Bombay High Court High Court

In vs Companies Act on 30 June, 2008

Bombay High Court
In vs Companies Act on 30 June, 2008
Bench: R.M.S. Khandeparkar, P. B. Majmudar
                                                    -1-




                                                                                          
                                                                 
                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY

                           ORDINARY ORIGINAL CIVIL  JURISDICTION




                                                                
                                    APPEAL NO. 1229 OF 2001
                                         IN
                    ARBITRATION PETITION NO. 416 OF 2001
                                         IN




                                                   
                            AWARD NO. 24 OF 2001.
                                 ig        
    Oil and Natural Gas Corporation Limited,      )
    Bombay Regional Business Centre,              )
    Vasudhara Bhavan, Bandra (East),              )
                               
    Mumbai-400 051                                )..Appellants

                  versus
       


    Dai Ichi Karkaria Limited,                                            )
    a Public Company incorporated under the                               )
    



    Companies Act, 1956, having its Registered Office                     )
    at Liberty Building, Sir Vithaldas Thackersey Marg,                   )
    Mumbai-400 020                                                        )..Respondents





    Sri   Dara   Zaiwala,  Senior  Advocate,  with  Sri  K.H.  Mody   and  Ms.  Chandini
    Prakash, instructed by Little & Co., for the appellants.

    Mr. D.J. Khambatta, Senior Advocate, with Sarvasri Zuber Behram Kamdin,
    Vivek   Vashi   and   Ms.   Anuradha   Agnihotri,   instructed   by   Bharucha   &





    Associates for the respondents.

                                                        CORAM:  SRI        R.M.S. KHANDEPARKAR
                                                                                                   &
                                                                         SRI P.B. MAJMUDAR, JJ. 

                                              DATE:     JUNE 30, 2008




                                                                  ::: Downloaded on - 09/06/2013 13:32:20 :::
                                                    -2-

    JUDGMENT (Per Sri P.B. Majmudar, J.)

This appeal is directed against the judgment and order dated 14th

August, 2001, of the learned single Judge passed in Arbitration Petition No.

416 of 2001 by which the learned single Judge modified the award of the

Arbitrator to the extent of rate of interest provided by the Arbitrator by

reducing the same from 12 per cent to 10 per cent from February, 1993 upto

the date of the award. The rest of the award was confirmed by the learned

single Judge.

2. The facts in a nutshell are as under:

2.1 The respondent, Dai Ichi Karkaria Limited, is a Public Limited

Company incorporated under the Companies Act, 1956, having its registered

office in Mumbai. The respondent-claimant carries on business of

manufacture and sale, inter alia, of Pour Point Depressant (“PPD” for short).

The appellant is a Public Sector Undertaking engaged in oil exploration,

development, production and treatment of oil and natural gas. The appellant

floated a global tender for supply of 2,450 metric tons of PPD and ultimately

the tender of the respondent was accepted and the appellant placed a supply

order dated 2nd April, 1988 on the respondent. The respondent agreed to

supply 2,450 metric tons of PPD at the aggregate rate of Rs. 8,19,10,850/-

plus sales tax as applicable. Clause 29 of the supply order provided that the

::: Downloaded on – 09/06/2013 13:32:20 :::
-3-

appellant shall be entitled to place with the respondent repeat order for 50

per cent of the quantity of the supply order at the same price and on the

same terms and conditions as stipulated in the supply order during the validity

of the supply order or within six months from the date of supply order,

whichever was later.

2.2 The appellant by its letters dated 13th April, 1988 and 3rd May,

1988 agreed that in case there was any Government notification allowing

exchange rate fluctuation, the same should be complied with in accordance

with the provisions therein. The appellant agreed to this aspect pursuant to

the request made in this behalf by the respondent. Since the foreign

exchange fluctuation had occurred in the meanwhile, the respondent

requested the appellant to raise the price by absorbing the foreign exchange

fluctuation. Correspondence ensued between the parties in that behalf. The

appellant, however, refused to comply with the request made by the

respondent and on 12th June, 1989, the appellant placed a repeat order at

the same price and on the same terms and conditions as the original supply

order without providing for foreign exchange fluctuation or assuring the

respondent that its case would be referred to the concerned Ministry as per

the circular issued by the Government of India, Ministry of Finance. Following

upon the repeat order dated 12th June, 1989, a formal repeat order with some

minor amendments was placed by the appellant on the respondent on 26th

::: Downloaded on – 09/06/2013 13:32:20 :::
-4-

February, 1990 and this amended repeat order also did not accept the

request of the respondent to absorb foreign exchange fluctuation and insisted

on maintaining the same price as set out in the original supply order.

