High Court Kerala High Court

K.P.Mohanan vs Kerala State Electricity Board on 5 October, 2010

Kerala High Court
K.P.Mohanan vs Kerala State Electricity Board on 5 October, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 17929 of 2008(H)


1. K.P.MOHANAN, KADAVATH PURAYIL,
                      ...  Petitioner

                        Vs



1. KERALA STATE ELECTRICITY BOARD,
                       ...       Respondent

2. EXECUTIVE ENGINEER, ELECTRICAL DIVISION,

3. ASSISTANT EXECUTIVE ENGINEER,

4. ASSISTANT ENGINEER, ELECTRICAL SECTION,

5. DEPUTY CHIEF ENGINEER,

6. SPECIAL DEPUTY TAHSILDAR,

7. DEPUTY CHIEF ENGINEER, KSEB,

                For Petitioner  :SRI.P.M.PAREETH

                For Respondent  :SRI.C.K.KARUNAKARAN, SC FOR KSEB

The Hon'ble MR. Justice T.R.RAMACHANDRAN NAIR

 Dated :05/10/2010

 O R D E R
               T.R. RAMACHANDRAN NAIR, J.
                ~~~~~~~~~~~~~~~~~~~~~~~~~~~
                  W.P.(C). No.17929/2008-H
                ~~~~~~~~~~~~~~~~~~~~~~~~~~~

           Dated this the 5th day of October, 2010

                      J U D G M E N T

The petitioner challenges the proceedings Ext.P10 by

which the Appeal Petition filed by him, against the

assessment of unauthorised additional load, has been

rejected confirming the demand.

2. The amount in question, namely, Rs.1,02,724/- plus

surcharge was remitted by the petitioner during the

pendency of the proceedings. Now, what remains is the

claim for refund.

3. It is submitted by the learned counsel for the

petitioner that the petitioner’s Unit is a Small Scale

Industrial Unit with consumer No.18051. Initially,

connected load was 30HP. But the Unit could not start

functioning for various reasons. The petitioner was paying

the monthly minimum current charges in order to maintain

the service connection. The petitioner applied for

additional power allocation and it was granted by providing

15 HP power allocation w.e.f April 2002. A new meter was

installed from 24/03/2003. But, according to him, due to

short circuit it was burnt two days after its improper

W.P.(C). No.17929/2008
-:2:-

fixing. Ext.P2 is the true photograph produced in support

of the above plea. The situation continued till October,

2004. The petitioner paid monthly demands upto February,

2003 and no payment was made from March, 2003 since no

meter was installed after the burning of the same. But, in

April, 2003 the Sub Engineer of the Section inspected the

Unit and reported that there was an additional load of 18HP

and the monthly demand was to be enhanced from Rs.1035/- to

Rs.2205/-. However, no site mahazar was prepared and the

petitioner was not informed of the alleged inspection also.

It is pointed out that even though 40HP motor was kept in

the premises, that was not connected to the mains and the

allocation of the unauthorised connected load is not

correct. Reliance is placed on Ext.P3 a report dated

29/07/2004 submitted by the third respondent to the second

respondent wherein various aspects have been pointed out.

Ext.P4 is the proceedings whereby he was granted additional

power allocation of 15HP. But even after this he could not

commence production because of various problems. According

to the petitioner there was no meter or connection from

April 2003 to September 2004 and at the end of September,

2004 the meter was changed and he is liable to pay the

charges from October, 2004 to May 2005. Ext.P5 is the

W.P.(C). No.17929/2008
-:3:-

demand, which was disputed by him in Ext.P6. It is pointed

out that thereafter, based on an interim order passed by

this Court on 14/10/2008 in this writ petition, an amount

of Rs.1,31,327/- has been paid.

4. Ext.P6 filed before the Consumer Forum was

transferred to the Deputy Chief Engineer in the light of

Section 127 of the Electricity Act, 2003 which resulted in

Ext.P10 Order. The learned counsel for the petitioner

submitted that all the points raised by the petitioner have

not been considered in Ext.P10. It is pointed out that the

allocation of the unauthorised connected load is not

correct. The Deputy Chief Engineer has accepted the

contentions of the concerned officers without verifying the

real facts. My attention was invited to Regulation 27A(4)

(i) of the Kerala Electricity Supply Code, 2005 which

provides as follows:-

“In case of prejudicial use of power supply,

the Licensee should draw mahazar at the time of

inspection when such prejudicial use is detected.

The mahazar shall be drawn in the presence of the

Consumer or his representative along with two

other witnesses who shall sign the mahazar

report. One copy of such report shall be handed

W.P.(C). No.17929/2008
-:4:-

over under acknowledgment of the Consumer or his

representative.”

The learned counsel for the petitioner submitted that this

is a mandatory process even under the earlier regulations,

and the absence of mahazar vitiates the order itself.

5. Whether there was any unauthorised connected load

has to be assessed only on the basis of the materials. The

Deputy Chief Engineer has really presumed that there was an

unauthorised connected load whereas the petitioner

maintains the stand that the 40HP motor was never used.

Herein, the report, Ext.P3 is relevant. It is not clear

from the order Ext.P10 whether the report was available

before the Deputy Chief Engineer.

6. The respondents have filed a counter affidavit

supporting Ext.P10 order.

7. The learned counsel for the petitioner submitted

that as the relevant materials have not been considered by

the Deputy Chief Engineer, the order cannot be supported.

8. The question is whether actually there was any

unauthorised connected load. The internal reports if any

of the officers are not discussed in Ext.P10. Ext.P3 has

also not been brought to the notice of the Deputy Chief

Engineer. The conditions of supply and the regulations

W.P.(C). No.17929/2008
-:5:-

which are in force prior to the Supply Code also, according

to the learned counsel for the petitioner, necessitate for

the drawing of a mahazar and supply of the copy of the same

to the petitioner also. But this was never done.

9. All these are matters for the Deputy Chief

Engineer to consider afresh. In that view of the matter,

Ext.P10 is quashed. There will be a direction to seventh

respondent reconsider the matter with notice to the

petitioner. All the relevant materials including the

original of Ext.P3 will be called for and after hearing the

petitioner, appropriate orders will be passed within a

period of four months from the date of receipt of a copy of

this Judgment. Ultimately, if the petitioner is found

entitled for refund, the amount will be refunded within a

reasonable time.

The writ petition is disposed of as above. No costs.

(T.R. Ramachandran Nair, Judge.)

ms