High Court Rajasthan High Court - Jodhpur

Anand Bhatia vs Union Of India on 18 December, 2008

Rajasthan High Court – Jodhpur
Anand Bhatia vs Union Of India on 18 December, 2008
                                 1

 IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN
                          AT JODHPUR


                         JUDGMENT

             Anand Bhatia vs. The Union of India


      S.B.Civil Misc. Application (Arbitration) No.66/2006

             under section 11 (8) of the Arbitration and
             Reconciliation Act, 1996.


DATE OF JUDGMENT                       ::       18.12.2008

                            PRESENT

             HON'BLE MR.JUSTICE MANAK MOHTA


Mr.H.R.Soni for the petitioner.
Mr.Kamal Dave for the respondent.


BY THE COURT :

The instant Civil Misc. Application is being filed for the

appointment of the arbitrator to adjudicate the claim of the

applicant under sections 12,13,14,15 read with section 11 (8)

of the Arbitration Act 1996 (hereinafter referred to as the Act

of 1996′).

2

The brief facts of the case for the just disposal of this

application are that from the perusal of the record it reveals

that an agreement was entered into between the Union of

India and the appellant on 23rd October 1991 regarding

supply from AQG Quarry 30,000 cubic meter of 65 mm gauge

ballast to the Northern Railway specification and stacking

on the railway land at Pokaran Railway Station, then loading

into railway wagons at Pokaran Railway Station . Copy of the

said agreement was annexed as Annx.5. It was further

submitted that under the said contract the Railway Authority

used to assign the vacant lands for stacking the ballast and

then further railway authority was duty bound to provide DMT

( Special Train ) for lifting stacked ballast . The contractor was

to stack ballast at the specified land / plots to be allotted by

Railway for the purpose of stacking, and further within the

contract period Railway was to provide DMT so that the

material already stacked may be removed and contractor may

further stack the material by following same process.

It was submitted that the material so required was to be
3

stacked near the Railway land only and it was to be stacked

in huge quantity only on the specified land /plot demarcated

for this purpose but the Railway was not having much more

land/plots demarcated, the supply which was agreed, that was

30,000 cubic meter, was to be stacked as per the terms of the

contract but then the precondition for the purpose of the work

on the part of the Railway was that the railway was to supply

the DMT for lifting already stacked ballast by employing huge

quantity of labour and expanding huge amount of money for

bringing the trucks, stack all the plots allotted to him but then

within the stipulated time the railway could not supply the

requisite number of DMT and in absence of the same, the plot

already stacked could not be cleared and as per the clear

terms of the contract, unless and until the already stacked

material is cleared, the applicant could not have stacked the

other round of the ballast. It was further submitted that the

applicant performed his part to the best of his ability and still

made several demands to supply him DMT, so as to clear the

already stacked plots by lifting the stacked material, but all

efforts of the applicant could not be materialised as the railway

did not provide him DMT in time.

4

In this respect, it was further submitted that numerous

representations were made on behalf of the applicant. The

applicant has nowhere shown his inability to perform the work

in the contract period and after expiry of the contract period,

the applicant was not in a position to perform the work because

of escalation and high rise of labour cost, transportation

charges and royalty etc. It was submitted that the railway

authority, without considering the factual position, unilaterally

without authority, wrongfully forfeited the security amount of

the applicant and also imposed penalty on the applicant . It

was alleged that the railway authority was not authorised to

impose penalty . On the basis of the aforesaid submissions , it

was submitted that thus there arose a valid referable dispute

with regard to said contract. It was also submitted that as per

terms of the contract and as per agreed general conditions of

the contract , all disputes with regard to contract was to be

adjudicated by arbitral proceedings. The applicant in that

respect moved the authority. The applicant in his application

submitted the valuation of the dispute amount to be Rs.50lacs

plus interest @ 24% per annum from the date the amount
5

became due to the applicant.

