High Court Kerala High Court

P.P.George And Sons vs State Of Kerala on 6 April, 2009

Kerala High Court
P.P.George And Sons vs State Of Kerala on 6 April, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

OP.No. 2773 of 2003(E)


1. P.P.GEORGE AND SONS, N.H.47, ANGAMALY,
                      ...  Petitioner

                        Vs



1. STATE OF KERALA, REPRESENTED BY THE
                       ...       Respondent

2. KERALA STATE ELECTRICITY BOARD,

3. DEPUTY CHIEF ENGINEER,

4. ASSISTANT EXECUTIVE ENGINEER,

                For Petitioner  :SRI.T.M.ABDUL LATHEEF

                For Respondent  :SRI.C.C.THOMAS, SC, K.S.E.B

The Hon'ble MR. Justice K.SURENDRA MOHAN

 Dated :06/04/2009

 O R D E R
                         K. SURENDRA MOHAN, J
               ------------------------------------------------------------
                          O.P. NO: 2773 OF 2003
               -----------------------------------------------------------
                    Dated this the 6th April, 2009.


                                   JUDGMENT

As per G.O(MS)4/92/PD dated 6.2.1992 the Government of

Kerala announced a concessional power tariff and electricity duty to

industries, as a measure of incentive. The concessional tariff was

applicable only to units that started production between 1.1.1992

and 31.12.1996. Though the petitioner did not start commercial

production before 31.12.1996, he claims the benefit of the

concessional tariff alleging that he had started commercial

production in June 1996, using a diesel generator set installed by

him. On the above basis, he challenges the denial of the

concessional rate of electricity tariff to him.

2. The petitioner is running a printing press unit at

Angamaly, which is registered as a small scale industrial unit. The

unit had applied for electrical connection and as per Ext.P4

proceedings, the Executive Engineer K.S.E.Board sanctioned the

work on an estimate of Rs.1,16,640/- on 19.6.1995. Thereafter,

the concerned Minister had directed the grant of electricity

connection to the petitioner on priority basis, as per his letter dated

O.P.2773/2003 2

24.11.1995, which is Ext.P5. The petitioner alleges that the entire

work for giving electric connection to the petitioner was over in

1996 itself but, supply was delayed without any justification and

finally, he was granted electric connection only on 1.1.1997. But,

according to him, the petitioner started commercial production

before the said date using a generator set installed by him, having

a capacity of 62.5 KVA. Since the petitioner was not given electric

connection before 31.12.1996, he submitted Exts.P8 and P9

representations and also filed O.P.19444/2001 praying for the

issue of appropriate directions from this Court, commanding the

respondents to collect only the pre 1992 tariff rates from the

petitioner. During the pendency of the said Original Petition a bill

for Rs.75,095/- was issued to the petitioner which was also

challenged by him before this Court in a Miscellaneous Petition filed

in the writ petition referred to above. This Court had granted an

order of interim stay conditional on payment of an amount of

Rs.35,000/-. Subsequently the original petition was disposed of as

per Ext.P11 judgment directing the Deputy Chief Engineer, KSEB to

consider and dispose of the representations of the petitioner within

a period of three months of the date thereof.

3. The grievances of the petitioner were considered in

O.P.2773/2003 3

compliance with the directions of this Court and orders were

passed by the Deputy Chief Engineer, KSEB which is Ext.P13. As

per Ext.P13 it has been found that the petitioner is not entitled to

the concessional tariff rates claimed by him. He has also been

found liable to pay the amount demanded as electricity charges

from him. The petitioner has filed this Original Petition challenging

Ext.P13 order and claiming that he is entitled to the benefit of the

concessional pre 1992 tariff rates announced by the Government of

Kerala as per G.O(MS) 4/92 dated 9.2.1992. Though this petition

was filed in the year 2003 no counter affidavit has been filed on

behalf of the respondents. It is seen from the proceedings that

though sufficient opportunity was granted to the respondents, they

have not chosen to file a counter affidavit till date. No prayer for

time to file counter affidavit was also made by the counsel for the

respondents. Therefore, I have heard Shri. T.M.Abdul Latiff,

counsel for the petitioner and the standing counsel for the

KSEBoard.

4. The counsel for the petitioner submitted that, the

petitioner was entitled to be given the benefit of the pre 1992

concessional tariff. According to him the unit of the petitioner was

started before 31.12.1996. The petitioner claims that he had

O.P.2773/2003 4

executed a minimum guarantee agreement on 29.7.1995. The

Electrical Inspector, Ernakulam permitted energisation of his

generator and the electrical installation on 27.6.1996 and the unit

started commercial production immediately. The petitioner did

everything on his part and started commercial production using the

generator set before 1.1.1997. According to him the petitioner had

invested money and established the unit on the expectation that

electrical energy would be supplied to him at the pre 1992 tariff

rates. He contends that the concession made available to

industrial units should not be denied to him for the reason that the

petitioner had done everything that was to be done by him before

31.12.1996 and it was not due to any fault of his that the

energisation of electrical supply to his unit was delayed beyond the

cut off date of 31.12.1996.

5. The claim of the petitioner is opposed by the standing

counsel for the respondents. According to the counsel, the

concessional rate was announced by the State Government as early

as on 6.2.1992. Even at that time, the Government had announced

that the concession would be available only to units that started

commercial production between 1.1.1992 and 31.12.1996.

