Union Of India vs M/S. Modi Industries Ltd on 30 March, 1973

0
44
Supreme Court of India
Union Of India vs M/S. Modi Industries Ltd on 30 March, 1973
Equivalent citations: 1973 AIR 1281, 1973 SCR (3) 835
Author: A Grover
Bench: Grover, A.N.
           PETITIONER:
UNION OF INDIA

	Vs.

RESPONDENT:
M/S.  MODI INDUSTRIES LTD.

DATE OF JUDGMENT30/03/1973

BENCH:
GROVER, A.N.
BENCH:
GROVER, A.N.
MATHEW, KUTTYIL KURIEN

CITATION:
 1973 AIR 1281		  1973 SCR  (3) 835
 1973 SCC  (1) 781


ACT:
Indian Railways Act, 1890 Ss. 26 and 41-Complaint in respect
of past dues cannot be made under s. 41 before Railway Rates
Tribunal--In such cages. v. 26 of Act is not a bar to a suit
in civil court and question of reasonableness of charges can
be gone into by civil court.



HEADNOTE:
By  agreement dated July 4, 1933 the respondent company	 was
liable to pay charges for a railway siding at agreed  rates.
Clause	23 of the agreement laid down that it shall be	open
to the Railway Administration on giving six months notice of
sum  intent, to revise the said charges.. Clause 24  related
to  termination of the agreement in the event of  nonpayment
of dues within one month of demand., On March 26, 1949	the-
railway	 authorities informed the respondent that the  rates
were  proposed	to be increased with effect  from  April  1,
1949.	The  respondent objected" to the increase  as  being
against clause 23 of the agreement.  By a subsequent  letter
in September 1951 the Divisional Superintendent of the Rail-
way  asked the respondent to pay the charges at much  higher
rates.	 There	was  prolonged	correspondence	between	 the
parties	 without the respondent agreeing to pay	 the  higher
rates  demanded.   On September 29,  1955  the.	  Divisional
Engineer  addressed  a letter to  the  respondent  proposing
revision  of  the siding charges with effect from  April  1,
1956  after the expiry of six months according to clause  23
of the agreement.  These proposed'. charges were much  lower
than  the charges demanded by the earlier letters..  On	 May
17, 1957 the General Manager of the Railway sent a letter to
the  plaintiff for payment of Rs. 93,981-8-0 in	 respect  of
the  period  December  1  1949 to March	 31,  1956.  it	 was
intimated  that on failure to make the said  payment  within
one  month the supply of wagons would be stopped' and  steps
to determine the agreement would be taken., In May 1957	 the
respondent served a notice under s. 80 of the Code of  Civil
Procedure  and'	 thereafter filed a suit.  The	trial  court
partly	decreed	 the suit.  The High, Court  decreed  it  in
toto.  In the appeal by certificate to this Court, filed' on
behalf	of the Union of India, the questions that  fell	 for
consideration  were  :	(i)  whether  the  civil  court	 had
jurisdiction  in  view	of  Ss. 26 and'	 41  of	 the  Indian
Railways Act, 1890, to determine the reasonableness; of	 the
charges-,  (ii)	 whether  the  courts  below  if  they	 had
jurisdiction  were  justified in holding the charges  to  be
unreasonable.
Dismissing the appeal,
HELD  :	 (i) From the facts it appeared that the  rates	 are
being revised and actually enhanced, but then the matter was
kept  pending and there was exchange of	 correspondence	 and
discussion between the parties from time to time.  No effort
was  made to enforce the demand made in the various  letters
and the plaintiff was allowed to make payments according  to
the  rates originally agreed.  It was only in May 1957	that
the respondent was really threatened to make payment of	 the
outstanding  amount calculated at the revised rates on	pain
of  the	 supply of wagons being stopped	 and  the  agreement
being determined.
According to the decisions of this Court it was hardly	open
to the respondent to file a complaint under s. 41 of the Act
with regard to the.
836
Reasonableness	or otherwise of the rates and charges  which
had  already 'become due and payable.  The plaintiff had  no
grievance  whatsoever with :regard to the charges which	 had
been fixed with effect from April 1, 1956.  By means of	 the
letter dated September 29, 1955, and therefore there was  no
question  of its filings, a complaint with regard to  those
charges.   Its	grievance was confined only  to	 the  amount
which  was  being  demanded  on the  basis  of	the  revised
enhanced rates between the period December 1, 1949 and March
1,  1956.  If that amount bad actually been realised by	 the
railway authorities the plaintiff could only file a suit for
its  refund and could not have laid a complaint under s.  41
of  the	 Act before the Railway Tribunal.   By	analogy	 the
plaintiff  could not have filed a complaint with regard	 to
the  past dues as the Railway Tribunal could not have  given
any  relief in respect thereof 'following the law laid	down
by this ,Court.	 In this view of the matter apart from other
questions  involving  the  validity  of	 clause	 23  of	 the
agreement  as also of the notice or intimation of  rates  on
the  ground on noncompliance with its terms the suit  ,could
not  be	 held barred under s. 26 of the Act  and  the  civil
court could grant the relief claimed. [842H-843P]
Union  of  India  v. The  Indian  Sugar	 Mills	Association,
Calcutta,  [1967]  3 S.C.R. 219, Raichand  Amulakh  Shah  v.
Union  of  India, [1964] 5 S.C.R. 148 and Upper	 Doab  Sugar
Mills  Ltd.  v. Shahdara (Delhi)  Saharanpur  Light  Railway
Company Ltd., [1963] 2 S.C.R. 333 at p. 342, referred to.
(ii) There was no serious infirmity in the reasoning of	 the
High  Court by which it arrived at the conclusion  that	 the
question  of reasonableness of the charges, keeping in	mind
the  'facts  of	 this case, was justiciable.   Nor  bad	 any
justification  been  shown  'for  reopening  the  concurrent
finding	 of the two Courts below that the rates	 which	were
demanded for the period in question were unreasonable.	 The
suit was thus rightly decreed. [843E]



