counsel appearing for the respondents submitted that in the light

of the findings in the report submitted by the Chief Technical

Examiner and the State Government’s decision to order a

vigilance enquiry into the matter, the petitioner is not entitled to

any relief in this original petition. They also contended that the

contract in the case on hand is not a statutory contract and

therefore this original petition filed under Article 226 of the

Constitution seeking payment for the work is not maintainable.

The learned counsel appearing for the respondents also

OP 29878/02 -: 9 :-

submitted that in view of the report submitted by the Chief

Technical Examiner, no reliance can be placed on the report

submitted by the Director of Inland Navigation.

11. I have considered the rivalcontentions. The Chief

Technical Examiner has in his report dated 22.9.2007 [Ext.R3(a)]

observed as follows:

“2. The completion certificate issued by the

Regional Manager, KSCC, Kannur is also not found

bonafide as explained in paras 1,2,3,4,75.

3. As explained in para 6 it is noted that

proportionate amount has not been transferred to

M/s. Geo Tech by KSCC for the work executed.

4. The Chief Engineer has already reported that

the work in total has not yet been completed which

was found to be true in site inspection as explained in

para 2.2.

5. In view of all the above facts, a detailed

Vigilance Enquiry into the execution of the above

work as advised by the Hon’ble High Court may be

considered to bring out any foul play or manipulation

and also to fix the responsibility.”

12. The report submitted by the Chief Technical Examiner

discloses that it was prepared after enquiry and site inspection.

OP 29878/02 -: 10 :-

The Chief Technical Examiner has in paragraph 2 thereof noticed

irregularities in the execution of the work. He has also expressed

a doubt as to whether canal would be navigable. He has also

noticed overlapping of the dredging work. The Chief Technical

Examiner has reported that the work in total has not been

completed and that the report in that regard submitted by the

Chief Engineer is true. The Chief Technical Examiner has in view

of his observations and findings recommended a detailed

vigilance enquiry into the execution of the work awarded by the

Corporation to the petitioner. This Court had in the order passed

on 14.3.2007 directed that if the Secretary to Government finds

that there is foul play or manipulation by any official of the

Government/ Corporation, he will order vigilance enquiry into the

matter. The State Government has accordingly ordered a

vigilance enquiry and it is in progress. In that view of the matter

and having regard to the findings in Ext.R3(a) report submitted

by the Chief Technical Examiner, I am of the considered opinion

that at this stage, no relief can be granted to the petitioner. It is

certainly not in public interest to direct payment for the work

done, when there is serious dispute between the parties as

OP 29878/02 -: 11 :-

regards the question whether the work has been completed and if

so, whether it was done in terms of the agreement. The work

was awarded by the State Government to the Corporation and by

the Corporation in turn to the petitioner to render Sultan Canal

navigable. Therefore, the work in question is of considerable

public importance. In these circumstances, I hold that the

petitioner is not entitled to any relief in this original petition.

However, I am of the opinion that the vigilance enquiry cannot be

unduly delayed. I had during the course of hearing ascertained

from the learned Government Pleader the time frame required for

completing the vigilance enquiry. Sri.K.Sandesh Raja, the learned

Government Pleader appearing for the third respondent

submitted that the State Government would require a minimum

period of one year to complete the vigilance enquiry. Having

regard to the fact that the work is of considerable public

importance and the fact that any delay in completing the

vigilance investigation will be detrimental to public interest, I

direct the State Government to take such steps as are necessary

to complete the vigilance enquiry within six months from today.

I make it clear that I have not pronounced upon the entitlement

OP 29878/02 -: 12 :-

of the petitioner to receive payment for the work done. It will be

open to the petitioner to initiate other appropriate proceedings

seeking for payment for the work done after the vigilance enquiry

is completed.

Subject to the above observations, this original petition is

dismissed. No costs.

P.N.Ravindran,
Judge.

ess 2/4