Therefore, the cut off date was well within the contemplation of the

O.P.2773/2003 5

petitioner even when he started preparations for establishing his

unit. Since the petitioner’s unit was not energised before the cut

off date, he was not entitled to the concession. According to the

counsel, in Ext.P13, the impugned order, all the contentions of the

petitioner have been considered. The counsel for the respondents

contended that, it was not due to any fault on the part of the KSE

Board that the unit was not given electric connection before

31.12.1996. It is further contended that the petitioner had not

submitted any application for availing the concessional tariff rate at

any time. He has made his claim for the first time only in

O.P.19444/2001 filed by him. Therefore, it is pointed out that the

original petition is liable to be dismissed.

6. It is seen from Ext.P13 order that the equipments for

providing supply to the petitioner’s unit was received only on

27.12.1996. The installation work was completed on 30.12.1996

and the same was inspected by the Electrical Inspector on 1.1.1997.

The installation was energised on getting oral sanction of the

Electrical Inspector on 1.1.1997 itself. The Deputy Chief Engineer

who considered the above contention has found that the records do

not show any delay in giving power connection to the petitioner.

The dates mentioned above would show that there was no delay on

O.P.2773/2003 6

the part of the authorities in giving connection to the petitioner’s

unit. There is nothing on record to show that the above statements

in Ext.P13 are false. The above question being a pure question of

fact, the finding of the Deputy Chief Engineer in Ext.P13 on this

point has to be accepted. The petitioner has also not disputed the

above statements contained in Ext.P13, in the above Original

Petition. In the absence of any evidence or material to show that

the respondents were at fault in delaying grant of electric

connection to the petitioner’s unit, the above finding in Ext.P13 is

only to be upheld.

7. The next question to be considered is whether the claim of

the petitioner that he has to be granted the Ext.P3 concessional

tariff for the reason that he had started commercial production

well before 31.12.1996. A copy of the G.O dated 6.2.1992 has

been handed over to me by the parties, in court. It is to be noted

that the concession granted by the Government is in respect of

consumption of electrical energy by industrial units. The same is

granted to units which started commercial production between

1.1.1992 and 31.12.1996. Since the concession granted is in

respect of electrical energy consumed by industrial units that

started commercial production during the relevant period, the

O.P.2773/2003 7

concession cannot be made available to units which do not

commence consumption of energy during the relevant period.

Admittedly the petitioner’s unit has not consumed any electrical

energy before 31.12.1996. According to him, he has commenced

commercial production using a diesel generator. There is

absolutely no evidence to show that he had started commercial

production before 31.12.1996. Though the petitioner has

produced Ext.P17 certificate of registration dated 10.7.1996 issued

under the Kerala General Sales Tax Act, the same does not show

that he has started commercial production. Exts.P18 and P19 are

also not acceptable as evidence of commencement of commercial

production. It therefore follows that the petitioner has not been

able to produce any evidence of commencement of commercial

production before 31.3.1996.

8. Apart from the above, it is common knowledge that

commercial production of an industrial unit by utilising power

generated by diesel generators is not at all viable. That is the

reason why all industrial units apply for regular electric connection.

The diesel generators are meant only as a stand by, to prevent loss

that may be caused by disruption of production due to failure of

electric supply. The diesel generator installed by the petitioner

O.P.2773/2003 8

does not have the capacity to meet the power requirements of the

petitioner. Even if it is assumed that the unit had started

production using a generator set, the same can only be presumed

to have been in anticipation of getting a regular electric connection.

Therefore, even if it is assumed that the petitioner had started

production using a diesel generator set, the same would not entitle

him to the benefit of the concessional pre 1992 tariff rates

announced by the Government of Kerala.

9. I am supported in this reasoning by the decision of the

Hon’ble Supreme Court reported in Southern Ispat Ltd. v. State of

Kerala and others {(2004) 4 SCC 68}. In the said decision, the very

same notification dated 6.2.1992 was considered by the Apex

Court. The industrial unit in the said case claimed the benefit of

the Government order alleging that production had been started

before 31.12.1996 using a diesel generator set. The unit had also

produced returns submitted to the commercial taxes department,

the assessment order issued by the sales tax department and the

balance sheet of the company as on 31.3.1997 to show that it had

started commercial production. However, the said documents were

all rejected as unreliable and self-serving by the Apex Court. It has

also been held that the question whether the unit had started

O.P.2773/2003 9

commercial production before the appointed date was a question of

fact which was not liable to be interfered with.

10. In the above case also this Court had directed the Deputy

Chief Engineer KSE Board to consider the grievance of the petitioner

and the order passsed after such consideration is Ext.P13. The

authority who is the fact finding body has determined the questions

of fact against the petitioner. The said findings do not call for any

interference in this original petition. The Original Petition fails and

is hereby dismissed. No costs.





                                            K. SURENDRA MOHAN
                                                    Judge
jj

O.P.2773/2003    10

    K. SURENDRA MOHAN, J.

-----------------------------

   O.P.NO: 2773 OF 2003-E

-----------------------------



          JUDGMENT



   Dated: 6th April, 2009.