High Court Kerala High Court

A.K.G. Memorial Labour Contract vs The Director on 27 January, 2009

Kerala High Court
A.K.G. Memorial Labour Contract vs The Director on 27 January, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 28299 of 2008(R)


1. A.K.G. MEMORIAL LABOUR CONTRACT
                      ...  Petitioner

                        Vs



1. THE DIRECTOR,
                       ...       Respondent

2. THE JOINT DIRECTOR,

3. THE MANAGER,

                For Petitioner  :SRI.K.MOHANAKANNAN

                For Respondent  : No Appearance

The Hon'ble MR. Justice ANTONY DOMINIC

 Dated :27/01/2009

 O R D E R
                        ANTONY DOMINIC, J.
                   -------------------------
                    W.P.(C.) No.28299 of 2008
             ---------------------------------
             Dated, this the 27th day of January, 2009

                           J U D G M E N T

The petitioner is challenging Ext.P7 and seeks a direction to

respondents 1 & 2 to release payment due under Exts.P1 & P2.

Records would show that the petitioner was awarded the contract of

garden maintenance and beautification at Guest House, Sultan

Bathery during the period from 10/08/2007 to 09/08/2008. The

petitioner states that during that period they had executed the work

in discharge of his contractual obligations, and that Exts.P1 & P2

bills submitted by him were recommended for payment, by the 3rd

respondent to the 2nd respondent. It is stated that the payment was

not made, and as a result of which, the petitioner could not engage

it’s workers due to non-availability of funds for payment of wages.

2. According to the petitioner, claiming payment he made

Exts.P4 & P5 representations and that as there was no response to

these representations, Ext.P6 notice was issued on its behalf. To

Ext.P6, the petitioner got Ext.P7 reply, where it was inter alia stated

that the contract was terminated with effect from 13/02/2008. The

petitioner complains that all the statements in Ext.P7 are incorrect.

WP(C) No.28299/2008
-2-

It is also contended that before terminating the contract with effect

from 13/02/2008, the petitioner was not given even a notice.

3. Though the learned Government Pleader raised dispute

about the nature of the performance of the work by the petitioner,

admitted position is that, before terminating the contract awarded

to the petitioner, no notice was issued to them. In my view, the

respondents ought to have issued notice to the petitioner before

terminating the contract and therefore, the termination of the

contract is clearly violative of the Principles of Natural Justice.

Therefore, the termination of the contract awarded to the petitioner

is set aside and the 1st respondent is directed to give notice to the

petitioner, give it an opportunity to make their representation in the

matter and thereafter, decide on the issue of cancellation of the

contract awarded to the petitioner.

4. The 1st respondent shall also take a decision on the

monetary claims of the petitioner made as per Exts.P1 & P2.

5. This shall be done as expeditiously as possible, at any

rate, within six weeks of production of a copy of this judgment.

The writ petition is disposed of as above.

(ANTONY DOMINIC, JUDGE)
jg