It was submitted that as per provisions of General

Conditions of Contract the dispute was referable for

adjudication to two arbitrators. It was further submitted in the

application that the railway authority, without caring the

relevant provisions , proceeded in an arbitrary manner. As per

agreed terms and conditions, out of the two arbitrators one

would be appointed by Railway authority and one of them

would be nominee of the party and they will further appoint

umpire. But the railway authority did not proceed as per true

spirit of the terms and appointed sole arbitrator namely

Rashmi Chawala. Thereafter, the petitioner submitted an

application for the appointment of the arbitrator as per agreed

terms, on which orders were passed to appoint arbitrator in

accordance with clause 64 of General Conditions of

(Regulations and Instructions for Tenderers and Standard

Forms ) Contract. It is further revealed that thereafter two

arbitrators were appointed. Rashmi Goyal was nominated as

Railway nominee and B.K. Gupta, Dy.CE/C/Ju.II Northern

Railway, Jodhpur was nominated as contractor’s nominee on
6

the suggestion of the applicant. In this connection reference

was made to Annx.1. It was further contended that these

nominated arbitrators, in fact, never entered into reference.

It was also submitted that one of the arbitrator

B.K.Gupta, the nominee on the part of the contractor, lodged

an FIR against the applicant before the RPE that the applicant

had committed theft of the railway property, which he was

required to transport under another contract agreement with

Railway . It was submitted that on that FIR, RPF authorities

filed a complaint in the shape of charge sheet against the

applicant petitioner. The petitioner was falsely implicated in

that criminal case and ultimately case was decided in his favour

by the learned Addl.Sessions Judge No.1, Jodhpur in regular

criminal case No.06/2005 decided on 26.09.2005. A copy of

the said judgment was annexed as Annx.2. It was further

submitted that thus, the action of B.K.Gupta was contrary to

applicant’s interest, therefore, he moved this Court under

section 11 (6) of the Arbitration Act to appoint Arbitrator. In the

meantime, the Railway authority also unilaterally changed

their nominee and in place of Rashmi Goyal , they appointed
7

Smt.Neelam Sanghi. In this respect, Annx.3 was annexed. It

was again submitted that despite change of nominated

arbitrator by the Railways, the arbitrators never entered into

reference. The application was registered as Civil misc.

Arbitration Application No.22/2003. The railway authority,

without filing any detailed reply, submitted that the arbitrator

has been appointed. Therefore, the application was dismissed

as infructuous. The copy of the order passed was annexed

as Annx.4. It was submitted that the position remained as it

was. The arbitrators appointed long back vide order dated

20.06.95 and further modified by order dated 06.03.2000 have

still not entered into reference, though the dispute was to be

decided within a period of four months, that had expired long

back and, thereafter, they were not authorised to pass any

award. In these circumstances, the present application was

filed.

It was further submitted that, before filing the said

application, several representations and requests were made

for reference. Thus, , the railway authority got adequate notice

by judicial proceedings continued between the parties. It was
8

also submitted in the petition that several letters / notices were

given to the arbitrators nominated by the railway but they

were received back with the note that the addressee has left

the place without address , some of them were placed with

application. Thus, it was also submitted that the applicant

made maximum efforts to materialise the arbitration

proceedings and to get the dispute adjudicated but everything

went in vain. Therefore, submitting this application, a prayer

was made to appoint an independent and sole arbitrator.

Notice of this application was given to the respondents.

The Railway Authority denied the allegations made in the

application and filed a detailed reply mainly alleging therein

that the arbitrators have already been appointed. Further,it was

submitted that the matter was previously heard by the court

on the said allegations and the application was rejected vide

order dated 12.09.03. Therefore, for the same relief, second

application is not maintainable and is hit by the principles of

resjudicata. Along with the reply, the learned counsel also

placed the order of this court dated 12.09.03. It was also

submitted that by way of this application, in fact the appellant
9

was to get removal of the nominated arbitrators. For that he

should have moved the civil court. Thus, by way of present

application he is not entitled for any relief and prayer was

made to dismiss the application.

