High Court Jharkhand High Court

M/S Shree Durga Steel Industri vs Jharkhand State Electricity Bo on 5 January, 2010

Jharkhand High Court
M/S Shree Durga Steel Industri vs Jharkhand State Electricity Bo on 5 January, 2010
                             IN THE HIGH COURT OF JHARKHAND AT RANCHI
                                          L.P.A. NO. 466 of 2009
              M/s Shree Durga Steel Industries, Dhanbad              ......     Appellant
                                        Versus
             1. Jharkhand State Electricity Board
             2. The General Manager-cum-Chief Engineer, Dhanbad
                Electric Supply Area JSEB, Dhanbad.
             3. The        DGM-        cum-Electrical      Superintending
                Engineer,Dhanbad Electrical Circle, Saraidhella,Dhanbad.
             4. The Assistant Electrical Engineer, Dhanbad Electric Circle,
                R.E.-cum-Supply Sub Division,Govindpur, Dhanbad.
             5. The Electrical Executive Engineer (Commerce &
                Revenue),Dhanbad Electric Circle, Dhanbad.
                                                                  ....... Respondents


                 CORAM :                  HON'BLE THE CHIEF JUSTICE
                                        HON'BLE MR.JUSTICE R.R.PRASAD
                                              ......

                    For the Appellant   : Mrs.Ritu Kumar
                    For the Respondents : M/s Rajesh Shankar & Abhay Prakash
                                       .....

3/5.1.2010

This appeal is directed against the order dated 4.9.2009 passed

by the learned Single Judge in W.P.(C) No.3373 of 2009, whereby the

writ petition, claiming the benefit of One Time Settlement Scheme was

denied to the petitioner-appellant as the writ petition was dismissed.

The appellant being aggrieved with the order of the learned Single

Judge has preferred this appeal.

Mrs. Ritu Kumar, learned counsel for the appellant, has

submitted that the learned Single Judge has relied upon erroneously

that the benefit of One Time Settlement Scheme could not be

conferred on the appellant-Industry since the certificate case was

pending in regard to the amount which was to be paid by the appellant

to the respondent-Jharkhand State Electricity Board. It was submitted

that the appellant was entitled to the benefit of One Time Settlement

Scheme , even though the matter had been adjudicated by way of

certificate proceeding.

However, we found it difficult to accept this contention as the

contention of the counsel for the appellant that the benefit of One time

Settlement Scheme should have been allowed to be availed of by the
2

appellant even though the certificate proceeding had concluded, has

no substance as it is not the case of the appellant that during

pendency of the certificate proceeding, the appellant had sought the

benefit of One Time Settlement Scheme.

The contention of the counsel perhaps could have been

accepted if the adjudication of the matter was still subjudice and had

not been concluded under the certificate proceeding. But, in the

instant matter, it is an admitted position that the amount payable by

the petitioner-appellant herein had already reached its conclusive

stage since the certificate proceeding concluded after proper

adjudication and the amount was held payable by the appellant. In

that view of the matter, the only course left open for the appellant

was to assail the order passed in the certificate proceeding as it is an

admitted position that One Time Settlement Scheme was meant only

for such consumers whose matter had not been adjudicated before

any Forum and the dispute was at the initial stage. This is not the

position in the instant matter as already indicated hereinbefore.

Hence, the view taken by the learned Single Judge, rejecting the writ

petition requires no interference and we concur with the view taken by

the learned Single that once the certificate officer had concluded the

certificate proceeding after which the appeal also was dismissed, the

question of benefit of One Time Settlement Scheme would not be

available to the appellant.

Under the circumstance, this appeal has no merit and

consequently it is dismissed.

( Gyan Sudha Misra,C.J.)

( R.R. Prasad, J. )

G.Jha/