Supreme Court of India

Bihar State Mineral Dev. Corpn. & … vs Encon Builders (I) Pvt. Ltd on 21 August, 2003

Supreme Court of India
Bihar State Mineral Dev. Corpn. & … vs Encon Builders (I) Pvt. Ltd on 21 August, 2003
Author: S.B. Sinha
Bench: Cji, S.B. Sinha.
           CASE NO.:
Appeal (civil)  2025 of 1997

PETITIONER:
Bihar State Mineral Dev. Corpn. & Anr.		


RESPONDENT:
Vs.

Encon Builders (I) Pvt. Ltd.				


DATE OF JUDGMENT: 21/08/2003

BENCH:
CJI & S.B. Sinha.


JUDGMENT:

J U D G M E N T

S.B. SINHA, J :

The appellants before the High Court are in appeal before us

against the judgment and order dated 10.9.1996 passed by the High Court

of Patna, Ranchi Bench, Ranchi, in Misc. Appeal No.176 of 1995 (R)

dismissing an appeal preferred by the appellants herein purported to be

in terms of Section 39(1)(i) of the Arbitration Act, 1940 (‘the Act’

for short), against an order dated 11.9.1995 passed by the Subordinate

Judge-VI, Ranchi, allowing Arbitration (Misc.) Case No.39 of 1995 filed

by the respondent herein.

The basic fact of the matter is not in dispute. Appellant No.1

herein invited tender for removal of soil, sandstone, shale,

conglomerates/coal etc. and stacking it up to a distance of 1. k.m.

Pursuant to or in furtherance of the notice inviting tender issued by

Appellant No.1, the respondent herein submitted his tender which was

accepted. According to the appellants, the respondent failed and

neglected to produce 10,000 M.T. of coal per month and stack the same

in the dump yard which was the subject-matter of the agreement dated

17.3.1992, as a result whereof the balance job was got done by another

agency.

According to the appellants by reason of the aforementioned acts

of omission and commission on the part of the respondent, it suffered a

huge loss. The agreement of the respondent, however, was not expressly

cancelled by Appellant No.2 herein. The respondent herein allegedly

invoked the purported arbitration agreement contained in the said

agreement dated 17.3.1992.

Clauses 37, 59 and 60 which, according to the appellants, are

relevant for the purpose of this case read thus :

“37. It will be at the absolute discretion of the

Managing Director of the Corporation to terminate the

agreement in the following events :

a. If the excavation work is found to be

unsatisfactory.

b. If the agency be involved in any action

involving moral turpitude.

c. If the agency be involved in any action causing

breach of peace indiscipline at the Mines or

stops the work before the expiry of the

agreement period.

d. If the agency fails to comply with any of the

terms and conditions contained herein or that

would be mutually agreed upon for the execution

of the work.

e. If the agency fails to pay full wages to

workmen as per prevailing act/awards from the

management premises and in presence of

Corporation authorised representative.

Before terminating the agreement, one month’s

notice under registered post on the address

given in this agreement will be given to the

agency without prejudice to the right and claim

under the agreement and the corporation; will

have the right to adjust such amount towards

the financial loss that corporation might incur

due to such acts or commissions of the agency

from bills or security deposit or earnest

deposit or through other legal proceedings.”

59. If during course of inspection or on

reports of officers of the Corporation the

Managing Director finds that the working

operation are not carried out in a workman like

manner or payments to workmen are not made

timely and according to provisos of the rules

and regulations he may impose fine on the

agency up to a maximum of rupees five thousand

at a time depending on the gravity of the

violations.

60. In case of any dispute arising out of the

agreement, the matter shall be referred to the

Managing Director, Bihar State Mineral

Development Corporation Limited, Ranchi, whose

decision shall be final and binding.”

The respondent also allegedly made claim against the appellants.

The disputes were said to have been referred to Appellant No.2 herein

purported to be in terms of clause 60 of the said agreement. But who

referred the said dispute and how it was done is not borne out from the

records.