It is further revealed from the record that to counter the

allegations made in the reply by the railway authority, petitioner

filed an additional affidavit along with relevant documents. It

was submitted in the affidavit reiterating the earlier ground that

the petitioner applied to the authority for copies of certain

letters written by the Railway authority to the arbitrators

under Right to Information Act, which were lying in the office

file of Railway and in pursuance of that, certain copies of the

letters were supplied . In the affidavit he submitted the details

of letters, on the basis of copies supplied by the Railways and

submitted that a letter dated 15/18.12.95 was issued from the

office of G.M. Railways, intimating the arbitrators that an

award was required to be made within a period of four months,

after entering into reference. Further, intimating them that if

the claimant is delaying then to proceed exparte. Copy of

letter Anx. 14 was placed in this respect. Letter dated
10

04.06.99 , Annx.15, was issued for finalisation of the arbitration

case . A letter dated 06.03.2000 again issued by the Office of

the G.M. Railways to nominated arbitrator Neelam Sanghi ,

requesting her to enter into arbitration, Annx. 16 was

produced in this respect. Letter dated 16.08.00 was sent by

one of the arbitrator Mr.B.K.Gupta replying to G.M., Railways

that after the expiry of four months, arbitrator has no power to

pass award and informed to make a request before the court

for extension of time. Copy of this letter was produced, marked

as Annx.17. Letter dated 29.03.04 issued from the office of the

Senior Divisional Engineer NW. Railways, addressed to

Dy.CME, NW Railways, Jaipur, intimating that till today he has

not received any notice of arbitration proceedings from Neelam

Sanghi and B.K.Gupta. Copy of this letter is marked as

Annx.19, similar type of letter dated 27.06.05, marked as

Annx.20. In the affidavit he further submitted that one of the

arbitrator B.K.Gupta has already been relieved after transfer

from the Railway Coach Factory but the Railway authority did

not supply the correct address. In this respect he also filed

Annx.21 to 24.

11

Thereafter, arguments were heard and perused the

pleadings of parties as well as record of the case.

During the course of arguments, learned counsel for the

petitioner further reiterated the contentions placed by way of

application and again stressed that the matter is pending for

the last 15 years without any adjudication. The dispute of the

appellant is genuine, the railway authority proceeded arbitrarily

and thereby the applicant has suffered a huge loss by their

inaction. His security money has been forfeited and for his no

fault he has been penalised. It was urged that due to

arbitration clause , he is not entitled to approach directly to the

civil courts. The nominated arbitrators have never entered into

arbitration proceedings, therefore, now the railway authority

has waived his right to appoint new arbitrators, thus, in the

given circumstances, the sole independent arbitrator is

required be appointed. It was also submitted that the railway

now cannot take shelter of clause rule 64 of the General

Conditions of Contract . The nominated arbitrators by the

railway are not ready to proceed in arbitral proceedings and

they never entered into reference, they never issued any
12

notice of reference and now they are not competent to pass

award as arbitrators.

During the course of arguments, he drew my attention

towards the letter supplied by the Railway Authority on his

request under the Right of Information Act and again on the

strength of those letters, submitted that it is established from

their own record that the arbitrates have never entered into

arbitral proceedings. The prescribed time for passing the award

has expired long back , one of the arbitrators himself has

shown his incapacity to pass an award as it is disclosed from

the letter given by B.K.Gupta dated 25.09.00, annx.18. In these

circumstances, no arbitral proceeding is legally pending

before the Arbitrators, therefore, it was again stressed that an

independent sole arbitrator may be appointed and prayed that

the application may be allowed.

In support of his contentions, he also cited judgments

given in cases of Krishan Lal vs. Haryana S.A.M. Board[ AIR

1986 P&H 376], VIP Industries Ltd. v. Saboo Sodium

Chloro Ltd. & Anr. [AIR 2008 (NOC) 1449 (Raj.) 439], Murari
13

Lal Khandelwal vs. Rajasthan State Seeds Corporation &

Ors. [AIR 2008 Rajasthan 108], Mahipatlal Patel vs. Chief

Engineer & Anr. (Civil Appeal No.2350/2008), and Citibank

N.A. Vs. TLC Marketing PLC & Anr. [AIR 2008 SC, 118].

On the contrary, learned counsel for the railways refuted

the contentions and submitted that the present petition is not

sustainable, as already on the same relief application filed

earlier has been dismissed. Further, for the removal of the

arbitrator the present application is not maintainable . It was

also submitted that as per terms of the contract under the

General Conditions of Contract (Regulations and instructions

for tenderers and Standard Forms of Contract, as per clause

64 no independent arbitrator can be appointed. Only gazetted

Railway Officer could be appointed as arbitrator. The learned

counsel drew my attention towards the said clause and further

made submission that the application is not entertainable in its

present form and prayed that it may be dismissed. In support of

his contention he placed reliance on the provisions of General

Conditions of Contract.

14

I have considered the rival submissions and keeping in

mind the contentions raised by the learned counsel for the

parties, perused the record.