JUDGMENT:

CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1616 of
1967.

Appeal by certificate from the judgment and order dated ‘-
September 30, 1966 of the Allahabad High Court in First
Appeal -No. 198 of 1960.

Gobind Das and B. D. Sharma, for the appellant.
C. B. Agarwala, Uma Mehta, S. K. Bagga, Swreshta Bagga and
Ram Arora, for the respondent.

The Judgment of the Court was delivered by
GROVER, J.—This is an appeal by certificate from a
judgment ,of the Allahabad High Court in a suit filed by the
plaintiff-respondent for an injunction against the
defendant-appellant restraining it from realizing the sum,
of Rs. 93,981-8-0 on account of the alleged siding charges
for the period December 1, 1949 to March 31, 1956 and from
stopping the supply of wagons in the railway siding of the
plaintiff and further from cancelling the agreement ,dated
July 4, 1933 for the aforementioned reason.
The facts necessary for deciding the appeal may be stated.
By means of an agreement dated July 4, 1933 the plaintiff
entered into an agreement with the Secretary of State for
India-in-Council through the agent of the North Western
Railway (now represented
837
by the Union of India) whereby it was agreed that the former
shall Jay a railway siding from Begamabad Station Yard of
that railway for enabling the plaintiff to carry on its
business at its, premises. Clause 13 of the agreement was
as follows :-

“Freight for all classes of goods will be
charged upto and from Begumabad Station.
Railway Receipts and invoices shall be issued
to and from the station only and in accordance
with the rates from time to time published in
the Goods Traffic Books of this Railway Admi-
nistration will make the following charges in
each direction from every wagon loaded or
empty in or removed from the lines A and B
mentioned in clause 15 below
(1) Per 4 wheeled wagon Re. One.

(2) Per 6 wheeled wagon Re. One and annas
eight
(3) Per 8 wheeled wagon Re. two.”
Clause 23 of the agreement provided
“Notwithstanding anything laid down in the
foregoing clauses of this Agreement, it shall
be open to the Railway Administration on
giving six months notice of such intent, to
revise the charges laid down in clauses 8, 12,
13 and 19 of this Agreement”.