Allegedly, 22.6.1995 was the date fixed for hearing of the matter

before Appellant No.2 which was subsequently adjourned to 6.7.1995.

The respondent herein questioned the validity of clause 60 of the

agreement by a letter dated 15.7.1995.

It thereafter filed an application under Section 33 of the Act in

the Court of the Subordinate Judge-VI, Ranchi. The said application

was allowed by the learned Subordinate Judge, by reason of an order

dated 11.9.1995, whereby and whereunder, Appellant No.2 was restrained

from acting as an Arbitrator. The learned Judge further held that

clause 60 of the agreement cannot be construed to be an arbitration

agreement.

Aggrieved thereby and dissatisfied therewith, the appellants

preferred an appeal before the High Court. By reason of the impugned

judgment, the said appeal was dismissed. The appellants are in appeal

before us against the said judgment.

Mr. Dinesh Dwivedi, learned senior counsel appearing on behalf of

the appellants, would submit that the courts below committed manifest

illegality in passing the impugned judgment insofar as they held that

clause 60 of the agreement does not constitute an arbitration agreement

as the same satisfies the definition thereof as contained in Section

2(a) of the Act, insofar as it contains the following essential

elements of an arbitration agreement, namely, (a) the agreement is in

writing; (b) the agreement is to submit a present or a future

difference; (c) dispute is to be referred to a named arbitrator; and

(d) the decision of the arbitrator is final.

The learned counsel would contend that as the essential elements

of arbitration are satisfied from clause 60 of the agreement, it was

not necessary to specifically use the terminology ‘arbitration’

therefor and no particular form is required therefor. Reliance in this

connection has been placed on Smt. Rukmanibai Gupta vs. The Collector,

Jabalpur and others [AIR 1981 SC 479].

The learned counsel would further submit that the High Court

further erred insofar as it failed to take into consideration the fact

that an employee of the Principal can be named as an arbitrator

wherefor bias on his part cannot be presumed. Strong reliance in this

behalf has been placed on The Secretary to the Government, Transport

Deptt., Madras vs. Munuswamy Mudaliar and others [AIR 1988 SC 2232],

State of U.P. vs. Tipper Chand [(1980) 2 SCC 341], K.K. Modi vs. M.N.

Modi & Ors. [JT 1998 (1) SC 407], Michael Golodetz and Others vs.

Serajuddin and Co. [AIR 1963 SC 1044] and State of Orissa and Others

vs. Narain Prasad and Others [(1996) 5 SCC 740].

The short question which arises for consideration in this appeal

is as to whether the learned court below committed an illegality in

refusing to refer the matter to arbitration.

The essential elements of an arbitration agreement are as follows

:

(1) There must be a present or a future difference in

connection with some contemplated affair.

(2) There must be the intention of the parties to settle

such difference by a private tribunal.

(3) The parties must agree in writing to be bound by the

decision of such tribunal.

(4) The parties must be ad idem.

There is no dispute with regard to the proposition that for the

purpose of construing an arbitration agreement, the term ‘arbitration’

is not required to be specifically mentioned therein. The High Court,

however, proceeded on the basis that having regard to the facts and

circumstances of this case, the arbitration agreement could have been

given effect to. We may, therefore, proceed on the basis that Clause

60 of the Contract constitutes an arbitration agreement.

A finding has been arrived at by the High Court that the Second

Appellant was the only competent authority to arrive at his

satisfaction that the agreement was liable to be terminated. By reason

of the power conferred upon the Managing Director of Appellant No.1, he

is also entitled to impose fine on the contractor depending upon the

gravity of violation of the agreement.

The respondent would contend that although the agreement was not

expressly terminated, the work had illegally been re-allotted to

another agency by the second appellant. The correctness or otherwise of

the said decision on the part of the second appellant was in question.

The High Court, therefore, arrived at a finding that as for all intent

and purport the agreement was terminated by Appellant No.2, he could

not assume the role of an arbitrator.