2.3 The respondent was not prepared to accept the amended repeat

order dated 26th February, 1990, as it was of the view that under the circular

of the Government of India, Ministry of Finance, the appellant was bound to

absorb the foreign exchange fluctuation or at least to forward the case of the

respondent to the concerned Ministry with its recommendation. Thereafter

negotiations went on between the parties in this regard and in the course of

negotiations, the appellant acceded to the request of the respondent for

revised price of PPD and to give foreign exchange fluctuation by its telex

dated 27th July, 1990. The appellant thereafter by its letter dated 28th July,

1990 forwarded to the respondent certain amendments to the repeat order

dated 26th February, 1990. These amendments related, inter alia, to the

dates of delivery of PPD at Nhava Seva site of the appellant and the foreign

exchange content for metric ton of PPD and also increased the price to Rs.

39,287.44 per metric ton from the original price of Rs. 33,433.51 per metric

ton. The letter dated 28th July, 1990 made it clear that all other terms and

conditions of the repeat order dated 26th February, 1990 will remain

unaltered. The respondent, however, not prepared to accept the amended

repeat order dated 28th July, 1990, since the amendments did not fully

::: Downloaded on – 09/06/2013 13:32:20 :::
-5-

concede the request made by the respondent in its letters dated 14th June,

1990 and 5th July, 1990, and accordingly the said repeat order dated 28th July,

1990 was not accepted by the respondent which resulted into further

negotiations between the appellant and the respondent. Considerable

correspondence ensued between the parties and in the course of which the

appellant addressed a letter dated 31st January, 1992 clarifying its position in

regard to the various issues. The appellant also set out a new delivery

schedule for supplies of PPD without imposing liquidated damages, as a

special case, and accordingly as per the new delivery schedule, delivery was

to commence at 350 Metric ton per month from February, 1992 onwards.

The appellant also made it clear that the respondent may accept 4 per cent

price reduction if new specifications were to be applied or in the alternative

the respondent may supply material as per the specifications indicated in the

original supply order. The appellant also requested the respondent to convey

its option immediately so that the supply order could be amended suitably, if

necessary. The respondent by its letter dated 4th February, 1992, reiterated

its contention that it was entitled to the benefit of foreign exchange

fluctuations. Accordingly, the proposal made by the appellant in its letter

dated 31st January, 1992 was not accepted by the respondent. This resulted

into further negotiations between the parties and ultimately an amended

repeat order dated 12th October, 1992 was issued by the appellant which

was accepted by the respondent. As per the aforesaid amended order dated

::: Downloaded on – 09/06/2013 13:32:20 :::
-6-

12th October, 1992, a clause was incorporated to the effect that “other terms

and conditions of the subject order will remain unaltered”. So far as the

orders dated 26th February, 1990 and 28th July, 1990 are concerned, both

expressly stated that the sales tax was payable as “extra as applicable”.

There was no delivery schedule specified in the amended order dated 12th

October, 1992. The respondent actually completed the supplies under the

amended order dated 12th October, 1992 by February, 1993.

2.4 While making payment of the price for the supplies made by the

respondent, the appellant deducted an aggregate sum of Rs. 24,06,356.00

towards liquidated damages for delay in supplying PPD. The appellant also

refused to grant foreign exchange fluctuations to the respondent and also

failed to reimburse the difference of 6 per cent in sales tax payable under the

Maharashtra Sales Tax Act which had increased from 4 per cent to 10 per

cent with effect from 1st June, 1992. The respondent thereupon sought

arbitration in respect of its claim against the appellant in accordance with the

provisions in that behalf contained in the original supply order and the matter

was referred to the sole Arbitrator to adjudicate upon the claim of the

respondent.