Clause 24 related to termination of the agreement in the
event of non payment of dues within one month of demand. On
March 26, 1949 the Divisional Superintendent of the E.P.
Railway (successor in interest of the North Western Railway)
informed the plaintiff that the rates were proposed to be
increased with effect from April 1, 1949, the increased
charges being mentioned in that letter. As this intimation
was not in accordance with clause 23 of the agreement the
plaintiff refused to agree to the increase. Other
objections were ‘also raised, one of the objections being
that the charges were excessive. The Divisional
Superintendent addressed another letter on May 18, 1949
informing the plaintiff that with effect from December 1,
1949 the charges mentioned therein would be made. A good
deal of correspondence and discussions between the
representatives of the plaintiff and the railway authorities
took place and by a letter dated July 20, 1951 the
Divisional Superintendent intimated that the revised siding
charges in force from December 1, 1949 were purely pro-
visional and were subject to revision. Meanwhile and
subsequent to the above date the required tests were made to
determine the charges. In September 1951 the Divisional
Superintendent wrote to the plaintiff that the siding
charges should be, paid with effect
838
from December 1, 1949 to September 30, 1951 at the following
rates :-

  (i) Per 4 wheeled wagon	    Rs.	    51-
  (ii) Per 6 wheeled wagon	    Rs.	    7/8/-
  (iii) Per 8 wheeled wagon	    Rs.	     10/-

The plaintiff protested against what was called the
exorbitant nature of the charges and made it clear that the
letter of September 1951 did not comply with clause 23 of
the agreement and that the charges were unreasonable and
could not be legitimately made. Another letter dated
October 26/November 6, 1951 was sent by the Divisional
Superintendent saying that the siding charges to be levied
with effect from first October 1951 were being assessed and
would be intimated to the plaintiff and meanwhile it should
,continue to pay the charges demanded in the letter of
September 1951 provisionally. The Divisional Superintendent
addressed another letter dated November 27, 1951 explaining
the result of the test and the actual cost of the shunting
etc. A demand was made’ that the revised siding charges
should be paid from December 1949 to September 30, 1951 at
Rs. 4/- per 4 wheeler, Rs. 6/per 6 wheeler and Rs. 8/- per 8
wheeler. The plaintiff, however. did not pay the increased
rates demanded. On September 29, 1955 the Divisional
Superintendent addressed a letter to the plaintiff proposing
revision of the siding charges with effect from April 1,
1956 after the expiry of six months according to clause 23
of the ,agreement. The charges as demanded were as
follows:–

(i) 4 wheeled wagon Rs. 1 20/-

     (ii) 6 wheeled wagon     Rs. 2 -10/-
     (iii) 8 wheeled wagon    Rs 3 501-

On May 17, 1957 the General Manager of the Railway sent a
letter to the plaintiff for payment of the, amount of Rs.
93,981-8-0 representing the difference between the amounts
due from December 1, 1949 to March 31, 1956. It was
intimated that on failure to make the said payment within
one month the supply of wagons would be stopped and steps to
determine the agreement would be taken. In May 1957 the
plaintiff served a notice under s. 80 of the Civil Procedure
Code to be defendant and ,.hereafter in October 1958 the
suit out of which the appeal has arisen was filed.
Out of the issues framed by the trial court on the pleadings
of the parties the following need be mentioned
(1) “Whether the enhancement of the siding
charges by the defendant is unjustified,
exorbitant and illegal ?

8 39
(2) Whether the demand of Rs. 93,981-8-0 by
the defendant is illegal ?

(3) Whether the court has no jurisdiction to
try the suit ?”

On issue. No. 1 the trial court held that the charges
demanded were unjustified and exorbitant. It was held that
out of the demand of Rs. 93,981-8-0 the demand for Rs.
22,111-3-0 was illegal. On issue No. 4 the trial court
expressed the view that it had jurisdiction to try the suit
in respect of that portion of the claim whereby the legality
of the enhanced siding charges had been challenged on
account of being in violation of clause 23 of the agreement
but it had no jurisdiction to try the suit in respect of the
second ground whereby the enhanced siding charges had been
challenged as unjustified and exorbitant.
The plaintiff appealed to the High Court and the defendant
filed cross objections. The High Court affirmed the finding
of the courts below that the enhancement made by the Railway
Administration was highly unjustified and exorbitant. But
it did not accept its finding about the legality of the
enhancement and also on the question of the jurisdiction of
the civil court. The appeal was consequently allowed in
toto and the cross objections were dismissed.
The principal question which has been agitated before us
relates to the jurisdiction of the civil court to determine
the reasonableness of the charges. A subsidiary question
has been raised that assuming the civil court had the
jurisdiction, whether the courts below were justified in
holding that to be unreasonable. For the purpose of
determining the question of jurisdiction we shall have to
examine the relevant provisions of the Indian Railways ,Act,
1890, hereinafter called the ‘Act’. Section 3 contains the
definitions. Clauses 11 and 13 defining the words “traffic”
and rates” are as follows –

