Central Information Commission Judgements

Shri S.K. Verma vs The Oriental Insurance Company … on 30 January, 2009

Central Information Commission
Shri S.K. Verma vs The Oriental Insurance Company … on 30 January, 2009
                CENTRAL INFORMATION COMMISSION
                              .....

F.No.CIC/AT/C/2008/00251
Dated, the 30th January, 2009.

Complainant : Shri S.K. Verma

Respondents : The Oriental Insurance Company Limited

This complaint has been filed by Shri S.K. Verma (complainant) against
the PIO, Shri Warendra Sinha, Chief Regional Manager, Ghaziabad for delayed
transmission of information in response to complainant’s RTI-application dated
18.02.2008. The brief chronology is as follows:-

    Date                                       Event
 18.02.2008     Complainant filed his RTI-application before the PIO & CRM,
                Ghaziabad
 22.02.2008     Date of receipt of the application by the CPIO
 04.03.2008     CPIO transferred the petition to the holder-of-the-information
                (the public authority's Head Office)
 25.03.2008     Information received by the CPIO from the Head Office
 23.04.2008     Information supplied to the complainant

2. It is seen that there has been a delay of 23 days by PIO, Shri Warendra
Sinha, Chief Regional Manager, Ghaziabad in furnishing his reply.

3. PIO has explained that this delay was not wanton, or mala-fide but was on
account of the fact that the PIO had to obtain instructions from the public
authority’s Head Office regarding transmitting information as requested by the
complainant. This was what caused the delay. It is the PIO’s submission that
this was the first time that he was handling an RTI-application and despite his
best efforts, he could not prevent the delay as the correspondence with the head
office took longer than expected.

4. Considering all submissions in this matter, I’m inclined to agree with the
PIO that the delay in this matter was not on account of any negligence, or due to
deliberate withholding of information. It was mostly on account of the delay in
the completion of process of transmitting to the complainant authentic and
authorized information. In view of this, I do not wish to impose any penalty on
the PIO.

AT-30012009-48.doc
Page 1 of 2

5. Complaint closed.

6. Copy of this decision be sent to the parties.

( A.N. TIWARI )