Delhi High Court High Court

B.S.N.L. vs Saroj Krishana Atray & Ors on 20 May, 2010

Delhi High Court
B.S.N.L. vs Saroj Krishana Atray & Ors on 20 May, 2010
Author: Rekha Sharma
                                                             REPORTABLE


*       IN THE HIGH COURT OF DELHI AT NEW DELHI


                                FAO No.72/2007


                                          Date of Decision: MAY 20, 2010


        B.S.N.L.                               ..... Appellant
                              through Mr. Asad Alvi, Advocate with
                              Mr. Faiz Hyder Rizvi, Advocate

                     versus


        SAROJ KRISHANA ATRAY & ORS         ..... Respondents
                     through Mr. Naresh Kaushik, Advocate with
                     Ms. Amita Kalkal Chaudhary & Mr. Aditya
                     Verma, Advocates

        CORAM:
        HON'BLE MISS JUSTICE REKHA SHARMA

1.      Whether the reporters of local papers may be allowed to see the
        judgment? Yes
2.      To be referred to the reporter or not? Yes
3.      Whether the judgment should be reported in the „Digest‟? Yes

REKHA SHARMA, J. (ORAL)

This appeal has been preferred by the appellant against the

order of Additional District Judge, Shri M.K.Gupta dated

October 16, 2006 whereby the learned Judge has dismissed the

objections filed by the appellant against the arbitration award dated

September 05, 2005 made by Sole Arbitrator, Shri S.M.Aggarwal.

Unfortunately, the Additional District Judge has given no reasons for

dismissing the objections except stating the provisions of law. Hence,

FAO No.72/2007 Page 1 of 7
it has fallen upon this Court to deal with the objections raised before

the Additional District Judge.

It is not in dispute between the parties that a lease deed was

entered between them in respect of Flat No.1502 on 15 th Floor,

Devika Tower, 6, Nehru Place, New Delhi, measuring 400 sq. ft. The

first such lease deed was dated March 28, 1986 and it was to

commence with effect from April 01, 1986. It is also not in dispute

that the said lease deed dated April 01, 1986 was renewed from time

to time after every three years and the last renewal was made on

April 01, 2001, the other terms and conditions of the lease deed

remaining the same.

It so happened that on December 31, 2002 the appellant who

was the lessee of the said premises gave a notice in writing to the

respondents-lessors, intimating thereby that it proposed to surrender

the premises after the expiry of the period of three months, i.e. on

March 31, 2003. The respondents in response to the notice wrote to

the appellant on January 10, 2003 calling upon it to restore the flat in

question in the same shape and condition in which it was taken at the

time of execution of the initial lease deed and till then declined to take

possession of the same. The appellant, in the meanwhile, in terms of

its notice dated December 31, 2002 though vacated the flat, but put

its own lock on the same. The respondents, on the other hand,

invoked the arbitration clause and consequently, Shri S.M.Aggarwal,

a retired Additional District Judge was appointed as the arbitrator to

go into the questions – whether the appellant had offered to the

FAO No.72/2007 Page 2 of 7
respondents possession of the flat in the same shape in which it was

taken when the lease deed was executed and if not, whether the

respondents were entitled to the rent of the flat as agreed upon up till

the expiry of the period of notice, i.e. March 31, 2003 and thereafter

on enhanced rent which as per the terms of the lease deed was to be

15% more than the last agreed rent till the flat was handed over to the

respondents in the original shape and further, whether the

respondents were liable to claim the expenses incurred in bringing

the flat to its original shape as well as the maintenance charges which

the respondents became liable to pay after March 31, 2003.

It is the case of the respondents that when the flat in question

was leased out to the appellant, it had four walls and a toilet block

with a separate and an independent entry gate having full-fledged

partitioned wall from floor up to the ceiling between the demised flat

No.1502 and contiguous adjoining flats No.1503A and 1508A and that

the appellant who was also in possession of the adjoining contiguous

flats dismantled the wall of flat No.1502 so as to make all the flats

into a one full hall.

The appellant has disputed that the flat in question was given in

the manner as stated by the respondents.

The arbitrator after examining evidence led before him has held

that the flat as initially let out to the appellant was having four walls

and a toilet block. The arbitrator while giving this finding has,

particularly, made reference to the affidavit of Shri Subhash

Sharma, XEN (Electrical) who was examined by the appellant as its

FAO No.72/2007 Page 3 of 7
witness. The relevant paragraph, where the arbitrator has discussed

the evidence of this witness, runs as under:-

“x x x x x x

12. The claimants‟ attorney in his Affidavit had
categorically stated on oath that that flat No.1502
with four walls and independent gate for entry and
exit having a toilet block was the one let out to the
respondent. The respondent in the Affidavit of
Shri Subhash Sharma, XEN (Elect.) did not take any
specific stand-controverting stand of the claimants.
The respondent‟s Shri Rakesh Mathur, the then
Electrical Engineer had responded to the claimants
letter dated 10.4.2003 enclosing letter of builders
M/s. Pragati Construction Company of Devika Tower
and had taken entirely absurd stand that
M/s. Pragati Construction Company might have
handed over the possession of the flat to the
claimants as per contents of their letter. But that
did not mean that the flat was handed over to the
respondent in the same state. Hence, the
respondents are not liable to construct any partition
wall etc. The letter date 7.3.2003 of M/s. Pragati
Construction Company which was enclosure of
claimants letter dated 10.4.2003 clearly mentioned
confirming enquiry of the claimants that flat
No.1502 in Devika Tower measuring 400 Sq. feet
was handed over to the claimants on 1.5.1986,
complete in all respects viz. partition walls, toilet,
wiring of electricity and telephone, fire/smoke
detectors etc. On page P-55 of the statement of
facts and claims is a provisional letter of possession
dated 28.3.1986 vide which M/s. Pragati
Construction Company had given provisional
possession and the claimants had taken over
provisional possession of flat No.1502 in all
resepcts.”

