High Court Jharkhand High Court

Binod Kumar @ Binod Kumar Bhag vs M/S S.K.Distributors & Ors on 12 September, 2011

Jharkhand High Court
Binod Kumar @ Binod Kumar Bhag vs M/S S.K.Distributors & Ors on 12 September, 2011


    IN THE HIGH COURT OF JHARKHAND AT RANCHI               
                                         Arbitration Appeal No.1  of  2009    

            M/s Luxmi  Industries, Lohardaga                …..Appellant        
Versus 
   M/s Steel Authority of India Ltd. New Delhi & anr…… Respondents
  
                   
                                                      
                                           CORAM : HON’BLE THE CHIEF JUSTICE  
                                                                        …..   

                            For the Appellant      : Mr.Atanu Banerjee,Adv.

                                  For the Respondents           : Mr.Ananda Sen,Adv.
                                                       
                                                                                    th
                                                                          Dated­ 12     September , 2011 

         By Court­    This appeal has been preferred under Section 37 of the 

Arbitration & Conciliation Act, 1996 against the order dated   19th 

December, 2008 passed by the court of Sub Judge­II, Lohardaga in 

Title   Arbitration   Suit   No.17   of   2005,   whereby   the   objection 

submitted by the appellant has been dismissed.

2. Learned counsel for the appellant submitted that the learned 

Arbitrator did not award the interest over the delayed payment of 

the   earnest   money.   However,   it   appears   from   the   award   that   at 

internal page­12 of the award  , the learned Arbitrator has awarded 

the interest on earnest money deposited by stating that appellant 

shall be entitled to interest @ 10% per annum on 1st January, 1997 

to   the   date   of   award   on   the   delayed   payment   of   earnest   money. 

There is a reference of the claim of the appellant with respect to 

interest on account of the delayed payment of earnest money, which 

had been taken note of by the learned Arbitrator at page­5 , in item 

no.4. Therefore, if the amount of the earnest money has been paid 

to   be   appellant   after   it   became   due   then   he   has   been   awarded 

interest @ 10% per annum. Therefore, in view of the above reasons, 

I   do   not   find   the   contention   of   the   appellant   that   it   has   been  
2.

denied interest over the late payment of earnest money. If petitioner 

has   not  get  yet  the   said   amount,  it  is   free   to  get  the   amount  by 

executing the award.

3. Learned counsel for the appellant raised doubt because of the 

reason that Arbitrator observed “amounts found due”  and, therefore, 

it may be made clear that the amounts found due by the Arbitrator 

is in relation to the earnest money amount, which has been found 

due in the award. The claim of appellant is based on Clause 4.5.3 of 

the Annual Booking Scheme. This apprehension of the appellant has 

no basis because of the reason that  awarding of interest on delayed 

payment of  the  earnest money and acceptance of the  plea of the 

contractor­appellant that it is entitled to interest @ 10% on delayed 

payment of earnest money, clearly indicate that such right of interest 

over the delayed payment of earnest money has been recognized. 

Therefore,   if   there   is   a   confusion,   now   it   stands   clarified   by   this 

order. 

4. In view of the above reasons, the appeal of the appellant is 

disposed of with the above observation.

   

                ( Prakash Tatia, C.J.)

                                                                                                       
G.Jha/