“(11) “trafic” includes rolling stock of every
description as well as passengers, animals and
goods;

(13) “rate” includes any fare, charge or other
payment for the carriage of any passenger,
animal or goods”;

Chapter V headed “traffic facilities” commences with S. 26.
According to that section except as provided in the Act no
suit shall be instituted or proceedings taken for anything
done or any omission made by the Railway Administration in
violation or contravention of any provision of that Chapter.
Section 27 (1 ) places a duty on every Railway
Administration to afford all reasonable facilities for the
receiving, forwarding and delivering of traffic upon and
from the several railways belonging to or worked
840
by it and for the return of the rolling stock. Section 29
is as follows :-

S.29 (1) “The Central Government may by
general or special order fix maximum and
minimum rates for the whole or any part of a
railway and prescribe the conditions in which
such rates will apply.

(2) The Central Government, may, by a like
order, fix the rates of any other charges for
the whole or any part of a railway and
prescribe the conditions in which such rates
of charges shall apply.

(3) Any complaint that a railway
administration is contravening any order
issued by the Central Government under sub-
section (1) shall be determined by the Central
Government”..

Section 34 relates to the constitution of the Railway Rates
Tribunal for the purpose of discharging functions specified
in Chapter V. Sections 39 and 40 give the jurisdiction
and powers of the Tribunal, Section 41 to the extent it is
material may be reproduced :-

S.41 (1) “Any complaint that a railway
administration-

(a) is contravening the provisions of s. 28
or

(b) is charging for the carriage of any
commodity between two stations a rate which is
unreasonable or

(c) is levying any other charge which is
unreasonable,
may be, made to the Tribunal, and the Tribunal shall hear
and decide any such complaint in accordance with the
provisions of this Chapter”.

(
2
)
……………………………………………
.

(3) In the case of a complaint under clause

(b) or clause (c) of subsection (1), the
Tribunal may fix such rate or charge- as it
considers reasonable :

Provided
that …………………………………..

(4)…………………… ”

on behalf of the appellant the bar created by the s. 26 to
the jurisdiction of ordinary courts has been invoked. It
has been argued that s. 29(2) postulates the fixation of
rates of charges other than those contemplated by sub-s.
(1). If there is any grievance that the railway
administration is levying a charge which is unreasonable it
will be covered by S. 41 (1) (c) and there-

841

fore, only a complaint can be made to the railway
administration in that matter. The jurisdiction of the
civil court will be barred because exclusive jurisdiction
has been conferred on the Railway Rates Tribunal for
determining whether the charge being levied is unreasonable.
According to the High Court Chapter V has nothing to do with
charges which are payable under a contract. The validity
and interpretation of clause 23 of the agreement between the
parties was a matter for the interpretation of the civil
court and could not possibly be barred by s. 26 of the Act.
Section 41 (1) (c) has no application to an enhancement
already made in the purported exercise of the right under a
contract.

Now section 26 only bars the institution of a suit or
proceedings for anything done or any omission made in
violation or contravention of any provision of Chapter V.
Section 29(2) empowers the Central Government to fix the
rates of any other charges by a general or special order.
In view of the language of s. 41 (1) (c) if it is assumed
that the rates cannot be unreasonable and if the Central
Government fixes unreasonable rates it may be possible to
say that there has been a contravention or violation of s.
29(2). But such fixation of rates under that provision has
to be by a general or special order. It has been suggested
that a communication made under a contract cannot fall
within the meaning of the word “order” as contemplated by s.

29. Prima facie, there may be some difficulty in acceding to
the contention of the learned counsel for the appellant that
any part of s. 29 will cover a revision of rates made by the
railway authority in terms of a contract but the matter
seems to stand concluded by the decision of this Court in
Union of India v. The Indian Sugar Mills- Association,
Calcutta
() according to which it is immaterial that the
charges being levied by the railway administration arise as
a result of a voluntary agreement. The real difficulties in
the way of the appellant are two fold; firstly, if any
question arises about the validity of a clause of a contract
that will be entertainable by a civil court. As laid down
in Raichand Amulakh Shah v. Union of India (2) the Railways
Tribunal has no jurisdiction to decide whether the rules
empowering the railway administration to levy a particular
charge are ultra vires or whether the railway administration
collected amounts in excess of the charges which it can
legally levy under a rule. In Upper Doab Sugar Mills Ltd.
v. Shahadara (Delhi) Saharanpur Light Railway Company
Ltd.
(,’) two main points arose; one was whether the Railway
,Tribunal had jurisdiction to entertain the complaint as
regards the reasonableness of the rates prior to the
institution of the complaint
(1) [1967] 3 S. C. R. 219. (2) [1964] 5 S. C. R. 148.
(3) [1963] 2 S. C. R. 333 at p. 342.