2.5 Parties filed their respective pleadings before the Arbitrator and

after hearing the parties, the learned Arbitrator came to the conclusion that

::: Downloaded on – 09/06/2013 13:32:20 :::
-7-

since no time for delivery was specified in the amended order dated 12th

October, 1992, it is implied that the supplies should be made within

reasonable time from the date of amended order. The sole Arbitrator found

that the respondents had complied with this obligation and complied delivery

of the supplies by February, 1993 and that there was no delay on the part of

the respondent in making supplies of PPD to the appellant and, therefore,

appellant was not entitled to deduct any amount by way of liquidated

damages from the price payable to the respondent. The learned Arbitrator

accordingly held that the respondent was entitled to recover the amount of

Rs. 24,06,356/- from the appellant together with interest thereon at the rate

of 12 per cent per annum from February, 1993 upto the date of the Award.

The Arbitrator also granted difference of of 6 per cent sales tax under the

Maharashtra Sales Tax Act on supplies of PPD made by the respondent. The

Arbitrator found that the refusal by the appellant to pay the difference of 6 per

cent by way of sales tax was not justified and accordingly awarded Rs.

28,87,627/- towards the difference in the sales tax together with interest at

the rate of 12 per cent from 28th February, 1993 till the date of the Award.

2.6 So far as original claim of the respondent regarding foreign

exchange fluctuation is concerned, the same was given up by the

respondent before the Arbitrator. The Arbitrator accordingly, by his award

dated 8th March, 2001, awarded an aggregate sum of Rs. 52,93,983/-

::: Downloaded on – 09/06/2013 13:32:20 :::
-8-

together with interest thereon at the rate of 12 per cent from 28th February,

1993 upto the date of the Award and thereafter at the rate of 9 per cent per

annum till payment.

2.7 The appellant instituted Arbitration Petition under Section 30 of the

Arbitration Act, 1940, challenging the award of the sole Arbitrator being

Arbitration Petition No. 416 of 2001. The learned single Judge rejected the

contention of the appellant in connection with the liquidated damages as well

as the payment of difference in connection with the sales tax. The learned

single Judge, however, modified the award to the extent of rate of interest by

reducing interest from 12 per cent as awarded by the Arbitrator to 10 per cent

from February, 1993 upto the date of the Award and the rest of the Award of

the Arbitrator was confirmed and accordingly the Award as modified was

made a decree of the Court.

2.8 It is the aforesaid order of the learned single Judge which is

impugned in this appeal at the instance of the appellant.

3. At the time of hearing of this appeal, the learned counsel

appearing for the appellant attacked the award of the Arbitrator on the

following grounds:

::: Downloaded on – 09/06/2013 13:32:20 :::
-9-

3.1 That in view of the delay in supplying the material, the respondent

was liable to pay liquidated damages and, therefore, the appellant was

justified in withholding the amount in question towards liquidated damages.

3.2 That the appellant was not required to pay the difference in

connection with the increase in the rate of sales tax and the appellant was

required to pay only 4 per cent of the sales tax irrespective of increase of the

same subsequently.

3.3 There is no provision for payment of interest in the contract and

that the Award in connection with the payment of interest is not sustainable

and the respondent was not entitled to get any interest in connection with the

amount awarded by the Arbitrator, and

3. 4 That the award of the Arbitrator is contrary to the terms of the

contract which would necessitate interference of the court on the ground of an

error apparent on the face of record.

4. To substantiate the argument, the learned counsel for the

appellant relied upon the decision of the Supreme Court in the case of Oil

::: Downloaded on – 09/06/2013 13:32:20 :::
-10-

and Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.1. On behalf of the

respondent, the learned counsel has supported the order of the learned

single Judge as well as the Award of the Arbitrator.

