High Court Kerala High Court

C.Balan Nair vs Kerala State Electricity Board on 23 June, 2009

Kerala High Court
C.Balan Nair vs Kerala State Electricity Board on 23 June, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 26907 of 2004(C)


1. C.BALAN NAIR,
                      ...  Petitioner
2. JOSEPH K.THOMAS, AGED 47 YEARS,

                        Vs



1. KERALA STATE ELECTRICITY BOARD,
                       ...       Respondent

2. THE DEPUTY CHIEF ENGINEER (APTS),

3. THE EXECUTIVE ENGINEER,

4. THE EXECUTIVE ENGINEER,

5. THE ASSISTANT EXECUTIVE ENGINEER,

6. THE ASSISTANT ENGINEER,

                For Petitioner  :SRI.KKM.SHERIF

                For Respondent  :SRI.K.S.ANIL, SC, KSEB

The Hon'ble MR. Justice ANTONY DOMINIC

 Dated :23/06/2009

 O R D E R
                       ANTONY DOMINIC, J.
                     ================
                 W.P.(C) NO. 26907 OF 2004 (C)
                 =====================

            Dated this the 23rd day of June, 2009

                           J U D G M E N T

First petitioner is the landlord and the second petitioner is

the tenant. In the building, the tenant is running a hotel and is

availing of supply of electricity with three consumer numbers.

2. The Anti Power Theft Squad of the Board had

conducted an inspection of the premises on 17/10/2001 and

Ext.P1 series are the three mahazars prepared. In all the three

consumer numbers, unauthorised additional load of 2 KW, 23KW

and 12 KW respectively were found. Accordingly, Ext.P2 series of

bills were issued and the 1st petitioner filed Ext.P3 appeal to the

2nd respondent. The appeal was rejected as per Ext.P7. It is

challenging Ext.P7 the writ petition is filed.

3. The contention raised by the counsel for the petitioners

is confined to the levy of twice the energy charges as penalty in

addition to fixed charges at 3 times. It is stated that such levy is

not contemplated under Regulation 42 and 43 of the Conditions of

Supply of Electrical Energy. Counsel also placed reliance on the

judgment of this Court in George Joseph v. K.S.E.B (2008(4)

WPC 26907/04
:2 :

KLT 610).

4. On the other hand, the counsel for the Board referred

me to the tariff order of 2002, in terms of which, according to her,

fixed charge plus energy charge is leviable. It is therefore

submitted that energy charges cannot be separated from fixed

charges when penalty is to be levied. Reference is also made to

the judgment of the Apex Court in Municipal Corporation,

Delhi v. Asian Art Printers (P) Ltd. (AIR 1995 SC 196) where

the Apex Court has accepted the contention identical to the one

raised by the counsel for the Board referring to the tariff order

issued by the Municipal Corporation, Delhi. Counsel for the Board

also placed considerable reliance on the judgment rendered by

the Division Bench of this Court in WA No.1231/2003, where

according to the counsel, the Division Bench has accepted the

competence of the Board to levy twice the energy charges as

penalty prior to 18/9/2002 when the Board issued a notification

reducing the penalty on detection of unauthorised additional load.

5. A reading of Ext.P2 series of invoices show that the

petitioner has been penalised both by levying fixed charges and

also energy charges. The dispute in this writ petition is confined

WPC 26907/04
:3 :

to the levy of energy charges only.

6. In so far as levy of penalty is concerned, that is

governed by Clauses 42 and 43 of the Conditions of Supply of

Electrical Energy. In the judgment in George Joseph v. K.S.E.B

(2008(4) KLT 610) referred to by the counsel for the petitioner

interpreting Clause 43 of the Conditions of Supply, a learned

Judge of this Court has held that such penalty is leviable only in

the case of theft of energy. In this case also, neither in the

mahazar or elsewhere, is there a case for the Board that there has

been theft of energy committed by the petitioners. If that be so,

Clause 43 is inapplicable to the case of the petitioners.

7. However Clause 42(d) of the Conditions of Supply of

Electrical Energy provides that in cases where the consumer

exceeds the contract load without the prior permission of the

Board, that amounts to misuse of energy and the consumer is

liable to be billed at thrice the rate applicable for the respective

tariff. Regular energy bill having already been issued ,as per the

impugned demand, twice the energy charges are demanded.

8. In my view, this is a case where the contract load has

been exceeded by the petitioner. If that be so, the levy of penalty

WPC 26907/04
:4 :

as done by Ext.P2 bill is permissible in terms of Clause 42(d) of

the Conditions of Supply of Electrical Energy. However, illegality

in the uniform levy of penalty as provided under Clause 42(d) of

the Conditions of Supply has already engaged the attention of a

Division Bench in the judgment in WA 1231/2003 where the

Division Bench has directed that the Board shall examine each of

the cases and decide on the penalty to be levied depending upon

the culpability of the consumer concerned.

9. It is now informed that the benefit of this judgment has

been uniformly made applicable by issuing general directions. If

that be so, necessarily, the petitioner should also get the benefit

of such reduction. It is therefore, directed that the respondents

shall rework the liability of the petitioner and after giving credit to

the amount already remitted by the petitioner pursuant to the

interim orders of this Court, the balance, if any, will be demanded

and paid by the petitioner.

Writ petition is disposed of as above.

ANTONY DOMINIC, JUDGE
Rp