6-L797SupCT/73
842
and the other was whether it had jurisdiction to grant
refund for the aforesaid period. This is what was said by
Das Gupta J.

“The words “charging” in cl. (b) and “levying”
in cl. (c) were used in the one and the same
sense. We find it impossible to agree however
that they were used to include “collecting”.
It appears to be clear that if the intention
of the legislature was to give the Tribunal
jurisdiction over complaints in connection
with charges ,already made the legislature
would have used the words “has charged and is
charging” and would not merely say “is
charging”. Special jurisdiction of such a
nature would be given clearly and the very
fact that the words “has charged” have not
been used is sufficient ground for ,thinking
that it was not the legislature’s intention to
give the Tribunal jurisdiction over complaints
in connection with charges made in the past.
In our opinion, the words “is charging” in cl.

(b) and “is levying” in cl. (c) must be
construed to mean “is demanding a price at the
present time for services to be rendered”.

Coming to the facts of the present case it is apparent that
one of the main questions involved was whether clause 23 of
the contract between the parties was not void because it
contravened s. 29 of the Indian Contract Act. Another
question which had to be investigated was whether a proper
notice regarding the enhancement of rates had been given in
accordance with the terms of the said agreement. From the
facts which have been stated it appears that the rates were
being revised and actually enhanced, but then the matter was
kept pending and there Was exchange of correspondence and
discussion between- the parties from time to time. No
effort was made to enforce the demand made in the various
letters and the plaintiff was allowed to make payments
according to the rates originally agreed. It was only in
May 1.957 that the plaintiff was really threatened to make
payment of the outstanding amount calculated at the revised
rates on pain of the supply of wagons being stopped and the
agreement being determined. It is somewhat surprising that
in September 1955 the rates which were revised were very
much less-than those which were demanded for the prior
period. The position thus remained in a flexible state and
there is a good deal of substance in the submission on
behalf of the plaintiff-respondent that a complaint was not
filed under S. 41 of the Act because the rates which “,were
being paid and actually accepted were the same as the
contractual rates and not the revised or enhanced rates.
According to the decisions of this Court referred to before,
it was hardly open to the plaintiff to file a complaint with
regard to the reasonableness or otherwise of the rates and
charges which had already become due
843
and payable. The plaintiff had no grievance whatsoever with
regard to the charges which had been fixed with effect from
April 1, 1956 by means of the letter dated September 29,
1955 and therefore there was no question of its filing a
complaint with regard to those charges. Its grievance was
confined only to the amount which was being demanded on the
basis of the revised ,enhanced rates between the period
December 1, 1949 and March 1, 1956. If that amount had
actually been realised by the railway authorities the
plaintiff could only file a suit for its refund and could
not have laid a complaint under s. 41 of the Act before the
Railway Tribunal. By analogy the plaintiff could not have
filed a complaint with regard to past dues as the Railway
Tribunal could not have given any relief in respect thereof
following the law laid down by this Court. In this view of
the matter appart from other questions involving the
validity of clause 23 of the agreement ,as also of the
notice or intimation of enhancement of rates on the ground
of non-compliance with its terms the suit could not be held
barred under S. 26 of the Act and the civil court could
grant the relief claimed.

We have not been shown any serious infirmity in the
reasoning of the High Court by which it arrived at the
conclusion that the question of reasonableness of the
charges, keeping in mind the facts of this case, was
justiciable. Nor has any justification been shown for
reopening the concurrent finding of the two courts below
that the rates which were demanded for the period in ques-
tion were unreasonable. The suit was thus rightly decreed.
The appeal fails and it is dismissed; but we make no order
as to costs.

G.C.			    Appeal dismissed.
844



LEAVE A REPLY

Please enter your comment!
Please enter your name here