5. It is submitted on behalf of the respondent that the powers of the

Court in a petition under Section 30 of the Arbitration Act, 1940 (hereinafter

referred to as “the Act”) is very limited as it is neither an appeal on facts nor

an appeal on law and the Court is required to consider only whether the

Arbitrator has committed an error apparent on the face of record and while

doing so, the Court cannot re-appreciate the evidence on record. It is further

submitted that from the material on record, the respondent has clearly

established that the appellant was not entitled to withhold any amount

towards liquidated damages especially when no delivery schedule was

fixed. It is also submitted that the appellant was bound to reimburse the

difference in the payment of sales tax. On the question regarding grant of

interest, it is submitted that the Arbitrator was within his right in awarding

interest for which a reference was made to the decision of the Supreme Court

in the case of Board of Trustees for the Port of Calcutta vs. Engineers-De-

Space-Age2 , the decision of a single Judge of this Court in the case of Oil and

1 (2003) 5 SCC 705
2 (1996) 1 SCC 516

::: Downloaded on – 09/06/2013 13:32:20 :::
-11-

Natural Gas Commission vs. Macqreqor-Navire Port Equipment and others3 and

the decision of another single Judge of this Court in the case of Oil and

Natural Gas Corporation Ltd. vs. Western Geco International Ltd.4

6. The learned counsel for the appellant relied on the decision of the

Supreme Court in the case of Sikkim Subba Associates vs. State of Sikkim5,

to substantiate the argument on the ground that if there is an error apparent

on the face of record, the order of the Arbitrator can be set aside by the

Court. The Arbitrator having acted beyond his jurisdiction is a ground which

is different from an error apparent on the face of record. The appellant has

also relied upon various other judgments on the ground that if the Arbitrator

has committed any error apparent on the face of record, or if he has

exceeded his jurisdiction, the Court can interfere with such an Award. It is

also submitted that the Arbitrator cannot act arbitrarily, irrationally,

capriciously or beyond the contractual terms.

7. We have heard the learned counsel for the parties. We have

perused the documentary evidence placed on record, the Award of the

Arbitrator as well as the order of the learned single Judge. We have also

3 2002 (1) Bom.C.R. 278
4 2006 (3) Bom.C.R. 848.

5 2001 (2) Arb. LR 17 (SC)17

::: Downloaded on – 09/06/2013 13:32:20 :::
-12-

considered the rival submissions advanced by the counsel appearing for the

parties. The first point which is required to be considered is as to whether

the Arbitrator has exceeded his jurisdiction in awarding the amount deducted

by the appellant towards liquidity damages. After considering the voluminous

documentary evidence on record, the Arbitrator has found that considering

the amended order dated 12th October, 1997, no time limit was fixed for

supply and in that view of the matter there was no delay on the part of the

respondent. It is required to be noted that the appellant at the first instance

placed reliance on the supply order issued to the respondent on 2nd April,

1998. Under clause (6) delivery in respect of that supply order was to be

completed by February, 1989. As per clause 18, the expression used in the

same is that “Sales tax extra as applicable”. Clause 20 provided that in the

event the Contractors failed to deliver or any instalments thereto within the

period fixed for such delivery in the schedule or at any time of contract before

expiry of such period, the purchaser without prejudice to any other remedy

available to him, may recover damages in breach of the contract. Clause 29

provides as under:

“Repeat order can also be placed with the supplier upto 50% of
the quantity of this order on the same terms and conditions as
stipulated in this original supply order during the validity of that
supply order or within 6 months from the date of this supply
order whichever is latter. It is the condition of this order which
will be obligatory on the part of the supplier to execute such
repeat order also as the consideration of this dealing in favour

::: Downloaded on – 09/06/2013 13:32:20 :::
-13-

of the purchaser forms part of the main consideration in its

order.”

8. The appellant thereafter placed repeat order on 13th June, 1989

and the delivery was to be made upto March, 1990. Subsequently

correspondence ensued between the parties. On 31st January, 1992, the

appellant wrote a letter to the respondent informing them that the case of the

respondent had been examined in detail taking into consideration various

letters and that, as a special case, appellant agreed for reimbursement of

excise duty on production of proof of payment of excise duty. The said letter

further states that the delivery was to commence against the order at the rate

of 150 metric tonnes per month from February, 1992 onwards.