There cannot be any doubt whatsoever that an arbitration

agreement must contain the broad consensus between the parties that the

disputes and differences should be referred to a domestic tribunal.

The said domestic tribunal must be an impartial one. It is a well-

settled principle of law that a person cannot be a judge of his own

cause. It is further well-settled that justice should not only be done

but manifestly seen to be done.

Actual bias would lead to an automatic disqualification where the

decision maker is shown to have an interest in the outcome of the case.

Actual bias denotes an arbitrator who allows a decision to be

influenced by partiality or prejudice and thereby deprives the litigant

of the fundamental right to a fair trial by an impartial tribunal.

The case at hand not only satisfies the test of real bias but

also satisfies the real danger as well as suspicion of bias. [See

Kumaon Mandal Vikas Nigam Ltd. vs. Girja Shankar Pant and Others

[(2001) 1 SCC 182].

In Judicial Review of Administrative Action, by De Smith, Woolf

and Jowell (Fifth Edition at page 527), the law is stated in the

following terms :

“The various tests of bias thus range along a

spectrum. At the one end a court will require that,

before a decision is invalidated, bias must be shown

to have been present. At the other end of the

spectrum, the court will strike at the decision where

a reasonable person would have a reasonable suspicion

from the circumstances of the case that bias might

have infected the decision. In between these

extremes is the “probability of bias” (this being

closer to the “actual bias” test), and the

“possibility of bias” (this being closer to that of

reasonable suspicion)”.

In “The Law and Practice of Commercial Arbitration in England by

Sir Michael J. Mustill and Stewart C. Boyd, it is stated :

“Since the general principles of law relating

to bias apply in the same way to arbitrations as to

other tribunals, and since instances which are

sufficiently serious to bring about the intervention

of the Court are very rare indeed, there is no need

to deal with the subject in detail.”

In ‘Russell on Arbitration’, 22nd Edition, the law is

stated thus :

“4-030 Actual and apparent bias. A distinction is

made between actual bias and apparent bias. Actual

bias is rarely established, but clearly provides

grounds for removal. More often there is a suspicion

of bias which has been variously described as

apparent or unconscious or imputed bias. In such

majority of cases, it is often emphasized that the

challenger does not go so far as to suggest the

arbitrator is actually biased, rather that some form

of objective apprehension of bias exists.

4-032 Pecuniary interest. There is an automatic

disqualification for an arbitrator who has a direct

pecuniary interest in one of the parties or is

otherwise so closely connected with the party that

can truly be said to be a judge in his own cause.

5-052 Impartial. Section 33(1) of the Arbitration

Act 1996 states that the tribunal must act

“impartially”. An arbitrator must also appear

impartial and if there are justifiable doubts as to

his impartiality this will provide a ground for his

removal by the court under section 24(1)(a) of the

Arbitration Act 1996 or may mean that the award can

be challenged.”

Mr. Dwivedi placed strong reliance in Munuswamy Mudaliar’s case

(supra). In that case an application under Section 5 of the Act was

filed. Furthermore, the fact of the said case is not applicable in the

present case inasmuch as therein actual work by the contract did not

start. In that situation, the risk and cost clause was invoked. The

only contention raised therein was that as the said clause was invoked

by the Chief Engineer; the Superintending Engineer being an inferior

authority to him would not be in a position to dispense with the

justice effectively. It was, in that situation, held by this Court as

under :

“This is a case of removal of a named arbitrator

under S.5 of the Act which gives jurisdiction to the

Court to revoke the authority of the arbitrator.

