High Court Kerala High Court

Chodoth Koya vs Administration Of The Ut Of on 9 December, 2009

Kerala High Court
Chodoth Koya vs Administration Of The Ut Of on 9 December, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 35389 of 2009(P)


1. CHODOTH KOYA, CONTRACTOR,
                      ...  Petitioner

                        Vs



1. ADMINISTRATION OF THE UT OF
                       ...       Respondent

2. THE SUPERINTENDING ENGINEER,

3. THE EXECUTIVE ENGINEER,

                For Petitioner  :SRI.K.B.GANGESH

                For Respondent  :SRI.S.RADHAKRISHNAN,SC,LAKSHADWEEP ADMN

The Hon'ble MR. Justice P.N.RAVINDRAN

 Dated :09/12/2009

 O R D E R
                           P.N.RAVINDRAN, J.
                           ---------------------------
                       W.P.(C) No. 35389 OF 2009
                            --------------------------
                Dated this the 9thday of December, 2009

                             J U D G M E N T

By Ext.P1 tender notice dated 16.9.2009, the third respondent

invited tenders for various items of works. The petitioner submitted his

tender in respect of the work described as item No.6 in Ext.P1 tender

notice. Four other persons had also submitted tenders. The rate quoted

by the petitioner was Rs.300/- below the probable amount of contract.

However, the third respondent rejected all the tenders and decided to

invite a fresh tender. Ext.P2 letter was thereupon sent to the petitioner

informing him that his tender has been rejected. He was also requested

to collect the earnest money deposited by him. The petitioner thereupon

sent Ext.P3 representation to the Administrator of the Union Territory of

Lakshadweep. The petitioner did not challenge Ext.P2 in this Court at that

stage. Later, the third respondent issued Ext.P4 tender notice dated

24.11.2009 inviting fresh tenders for the very same item of work. The last

date for obtaining the tender forms was 7.12.2009 and the last date for

submission of tenders was 10.11.2009. The petitioner did not apply for

tender documents. Instead he sent Ext.P5 letter to the Administrator of

the Union Territory of Lakshadweep requesting him to interfere and cancel

the rejection of his tender. This writ petition was thereafter filed on

8.12.2009 challenging Exts.P2 and P4 and seeking a writ in the nature of

W.P.(C) No. 35389/09
2

mandamus commanding respondents 1 to 3 to accept the tender submitted

by the petitioner pursuant to Ext.P1 in respect of the work described in

serial No.6 therein. The petitioner contends that as his tender was the

lowest, the respondents erred in rejecting his tender. He contends that no

valid reasons whatsoever has been set out in Ext.P2 to reject his tender

and therefore, the decision taken by the respondent to re-tender the work is

arbitrary and illegal.

2. I have considered the submissions made at the Bar by the

learned counsel appearing for the petitioner. The tender submitted by the

petitioner pursuant to Ext.P1 in respect of the work descried in item No.6

therein was rejected and the decision was communicated to him on

7.10.2009. He did not immediately challenge Ext.P2 in this Court. Instead,

he send a letter to the Administrator, Union Territory of Lakshadweep

requesting him to award the work to him. The work was re-tendered as

per Ext.P4 notification. Ext.P1 and P2 will show that besides the work

described in item No.6 of Ext.P1 tender notice, the work described in item

No.5 of Ext.P1 was also re-tendered. Therefore, it cannot be said that the

re-tendering has been resorted to solely with a view to eliminate the

petitioner. In my opinion, there is nothing in Ext.P2 which disentitled the

petitioner from participating in the tender pursuant to Ext.P4. However, for

the reasons best known to him, he did not apply for the tender documents.

W.P.(C) No. 35389/09
3

Instead he has chosen to challenge Exts.P2 and P4 in this Court

contending that as his tender was the lowest and below the probable

amount of contract, it ought to have been accepted. It is settled law that

the tendering authority is not bound to accept the tender merely for the

reason that it is the lowest.

3. In such circumstances, as the petitioner had no vested right

for the award of the work. I find no reason to interfere with Ext.P2. The

tendering authority is the best judge of the situation. In the absence of any

proof that the decision to reject the petitioner’s tender was rested on

extraneous considerations, I find no ground to interfere with the re-

tendering process.

I accordingly hold that there is no merit in the writ petition. The

writ petition fails and is dismissed.

P.N.RAVINDRAN, JUDGE

vps