9. So far as the delivery schedule set out in the letter dated 31st

January, 1992 is concerned, the same was never accepted by the

respondent as the respondent did not accept the proposal contained in the

said letter dated 31st January, 1992. It resulted into further correspondence

between the parties. In our view, therefore, the Arbitrator was perfectly

justified in holding that the delivery schedule set out in the letter dated 31st

January, 1992 did not bind on the respondent and on the contrary

negotiations went on between the parties and ultimately on 12th October,

1992 an amended order was agreed to between the parties. It has been

rightly held by the Arbitrator that liabilities of the parties in regard to supplies

::: Downloaded on – 09/06/2013 13:32:20 :::
-14-

of PPD came to be governed exclusively by the amended order dated 12th

October, 1992. The amended order dated 12th October, 1992 made certain

amendments in the “Subject Supply Order”. It is required to be noted that

the subject order referred to the amended repeat orders dated 12th June,

1989, 26th February, 1990 as amended by the amendment repeat order dated

26th July, 1990 did not make any reference to the appellant’
s letter dated 31st

January, 1992. Considering the said documents on record, the Arbitrator

found that no delivery schedule was set out in the amended order dated 12th

October,1992 and, therefore, ultimately it was required to consider whether

the supply was made within reasonable time from the date of the amended

order dated 12th October, 1992 and the Respondent ultimately completed the

delivery of supplies by February, 1993. On the aforesaid basis it was found

that there was no unreasonable delay on the part of the respondent in

supplying the material and that the appellant, therefore, was not entitled to

deduct any amount towards liquidated damages from the price payable to the

respondent for the supplies made to the appellant. In our view, considering

the aforesaid factual aspect of the matter and considering the fact that after

voluminous correspondence ensued between the parties, it can never be

said that the Arbitrator has exceeded his jurisdiction or has misdirected

himself in coming to the conclusion that the appellant was not entitled to

withhold any amount towards liquidated damages from the price payable to

the respondent. It is required to be noted that in a petition under Section 30

::: Downloaded on – 09/06/2013 13:32:20 :::
-15-

of the Act, the Court is not sitting in appeal over the Award of the Arbitrator.

The Court while examining the objections taken to an award filed by the

Arbitrator is not required to examine the correctness of the claim on merits

with reference to the materials produced before the Arbitrator. This Court can

interfere with the Award, if the Arbitrator has exceeded his jurisdiction or has

committed an error apparent on the face of record in interpreting the contract

and that the award is contrary to the terms of the contract.

10. The learned Arbitrator after considering the documents and

clauses contained in the contract between the parties has held that there was

no delay on the part of the respondent in supplying the material and,

therefore, appellant was not entitled to withhold the amount towards

liquidated damages. It is not in dispute that there was no time specified in the

amended order dated 12th October, 1992 for supply of material in question as

ultimately the respondent started supplying the material to the appellant

under the amended repeat order dated 12th October, 1992. In our view, the

learned Arbitrator has not committed any error apparent on the face of record

on this aspect and, therefore, the contention of the appellant, therefore, in this

behalf is rejected.

11. So far as the claim regarding difference in the payment of sales

tax is concerned, it is to be noted that the sales tax payable on the date of

::: Downloaded on – 09/06/2013 13:32:20 :::
-16-

delivery of the supplies was 10 per cent, since supplies were made after 1st

June, 1992. The Arbitrator has rightly found that the appellant was not

justified in reimbursing the claim towards the sales tax only to the extent of 4

per cent as at the time when the supply was made, the sales tax payable was

10 per cent as per Maharashtra Sales tax Act. The appellant was

accordingly bound to reimburse the total amount paid by the respondent

towards Sales Tax. As the sales tax was to be borne by the purchaser and if

there is change in the quantum of sales tax in between, whatever amount

paid by the respondent towards sales tax, the entire amount towards the

same was reimbursed and accordingly the Arbitrator has rightly awarded the

difference of 6 per cent of payment of sales tax. It cannot be said that the

Arbitrator has committed any error much less any error of law or any other

error apparent on the face of record while awarding the said amount. The

learned counsel for the appellant has placed reliance on the decision of the

Supreme Court in the case of Associated Engineering Company vs.

Government of Andhra Pradesh and another6 wherein the Supreme Court has

held in paragraph 24 as under:

“24. The arbitrator cannot act arbitrarily, irrationally,
capriciously or independently of the contract. His sole
function is to arbitrate in terms of the contract. He has no
power apart from what the parties have given him under the
contract. If he has travelled outside the bounds of the

6 (1991) 4 SCC 93

::: Downloaded on – 09/06/2013 13:32:20 :::
-17-

contract, he has acted without jurisdiction. But if he has

remained inside the parameters of the contract and has
construed the provisions of the contract, his award cannot be
interfered with unless he has given reasons for the award

disclosing an error apparent on the face of it”.