When the parties entered into the contract, the

parties knew the terms of the contract including

arbitration clause. The parties knew the scheme and

the fact that the Chief Engineer is superior and the

Superintending Engineer is subordinate to the Chief

Engineer of the particular Circle. In spite of that

the parties agreed and entered into arbitration and

indeed submitted to the jurisdiction of the

Superintending Engineer at that time to begin with,

who, however, could not complete the arbitration

because he was transferred and succeeded by a

successor. In those circumstances on the facts

stated no bias can reasonably be apprehended and made

a ground for removal of a named arbitrator. In our

opinion this cannot be, at all, a good or valid legal

ground. Unless there is allegation against the named

arbitrator either against his honesty or capacity or

mala fide or interest in the subject-matter or

reasonable apprehension of the bias, a named and

agreed arbitrator cannot and should not be removed in

exercise of a discretion vested in the Court under

S.5 of the Act.”

Such is not the position here.

In Serajuddin’s case (supra), this court was concerned with an

application under Section 34 of the Arbitration Act. It was held :

“…The Court insists, unless sufficient reason to

the contrary is made out upon compelling the parties

to abide by the entire bargain, for not to do so

would be to allow a party to the contract to

approbate and reprobate, and this consideration may

be stronger in cases where there is an agreement to

submit the dispute arising under the contract to a

foreign arbitral tribunal…”

It was further observed :

“…The Court ordinarily requires the parties to

resort for resolving disputes arising under a

contract to the tribunal contemplated by them at the

time of the contract. That is not because the Court

regards itself bound to abdicate its jurisdiction in

respect of disputes within its cognizance : it merely

seeks to promote the sanctity of contracts, and for

that purpose stays the suit…”

In the said case, the question of bias on the part of the

arbitrator did not fall for consideration.

In Narain Prasad’s case (supra), this Court was not dealing with

an arbitration matter but with the conduct of the parties in relation

to enforcement of a contract in a liquor vend. Therein the respondent

filed a writ petition for coming out his contractual obligation and in

the said fact situation obtaining therein this Court observed :

“…A person who enters into certain contractual

obligations with his eyes open and works the entire

contract, cannot be allowed to turn round, according

to this decision, and question the validity of those

obligations or the validity of the Rules which

constitute the terms of the contract. The

extraordinary jurisdiction of the High Court under

Article 226, which is of a discretionary nature and

is exercised only to advance the interests of

justice, cannot certainly be employed in aid of such

persons. Neither justice nor equity is in their

favour”.

In K.K. Modi’s case (supra), clause 9 of a memorandum of

agreement came up for consideration, which was in the following terms :

“Implementation will be done in consultation with the

financial institutions. For all disputes,

clarifications etc. in respect of implementation of

this agreement, the same shall be referred to the

Chairman, IFCI or his nominees whose decisions will

be final and binding on both the groups.”

It was held that the same did not constitute an arbitration

clause.

Yet again in Tipper Chand’s case (supra) whereupon reliance has

been placed by Mr. Dwivedi, the following clause was not held to be

an arbitration clause :

“For any dispute between the contractor and the

Department the decision of the Chief Engineer PWD

Jammu and Kashmir, will be final and binding upon the

contract.”

As in the instant case, the test of bias on the part of Appellant

No.2 is fully satisfied, the impugned order is unassailable. As bias on

the part of the second Appellant goes to the root of his jurisdiction

to act as an arbitrator, the entire action is a nullity.

As the acts of bias on the part of the second appellant arose

during execution of the agreement, the question as to whether the

respondent herein entered into the agreement with his eyes wide open or

not takes a back-seat. An order which lacks inherent jurisdiction

would be a nullity and, thus, the procedural law of waiver or estoppel

would have no application in such a situation.

It will bear repetition to state that the action of the second

appellant itself was in question and, thus, indisputably he could not

have adjudicated thereupon in terms of the principle that nobody can be

a judge of his own cause.

Furthermore, as the learned Subordinate Judge, inter alia, held

that clause 60 did not constitute an arbitration agreement, the same

could not have been the subject-matter of an appeal under Section

39(1)(i) of the Act inasmuch as thereby the arbitration agreement was

not superseded.

For the reasons aforementioned, there is no merit in this appeal

which is dismissed. As the respondent did not appear, there shall be

no order as to costs.