Delhi High Court High Court

Indian Bank vs Gawri Construction Udyog Ltd & Ors on 17 October, 2011

Delhi High Court
Indian Bank vs Gawri Construction Udyog Ltd & Ors on 17 October, 2011
Author: V. K. Jain
         THE HIGH COURT OF DELHI AT NEW DELHI
%                          Judgment Reserved on:   03.10.2011
                           Judgment Pronounced on: 17.10.2011

+ CS(OS) 864/1999

INDIAN BANK                                              ..... Plaintiff
                       Through          Ms. Seema Gupta, Adv.

                                         versus

GAWRI CONSTRUCTION UDYOG LTD & ORS
                                ..... Defendants
           Through Mr. M.L. Mahajan and Mr.
                   Gaurav Mahajan, Advs.



+ CS(OS) 865/1999

INDIAN BANK                                               ..... Plaintiff
                       Through          Ms. Seema Gupta, Adv.

                                         versus

GAWRI CONSTRUCTION UDYOG LTD & ORS
                                   ..... Defendants
           Through Mr. M.L. Mahajan and Mr.
                   Gaurav Mahajan, Advs.

                                         AND
+ CS(OS) 985/1999

INDIAN BANK                                              ..... Plaintiff
                       Through          Ms. Seema Gupta, Adv.

                                         versus

GAWRI CONSTRUCTION UDYOG LTD & ORS
                                   ..... Defendants
           Through Mr. M.L. Mahajan and Mr.
                   Gaurav Mahajan, Advs.


CS(OS)No.864/1999, 865/1999, 985/1999                            Page 1 of 37
 CORAM:-
HON'BLE MR JUSTICE V.K. JAIN

1.

Whether Reporters of local papers may
be allowed to see the judgment? Yes

2. To be referred to the Reporter or not? Yes

3. Whether the judgment should be reported Yes
in Digest?

V.K. JAIN, J

1. By this common judgment, I will dispose of all the

three suits and counter-claim referred above. Defendant No.

1 entered into construction-cum-agreements dated 23rd

April, 1990 with the plaintiff-bank for construction on

various properties. The sale deed was to be executed within

30 days from the date of giving possession to the plaintiff.

Under the agreement, defendant No. 1 was to pay all taxes

on the properties subject matter of the agreements till

possession was delivered to the plaintiff-bank. The

agreement provided for payment of penalty to the plaintiff-

bank at the rate of 0.5% of the total sale consideration

subject to ceiling of 7.5% of the total consideration if

possession of the flats, to be constructed by defendant No.

1, is delayed beyond 18 months from the date of the signing

of the agreement. The bank was entitled to rescind the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 2 of 37
agreement in case of delay beyond 15 weeks and in that

case the amount disbursed by it was recoverable with

interest from the date of disbursement.

2. Suit No. 864/1999 pertains to construction of 10

flats on Property No. C-17, Inder Puri. Suit No. 865/1999

pertains to construction of 12 flats of Property No. C-12,

Inder Puri. Suit No. 985/1999 pertains to construction of 12

flats of Property No. C-10, Inder Puri. Since defendant No. 1

has not executed the sale deeds in respect of the flats

constructed by it, despite delivering their possession to the

plaintiff, a decree for specific performance of the agreement

by directing defendant No. 1 to execute sale deed in respect

of the building constructed by it on the aforesaid plots has

been sought in all the three suits. In Suit No. 864/1999,

the plaintiff has also claimed a sum of Rs 5.20 lakh which it

claims to have paid as arrears of property tax for the period

prior to handing over of possession to the plaintiff which it

has paid to Municipal Corporation of Delhi. It is also

alleged that the plaintiff-bank has adjusted a sum of Rs

2,76,765/- towards price variation and liquidated damages

and a sum of Rs 50,000/- is payable by it to the defendant

which it is ready and willing to pay after settlement of the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 3 of 37
accounts. .In Suit No. 865/1999, the plaintiff has, besides

execution of the sale deed in his favour, also sought a

direction to defendant No. 1 install meters in every flat,

constructed by it. It is alleged that since possession of the

flats was delayed by defendant No. 1, it was liable to pay a

penalty of Rs 39,000/- which the plaintiff-bank has already

adjusted. According to the bank, it was required to pay a

sum of 19,033/- to the defendant which it is ready and

willing to pay. In Suit No. 985/1999, the plaintiff has, in

addition to execution of the sale deed in his favour, has also

sought recovery of Rs 1108.76/-, being the excess amount

paid to defendant No. 1. It is alleged that defendant No. 1 is

liable to pay a sum of Rs 36,400/- for delay in handing over

the possession which the plaintiff-bank has already

adjusted.

3. The suit has been contested by defendants No. 1

and 2 who have taken a preliminary objection that the suit

is bad for mis-joinder of defendants No. 2 and 3, who are

neither a necessary nor a proper party to the suit. They

have also denied the competence of Mr M.S. Parthasarthy to

sign and verify the pleadings and institute the suit on behalf

of the plaintiff-bank. They have also claimed that the suit is

CS(OS)No.864/1999, 865/1999, 985/1999 Page 4 of 37
barred by limitation and is not properly valued for the

purpose of Court fee and jurisdiction. On merits, it is

alleged that defendant No.1 has also been ready and willing

to execute the sale deed and it is the plaintiff which is guilty

of breach of terms of the agreement, as they have failed to

pay the amount due to the defendants.