In the case of Saw Pipes (supra) the Supreme Court has held that if an

award is contrary to substantive provisions of law or the provisions of the Act

of 1940 or against the terms of contract, it would be patently illegal and the

same would be subject to interference under Section 34 (2) (a) (v) of the Act

of 1940. On the other hand, the learned counsel for the respondent has

referred to a decision rendered by a Division Bench of this Court to which

one of us (R.M.S. Khandeparkar, J.) is a party in Appeal No. 1202 of 1997

(Oil and Natural Gas Corporation Ltd. vs. Dai Ichi Karkaria Ltd. The Division

Bench after considering various judgments of the Supreme Court,

summarised the propositions as under:

“(i) A Court while examining the objections taken to an award
filed by an Arbitrator is not required to examine the
correctness of the claim on merits with reference to the
materials produced before the Arbitrator. The Court cannot sit
in appeal over the views of the Arbitrator by re-examining and

re-assessing the material;7

(ii) The Arbitrator is constituted by the parties to be a final
arbiter of the disputes between them and the award is not
open to challenge on the ground merely that the Arbitrator has
reached a wrong conclusion or that he has failed to appreciate
facts;8

(iii) If there is no legal proposition either in the award or in
7 Puri Construction Pvt. Ltd. v. Union of India, AIR 1989 SC 777 (pages 13 and 14 at pages 782 and 783.

8 Hindustan Tea Co. v. K. Shashikant & Co., AIR 1987 SC 81 (para 2 at page 82)

::: Downloaded on – 09/06/2013 13:32:20 :::
-18-

any document annexed to the award which is erroneous and

which constitutes the basis of the award and the alleged
mistakes or errors are only mistakes of fact, the award is not
amenable to correct by the Court;9

(iv) Even assuming that there is an error of construction of
an agreement, or an error in law in arriving at a conclusion,
such an error is not an error which is amenable to correction in

a reasoned award. In order to set aside an award, there must
be a wrong proposition of law laid down in the award which
constitutes the basis of the award;10

(v) The reasonableness of the reasons furnished by
the Arbitrator in making his award cannot be challenged. The

fact that on the same evidence, a Court might have arrived at
a conclusion different from the one arrived at by the Arbitrator
is by itself no ground for setting aside the award;11

(vi) The application of the error apparent on the face of
the record test does not empower the Court exercising
jurisdiction under Section 30 to substitute the scrutiny by the

Arbitrator by an evaluation of the Court of the merits of the
documents and the materials on record. If the view of the

Arbitrator is a possible view, the reasons in the award cannot
be examined. Issues relating to a default in the performance
of contractual obligations; of whether time was of the essence
and of the assessment of the quantum of damages are issues

of fact and it is not open to the Court to interdict an award on
such factual issues;12

(vii) If the Arbitral Tribunal has committed an error of
fact or law in reaching its conclusion on a disputed question

submitted for adjudication, the Court would have no jurisdiction
to interfere with the Award. This would depend upon the
reference made to the Arbitrator. In a general reference for
deciding a contractual dispute, the Court could interfere if the
award is based on an erroneous legal proposition. In a
reasoned award, the Court can interfere if on the face of the
award, there is an erroneous proposition of law or application.

9 Jawaharlal Wadhwa v. Haripada Chakroberty, AIR 1989 SC 606 (para 6 at page 610)
10 U.P. Hotels v. U.P. State Electricity Board, AIR 1989 SC 268 (paras 17 and 19 at pages 274 and 275).
11 Delhi Municipal Corporation vs. M/s. Jagan Nath Ashok Kumar, AIR 1987 SC 2316.
12 Arosan Enterprises Ltd. v. Union of India, AIR 1999 SC 3804 (para 36 page 3819 and para 38 page 3820).

