High Court Kerala High Court

Bharath Sanchar Nigam Ltd vs Executive Engineer on 10 December, 2007

Kerala High Court
Bharath Sanchar Nigam Ltd vs Executive Engineer on 10 December, 2007
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C) No. 29048 of 2007(G)


1. BHARATH SANCHAR NIGAM LTD.,
                      ...  Petitioner

                        Vs



1. EXECUTIVE ENGINEER,
                       ...       Respondent

2. ASSISTANT ENGINEER (ELECTRICAL MAJOR

3. ASSISTANT ENGINEER,

                For Petitioner  :SRI.C.S.RAMANATHAN, SC, BSNL

                For Respondent  :SRI.P.P.THAJUDEEN, SC, K.S.E.B

The Hon'ble MR. Justice C.N.RAMACHANDRAN NAIR

 Dated :10/12/2007

 O R D E R
                      C.N.RAMACHANDRAN NAIR, J.

                            -------------------------

                         WP(C) No. 29048 of 2007

                       ---------------------------------

             Dated, this the 10th day of December, 2007


                                 J U D G M E N T

This writ petition is filed against disconnection of electricity

supply to the telephone exchange operated by BSNL. Pursuant to

interim order issued by this Court, learned standing counsel

produced the order issued by the Assistant Engineer finalising the

proposed demand issued based on the findings of APTS during their

inspection. If the allegation that one phase of the meter was not

working is correct, then the proposed additional bill is justified.

However, learned counsel for the petitioner submits that even after

connecting all the phases, the bills are the same as received by the

BSNL for the period prior to detection of the problem by APTS. If

the bill amount is the same, even after replacement of the meter

after inspection, then petitioner’s denial of allegation that one phase

of the meter was not working may be true. In the circumstances,

and since appeal is provided under Section 127 against the bill so

finalised by the Assistant Engineer, this writ petition is disposed of

directing the petitioner to file appeal before the Deputy Chief

Engineer, Electrical Circle, Thiruvananthapuram (Urban) within a

period of one month from the date of receipt of a copy of this

WP(C) No. 29048/2007

-2-

judgment. If appeal is filed, the Deputy Chief Engineer will call for

the subsequent bills after replacement of the meter and verify the

genuineness of the allegation and pass appropriate orders. The

Deputy Chief Engineer should pass interim orders regarding the

amount payable by the petitioner under the disputed bill for

maintainability of appeal and for stay within a period of two weeks

from the date of filing of appeal. The appeal also should be

disposed of without any delay. Interim orders against disconnection

of electricity supply will continue for a period of two months from

now. In between, the Deputy Chief Engineer should have passed

interim orders for payment or final orders in the appeal. Recovery

or disconnection will be made only if petitioner commits default in

making payment in terms of the Deputy Chief Engineer’s order.

Since Deputy Chief Engineer is given freedom to fix the amount

payable by the petitioner, there will be direction to the Deputy Chief

Engineer not to insist on payment of more than 50% as a condition

for maintainability of appeal. In other words, it is for him to fix the

amount payable after examining the correctness of the matter,

prima facie.

(C.N.RAMACHANDRAN NAIR, JUDGE)

jg