High Court Punjab-Haryana High Court

Dayanand Etc vs State Of Haryana And Others on 25 March, 2009

Punjab-Haryana High Court
Dayanand Etc vs State Of Haryana And Others on 25 March, 2009
      IN THE HIGH COURT OF PUNJAB AND HARYANA AT
                           CHANDIGARH.

                                             C.W.P. No.4730 of 2009
                                           Date of decision: 25.3.2009
Dayanand etc.
                                                        -----Petitioners
                                  Vs.
State of Haryana and others.
                                                      -----Respondents
CORAM:- HON'BLE MR JUSTICE ADARSH KUMAR GOEL
        HON'BLE MR JUSTICE JITENDRA CHAUHAN

Present:-   Mr. Mani Ram Verma, Advocate
            for the petitioners.
             -----

ORDER:

1. This petition seeks a mandamus for payment of

compensation with interest for the land which has been utilised for

constructing the Alampur Patodi Minor and for quashing letter dated

29.1.2009, Annexure P-6.

2. Case set out in the petition is that land of the petitioners

was utilised by the State for construction of Alampur Patodi Minor in

the year 1986. On 5.8.2008, the petitioners served Legal Notice,

which has been replied vide letter dated 29.1.2009, stating that the

work of construction of canal was started in the year 1986 and after

point at RD 6500, the same was shifted to another place. The land

beyond RD 6500 which belonged to the petitioners, was not required.

Compensation was paid for land upto RD 6500, but the State did not

require the land beyond RD 6500 and therefore, it was not

considered necessary to acquire the said land.

3. We have heard learned counsel for the petitioners.
C.W.P. No.4730 of 2009

2

4. Learned counsel for the petitioners submitted that

possession of land of the petitioner was taken in the year 1986 and

the land was utilised, though the same was not being now used by

the State. The petitioners have suffered loss and therefore, a

direction be issued for acquiring the land and for payment of

compensation.

5. As regards the alleged action of taking possession of the

land of the petitioners in the year 1986, we are of the view that the

issue cannot be gone into, at this stage, after 23 years, particularly

when the land is no longer in possession of the State nor needed by

the State and the petitioners slept over the matter for such a long

period.

6. As regards direction for acquisition, we are unable to hold

that there is any legal right to seek such a relief.

7. Only issue that survives is whether the petitioners are

entitled to compensation for any damage by any action of the State.

This issue will require adjudication of disputed facts, for which this

petition is not the appropriate remedy. If the petitioners are so

aggrieved, they will be at liberty to take their remedies in accordance

with law.

8. The petition is disposed of.


                                            ( ADARSH KUMAR GOEL )
                                                    JUDGE

March 25, 2009                               ( JITENDRA CHAUHAN )
ashwani                                               JUDGE