::: Downloaded on – 09/06/2013 13:32:20 :::
-19-

However, if a specific question of law is submitted to the

Arbitrator an erroneous decision therein would not render the
award bad unless the Arbitrator has proceeded illegally;13

(viii) The Court exercising jurisdiction under Section 30
of the Arbitration Act, 1940 is not entitled to probe the mental
process of the Arbitrator and where no reasons have been
furnished as to what impelled the Arbitrator to arrive at his

conclusion, the reasonableness of the reasons and the
appraisal of evidence are matters which lie in a realm of
arbitration. The Court does not take upon itself the task of
being a judge on the evidence before the Arbitrator. The error

apparent test does not empower the Court to invalidate an
award merely because by a process of interference and

argument, it may be demonstrated that the Arbitrator has
committed some mistake in arriving at a conclusion;14

(ix) An award may be remitted or set aside on the
ground that the Arbitrator making it had exceeded his
jurisdiction and evidence of matters not appearing on the face
of award will be admitted in order to establish whether or not

the jurisdiction has been exceeded, because the nature of the
dispute is something which has to be decided outside the

award. The Arbitrator having acted beyond jurisdiction is a
ground which is different from an error apparent on the face of
the award. However, a distinction in such a case must be
drawn between an error within the jurisdiction and an error in

excess of jurisdiction. While the Court may examine the
claims to find out whether they were within the disputes
referred to the Arbitrator, it is not open for the Court to find out
whether in arriving at the decision, an Arbitrator has acted
correctly or incorrectly. Hence, whether a particular amount

was liable to be paid or damages liable to be sustained was a
decision within the competence of the Arbitrator;15

(x) An Arbitrator cannot act arbitrarily, irrationally,
capriciously or independently of the contract. His sole function
is to arbitrate in terms of the contract. An Arbitrator who travels
outside the bounds of the contract, acts without jurisdiction.
However, so long as he remains within the parameters of the

13 ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 (para 54 page 736)
14 Sudarshan Trading Co. v. Govt. of Kerala, AIR 1989 SC 890 (para 29 page 901)
15 Sudarshan Trading (supra) Para 31 page 902.

::: Downloaded on – 09/06/2013 13:32:20 :::
-20-

contract and construes the provisions of the contract, the

award cannot be interfered with unless he has given the
reasons for the award disclosing an error apparent on the face
of it;16

(xi) The authority of the Arbitrator is derived from the
contract and he commits a misconduct if by his award, he
decides a matter excluded by the agreement. A conscious

disregard of the law or of the provisions of the contract from
which the Arbitrator has derived his authority vitiates the
award. An error in the construction of the contract is an error
within jurisdiction but an Arbitrator who travels outside the

contract commits a jurisdictional error.17″

After going through the award of the Arbitrator and after going through the

material on record, in our view, it cannot be said that the Arbitrator has

committed any error apparent on the face of record or that he has travelled

beyond the agreement between the parties in coming to the conclusion that

the appellant was not entitled to withhold any amount by way of liquidated

damages as ultimately the material was supplied within the reasonable time

and that the appellant was required to pay the difference in sales tax. The

Arbitrator reached the said conclusion after interpreting the agreement

entered into between the parties and it cannot be said that he has travelled

beyond the contract.

12. So far as the award of the Arbitrator granting interest is concerned,

in our view, the award of the Arbitrator in this regard is not sustainable. In
16 Associated Engineering Co. v. Govt. of A.P. (1991) 4 SCC 93 (para 24 page 103).
17 Associated Engineering Co. v. Govt. of A.P. (1991) 4 SCC 93 (paras 25 and 27 page 103).

::: Downloaded on – 09/06/2013 13:32:20 :::
-21-

this connection, it is relevant to mention clause 27 of the supply order dated

26th February, 1990, which provides as under:

“It is agreed term of the contract/supply order that the sum of
money or monies so withheld or retained under the lien

referred to above, by the Commission will be kept withheld or
retained as such by the Commission till the claim arising out of
or under the contract is determined by the Arbitrator (if the
contract is governed by the arbitration clause) or by the

competent court, as the case may be, and that the contractor
will have no claim for interest or damages whatsoever on

any account in respect of such withholding or retention under
the lien referred to supra and duly notified as such to the
Contractor. For the purpose of this clause, where Contractor is

a partnership firm or a limited Company, the Commission shall
be entitled to withhold and also have a lien to retain towards
such claimed amount or amounts in whole or in part from any
such sum payable to any partner or director of a limited

company, as the case may be, whether in his individual
capacity or otherwise”.