Having regard to the aforementioned finding of the arbitrator

who has relied upon the appellant‟s own witness, it is not open to the

appellant to contend that the flat in question when it was leased out

did not have four walls and a toilet block or a separate independent

entry gate. In any case, the issue before the arbitrator was a question

of fact and the arbitrator having given a finding, this Court will not

FAO No.72/2007 Page 4 of 7
re-appreciate the evidence led before the arbitrator and superimpose

its own finding on the issue raised and decided by the arbitrator.

The arbitrator has also given the finding that the actual physical

possession of the flat was given over to the respondents in his

presence on February 14, 2005 when he had himself visited the flat in

question and there the representative of the appellant and the

respondents were also present. The arbitrator in his award has also

noted the condition of the flat as it existed on February 14, 2005. The

relevant part of the observations made by the arbitrator in this regard

run as under:-

“x x x x x x

13. During the site inspection carried out on
14.2.2005 by the undersigned in the presence of the
parties, was had found a toilet block in the corner of
flat No.1501 owned by Shri T.S.Oberoi and also let
out to the respondent along with flat No.1502,
1503A and 1508A. We had also found only one gate
which was in fact the gate of flat No.1501 for entry
which led us to a big hall comprising of flat No.1501
of Shri T.S.Oberoi and flat No.1502 of the claimants
with a passage opened into flat No.1508A by
breaking into the partition wall separating flat
No.1502 and 1508A. We had also found that the
partition wall separating flat No.1502 from flat
No.1508A and 1503A had a passage opened into flat
No.1508A and portion of the wall between flat
No.1502 and 1503A had been lately raised for an
area of about size of two passages i.e. about 10 feet
but was left un-plastered. This shows that there was
indeed a full partition wall from floor up to roof
between demised flat No.1502 and adjoining
contiguous flat Nos.1503A and 1508A. The
inspection had also showed prominence of plaster of
the exterior wall of flat No.1502 adjoining the gate
of flat No.1501 which clearly revealed entry and
identical entrance gate which had been walled up.
Shri Tilak Raj Baweja, who was the concerned A.E.
(Elect.) at the time the termination of lease notice
was given could not point out any independent entry
to flat No.1502. The inspection had shown that
there was no partitioned wall between the demised

FAO No.72/2007 Page 5 of 7
flat No.1502 of the claimants and flat No.1501 of
Shri T.S.Oberoi in existence to distinguish one from
the other but on the floor and the ceiling there were
clear and corresponding tell tale marks that such a
partitioned wall once existed……..”

After having given the aforementioned findings, the arbitrator

made the following award in favour of the respondents:-

(i) The respondents were allowed rent @ Rs.10,862/- per

month up to March 31, 2004, i.e. up to the expiry of the period

of the lease deed, amounting to Rs.1,30,344/-.

(ii) The respondents have also been awarded compensation/

damages @ Rs.12,491/- per month from April 01, 2001 till

February 14/15, 2005 when the keys of the flat were actually

handed over to the respondents, amounting to Rs.1,12,419/-

from April 01, 2004 to December 31, 2004 plus Rs.18,736/- up

to February 14, 2005, totaling Rs.1,31,155/-.

(iii) The respondents have also been awarded Rs.30,000/-

towards the restoration cost and, Rs.21,118/- as maintenance

charges for the period April 01, 2003 to February 14, 2005.

It is apparent from what has been noticed above that the two

questions of fact, which arose before the arbitrator with regard to the

original condition of the flat and the date on which the possession was

actually handed over to the respondents, have been decided by the

arbitrator against the appellant and in favour of the respondents. The

rest of the award was only consequential and the respondents became

entitled to the claims as raised by them because those claims flowed

from the findings of fact given by the arbitrator. It is well settled that

FAO No.72/2007 Page 6 of 7
the decision of the arbitrator upon the question of facts is final and

binding on the parties and the Court shall not re-appreciate the

evidence led before the arbitrator. It has been conclusively held by

the Apex Court in the case of Oil & Natural Gas Corporation Ltd.

Versus SAW Pipes Ltd. reported in AIR 2003 SC 2629 that an arbitral

award can be set-aside if it is against the public policy of India or if it

is contrary to the fundamental policy of Indian law; the interest of

India; or justice or morality; or if it is patently illegal. The award in

question does not fall within the ambit of any of the aforesaid grounds

as have been laid down by the Supreme Court. I find no merit in the

appeal. The same is dismissed, with no order as to costs.

The appellant has already deposited in this Court the awarded

amount. The Registrar General is directed to release the amount

along with interest that has accrued thereon in favour of the

respondents on their making an application for releasing the same.

REKHA SHARMA, J.

MAY 20, 2010
ka

FAO No.72/2007 Page 7 of 7