From the perusal of the record, as well as the

contentions placed during the course or arguments, it is made

clear that a contract was entered into between the parties on

23.10.91 regarding supply of AQG Quarry 30,000 cubic meter

of 65 mm gauge ballast to the Northern Railway. It was also

agreed that supply were to be made according to specification

and strictly according to the terms of the contract. It is alleged

by the petitioner that specific land was to be provided by the

Railway Authority where the relevant material could be

stacked. Further, as per the terms of the contract, DMT

(special trains) for lifting the stacked ballasts,were to be

provided by Railway authority. It is alleged by the petitioner that

that railway did not discharge their obligation and due to

inaction on the part of the railways, he could not perform the

contract in time. He has further alleged that the railway

authority, without considering the factual aspect, had

proceeded to forfeit the security money and imposed
15

penalty. Thus, there was dispute between parties with regard to

terms of the contract. It is also not disputed by the parties that

as per the terms of the contract, and as per agreed clause

mentioned in the relevant general condition of the contract that

in case of any dispute with regard to the contract between the

parties, the matter will be resolved through arbitral

proceedings.

It is revealed from the record that the petitioner has time

and again moved the authority in this respect and the railway

authority, after a long exchange of communication and with

the intervention of the court , two arbitrators Neelam Sahini

and B.K.Gupta were appointed. But it is further revealed from

the record that they have not entered into arbitral proceedings.

This fact is established from the document filed by the

appellant , among them some of the letters are of the G.M.,

Railways which has not been disputed by Railway authority

despite sufficient time. From the perusal of these letters,

some of them of recent time, I am satisfied that the arbitrators

had never entered into arbitral proceedings. There are serious

allegations against B.K.Gupta , nominated arbitrator on the part

of the applicant . Looking to the serious allegations, it is not
16

desirable to continue him as arbitrator and B.K.Gupta himself

has shown his inability to pass the award on the pretext that

time has expired. With regard to other arbitrator Neelam

Sanghi, despite efforts, no response from her side is received

by Railway, as well as to petitioner , even her address is not

traceable and Railway authority has said nothing about her.

In this respect, the authorities cited by the learned

counsel for the petitioner’s side are also relevant. In the VIP

Industries’ case (supra) where grounds of reasonable

apprehension about impartiality of arbitrator, it was observed

that the High Court can exercise powers under Section 11 (6)

to appoint arbitrator after removing nominated arbitrator. In

Murari Lal Khandelwal’s case (supra) where there were

allegations against arbitrator of biasness, independent

arbitrator was appointed. In Krishan Lal ‘s case (supra), the

appointed arbitrator was transferred after reference of dispute.

It was held that where the arbitrator appointed by designation,

arbitrator so appointed is divested of jurisdiction in the matter.

I have also considered the contentions raised by the
17

learned counsel for the respondent . But looking to the facts

and circumstances of the case, as the appointed arbitrators

have not entered into arbitral proceedings, thus the contentions

are not sustainable. I have also considered the contentions

raised by the respondent that the matter was previously heard,

but the present application is based on the changed

circumstances. Therefore, the previous proceeding has no bar

to appoint independent arbitrator. I have also considered the

other contentions. The railway authority got appropriate time

and notice to proceed with the matter, but they failed to take

appropriate action and they remained in active on their part.

Thus, the contentions placed with regard to clause 64 of

General Conditions are also having no force.

In these circumstances, there is no option except to

appoint independent arbitrator. On the basis of aforesaid

discussions, the application filed by the petitioner is allowed

and Mr.S.R.Sharma , District & Sessions Judge (Rtd.) is

appointed as arbitrator both the appointed arbitrators will not

have any authority to pass any award. Application filed by

petitioner stands allowed.

18

The parties are entitled to file their claim and counter

claim before the arbitrator and the arbitrator will decide the

same in accordance with law. Rs.10,000/- is fixed as initial

expenses towards the arbitral proceedings, so that the

arbitration proceedings may start. This amount will be borne by

the petitioner and this amount will be adjustable from the final

charges determined by the arbitrator. Fee of the arbitrator and

other expenses of the arbitration proceedings will be

determined by the arbitrator himself. That will be borne by both

the parties equally. The appointed arbitrator be intimated

accordingly.

A copy of this order may also be sent to the District

Judges, Jaisalmer and Jodhpur, with a direction that if any

accommodation and infrastructure is demanded by the

Arbitrator for arbitral proceedings, that may be provided to

the Arbitrator.

(MANAK MOHTA), J.

l.george