In view of the above, it is amply clear that the respondent was not entitled to

claim any interest. In that view of the matter and especially when the

agreement nowhere provides that the Arbitrator will be entitled to adjudicate

the claim of interest, the award of the Arbitrator suffers from patent illegality

in so far as the award of payment of interest is concerned. The Supreme

Court in the case of Oil and Natural Gas Corporation Ltd. vs. Saw Pipes Ltd.18

which was a matter arising under the Act of 1996 has held as under:

“It is to be reiterated that it is the primary duty of the
arbitrators to enforce a promise which the parties have made
18 (2003) 5 SCC 705

::: Downloaded on – 09/06/2013 13:32:21 :::
-22-

and to uphold the sanctity of the contract which forms the

basis of the civilized society and also the jurisdiction of the
arbitrators. Hence, this part of the award passed by the
Arbitral Tribunal granting interest on the amount deducted by

the appellant from the bills payable to the respondent is
against the terms of the contract and is, therefore, violative of
Section 28 (3) of the Act.”

13. The appellant has also relied upon a decision of the learned

single Judge of this Court in the case of Oil and Natural Gas Commission vs.

McDermott International Inc19 wherein the learned single Judge has

considered the payment of interest under the Act of 1940. The learned single

Judge has held in paragraph 50 of the said judgement which considered the

question about award of pre-reference interest that as per the terms of the

contract in that case the interest could be awarded only with regard to the

undisputed amount, and for the disputed amount no interest could be

granted. The respondent on the other hand has relied upon the decision of

the Supreme Court in the case of Board of Trustees for the Port of Calcutta

(supra). The said decision is under the Act of 1940. The Supreme Court in

the said case has considered the question of payment of interest in regard to

the award of the interest by the Arbitrator post reference. In paragraph 4 it

has been held that after considering the clause in the contract by which the

Commissioner was prohibited from entering any claim of interest, the

Supreme Court has held that by the particular clause, the Commissioner was

19 2000 (3) Mh.L.J. 747

::: Downloaded on – 09/06/2013 13:32:21 :::
-23-

prohibited from entering any claim of interest but it does not mean that the

Arbitrator was also prohibited from awarding interest pending dispute. It has

been held that once the matter goes to arbitration the discretion of the

arbitrator is not, in any manner, stifled by the term of the contract and the

arbitrator would be entitled to consider the question of grant of interest

pendente lite and award interest if he finds the claim to be justified. The

Supreme Court has accordingly considered the payment of interest pendente

lite. So far as the facts of the present case is concerned, there is nothing on

record to show that the parties had agreed on the question of payment of

interest for the period prior to the reference. On the contrary, the agreement

speaks otherwise. Considering the factual aspect of the matter, in our

considered opinion, the arbitrator has exceeded his jurisdiction in awarding

the amount with interest which covers the payment prior to the making of the

reference. As a matter of fact, even as per the clause which we have quoted

above, no amount of interest was payable at all. Interpreting the said clause

and considering the factual aspect of the matter and the provisions of the Act

of 1940, in our view, the arbitrator has acted beyond his jurisdiction and,

therefore, part of the award in granting interest to the respondent is without

jurisdiction. The order of the Arbitrator is therefore clearly without jurisdiction

and accordingly the order of the arbitrator is modified to the extent of setting

aside the same in so far as it relates to payment of interest upto the date of

the award regarding pre-reference period as well as pending the reference.

::: Downloaded on – 09/06/2013 13:32:21 :::
-24-

However, we confirm the order of the learned single Judge in granting

interest from the date of the Award.

14. The grant of interest upto the date of award is accordingly set

aside by modifying the order of the arbitrator. The respondent will be entitled

to get interest from the date of the Award at the rate of 10 per cent.

Accordingly, this appeal is partly allowed by modifying the award to the

aforesaid extent. The order of the learned single Judge is also set aside to

the aforesaid extent and the order passed by this Court is accordingly made

a decree of the Court.

R.M.S. KHANDEPARKAR, J.

P.B. MAJMUDAR, J.

::: Downloaded on – 09/06/2013 13:32:21 :::