Bombay High Court High Court

Acting Through The Divisional vs M/S. Jeevat Construction on 26 November, 2009

Bombay High Court
Acting Through The Divisional vs M/S. Jeevat Construction on 26 November, 2009
Bench: Anoop V.Mohta
    SRJ arbp-80-09.sxw                    1

               IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                   ORDINARY ORIGINAL CIVIL JURISDICTION




                                                                        
                    ARBITRATION PETITION NO.80 OF 2009

    Union of India                            ]




                                                
    Acting through The Divisional             ]
    Railway Manager (WA), Western             ]
    Railway, Mumbai Central,                  ]
    MUMBAI.                                   ]..    Petitioners




                                               
                 V/s.

    M/s. Jeevat Construction                  ]
    4, Manik Smuruti, 16th Road,              ]
    Khar (W), Mumbai 400 052.                 ]..    Respondents.




                                    
                         
    Mr.Suresh Kumar for Petitioners.

    Mr. U.S.Samudrala for Respondents.
                        
                                      CORAM : ANOOP V. MOHTA,J.
                                      DATE : 26th NOVEMBER,2009.
      
   



    JUDGMENT:

1. Heard Finally.

2. The learned counsel appearing for the

Respondents on instructions, submits that the

Respondents are not pressing claim no.2 of security

deposit and claim no.10 about interest on the work

done payment. The Petitioner has challenged the same

only. In view of this, I am inclined to modify the

award to the above reasons. In view of the judgments

of Hon’ble Supreme Court, whereby the Hon’ble Supreme

Court has observed and in fact modified the awards

under section 34 of the Arbitration and Conciliation

::: Downloaded on – 09/06/2013 15:20:50 :::
SRJ arbp-80-09.sxw 2

Act,1996 (for short “Act”). The Hon’ble Supreme Court

in the matter of Delhi Development Authority v/s.

R.S.Sharma and Company, New Delhi (2008) 13 Supreme

Court Cases 80 has maintained the modified award. Even

otherwise, there is no bar under section 34 of the Act

to modify the award in situation like where the

parties themselves not pressing the claim. Now at this

particular point, it is difficult for Court to deny

the modification and delay the proceedings further by

quashing the award solely on this ground. The early

disposal is main object of the said Act.

3. In view of this, I am inclined to modify the

award as observed above. The claim no.2 and claim no.

10 are disposed off as not pressed.

4. With regard to the Counter Claim, there is a

clear finding on the Counter Claim of the Petitioner

as given in paragraph 6.2 which is reproduced

hereunder:-

                    The    Claimants      stated      that





               Respondent    did     not    submit     any

documentary proof & the details of
break up of said claims. The Claimant
requested payment of second running
bill but the Respondents did not pay
and therefore they could not be
carrying out the work. As such the
Respondent committed the breach by
termination of the contract.

Respondent s right to claim risk and
cost stands forfeited as per 64 of
Indian Contract Act.

::: Downloaded on – 09/06/2013 15:20:50 :::
SRJ arbp-80-09.sxw 3

5. Considering the rival contentions as well as

the reasonings so given, I see that there is nothing

to interference in the proceedings. It is well

established within the frame work of law. The award

now modified as agreed to the extent of clause item

nos. 2 and 10 as referred above and the rest of the

award as well as reasonings are maintained.

6. The Petition is accordingly disposed of.

7. No costs.

(ANOOP V. MOHTA, J. )

::: Downloaded on – 09/06/2013 15:20:50 :::