T.R. Ramachandran Nair, J.
- - - - - - - - - - - - - - - - - - - - - - - -
W.P.(C) No. 28944 of 2010-P
- - - - -- - - - - - - - - - - - - - - - - - - - -
Dated this the 20th day of September, 2010.
JUDGMENT
The petitioner has completed his 8th Semester B.Tech Course in Civil
Engineering from Government College of Engineering, Kannur. He is
aggrieved by the delay in publishing the result of revaluation of his 8th
Semester B.Tech Examination in Industrial Management (CE 2K 801) and
Construction Engineering and Quantity Surveying (CE 2K 804). The
petitioner applied for revaluation of the above papers on 2.9.2010 by
remitting prescribed fee. Exts.P2 and P2(a) are the true copies of the
application submitted by the petitioner and the cash remittance receipt.
Herein, the main prayer is for a direction to the University to complete the
revaluation as sought for in Ext.P2 application, within a period of two
weeks.
2. Heard learned Standing Counsel for the University. It is
submitted that sufficient time may be granted to complete the revaluation
and inform the result to the petitioner.
3. There will be a direction to the University to complete the
revaluation and inform the result to the petitioner within a period of six
wpc 28944/2010 2
weeks from the date of receipt of a copy of this judgment, if the application
and the payment of fee are in order and if the petitioner has complied with
all other formalities.
The writ petition is disposed of as above. No costs.