4. As regards the claim of the plaintiff for the amount

paid by it to MCD towards arrears of property tax, it is

alleged that no house tax was payable when the building

was under construction and, therefore, the claim of the

Corporation for the years 1988-89, 1989-90, 1990-91 and

1991-92 was without any basis and the plaintiff had no

right to deal with the demand of MCD without involving the

defendants. In Suit No. 865/1999, the defendants have

denied their liability to pay any penalty to the plaintiff and

have claimed that it was the plaintiff which was responsible

for the delay in construction. It is also alleged that the

defendants are also entitled to interest on the amount of

Rs19,033/- which the plaintiffs admit to be payable to

defendant No. 1 and the amount of interest comes to Rs

33,878/-. In Suit No. 985/1999 defendants have denied

their liability to pay the amount of Rs 36,400/- which the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 5 of 37
plaintiff claims to have adjusted.

5. A counter-claim of Rs 41,38,901/- had been filed

by defendant No. 1 in Suit No. 864/1999. It is alleged that

vide letters dated 13th August, 1988 and 1st January, 1990,

the plaintiff-bank accorded sanction for purchasing 33 flats

comprised in Property No. C-15, C-10 and C-12, Inder Puri

and 20 flats comprised in Property No. C-17 and C-40, Inder

Puri. However, on the suggestion of the plaintiff-bank, five

different agreements were executed. It is alleged that the

plaintiff made payment of Rs 22.35 lakh towards

construction of flats on Property No. C-40, Inder Puri. It is

alleged that the plaintiff-bank failed to approve the plan for

further construction as a result of which, construction

could not be started. The defendant raised a loan of Rs 1

crore from the bank. Since the sanction for the plans was

not forthcoming from the plaintiff-bank, defendant No. 1

requested it either to return the balance duly sanctioned or

cancel the agreement. While making payment towards

construction of flats, the plaintiff-bank adjusted the sum of

Rs 22.35 lakh which it had paid towards construction on

Property No. C-40, Inder Puri along with interest amounting

to Rs 11.77 lakh. It is alleged that defendant No. 1 was

CS(OS)No.864/1999, 865/1999, 985/1999 Page 6 of 37
forced to agree to the adjustments since original documents

were with the plaintiff bank and it was not ready to part

with them unless the aforesaid amount was adjusted

against the other amounts payable by the bank in respect of

other properties. Defendant No. 1 claimed that amount of

Rs 11.77 lakh along with interest on that amount which

comes to Rs 19.94 lakh. The defendants have also claimed

interest amounting to Rs 50,944/- on the liability of Rs

19,003/- admitted by the plaintiff-bank and Rs 1,23,500/-

towards interest on the liability of Rs 50,000/-. The

defendants have also claimed a sum of Rs 7,91,927/-

towards interest on delayed payment.

6. The following issues were framed on the pleadings

of the parties:-

i. Is shri M.S. Parthasathi, Assistant General Manager is

competent to sign verify and institute these suits on

behalf of the plaintiff bank?

ii. Are the suits of the plaintiff bad for misjoinder of the

defendants, as alleged in para 1 of the preliminary

objections?

iii. Are the suits being properly valued for the purposes of

court fee and jurisdiction? If not, with what effect?

CS(OS)No.864/1999, 865/1999, 985/1999 Page 7 of 37
iv. Are the suits of the plaintiff within time?

v. Did the plaintiff entered into only one transaction in

respect of 33 flats comprised in plot Nos. C-15, C-10

and C-12, Inder Puri, New Delhi and 20

flats comprised in plot Nos. C-17 and C-40, Inder Puri,

New Delhi.

vi. Whether the defendants have failed to complete all

legal formalities including obtaining completion

certificate in respect of the premises? OPP

vii. Whether there are some illegal and unauthorized

constructions made by the defendant and whether the

defendants are liable either to get the

buildings regularized or to pay damages for the loss to

be suffered by the plaintiff? OPP

viii. In view of the agreement to sell whether the defendants

can refuse execution of sale deed in favour of the

plaintiff? OPD

ix. Whether the defendants are entitled to receive any

amount from the plaintiff? If so, what amount? OPD

x. Whether the counter claim, arising out of a separate

contract, can be claimed in this suit by the

defendants? OPD

CS(OS)No.864/1999, 865/1999, 985/1999 Page 8 of 37
xi. Relief.

Issue No. 1

7. Mr M.S. Parthasarthy, who has signed and verified

the pleadings and instituted this suit on behalf of the

plaintiff-bank, filed his affidavit by way of evidence and was

partly examined on 23rd October, 2007. He was not

produced thereafter and the plaintiff-bank examined PW-3

Shri P.R. Pujari, Chief Manger with the plaintiff-bank. Mr

Pujari has identified the signature of Mr M.S. Parthasarthy

on the plaint and has also proved the copy of Power of

Attorney in favour of Mr M.S. Parthasarthy which is Ex.PW-

1/2 and which has been executed by Mr M.

Gopalakrishnan, Chairman and Managing Director of the

plaintiff-bank at the relevant time. A perusal of the Power of

Attorney Ex.PW-3/2 would show that vide this document,

Mr M.S. Parthasarthy was authorized to take all legal

proceedings whether civil or criminal for recovering and

receiving the debts of the bank and to institute, file and

prosecute all actions, including civil suits on behalf of the

plaintiff-bank. He was also authorized to sign, verify and file

vakalatnama, written statement, etc. on behalf of the

plaintiff-bank. The power of attorney purports to be

CS(OS)No.864/1999, 865/1999, 985/1999 Page 9 of 37
executed by the Chairman and Managing Director as well as

the Director and General Manager of the plaintiff-bank and

authenticated by public notary. Since, the power of

attorney in favour of Mr M.S. Parthasarthy has been

attested by Public Notary, there is a statutory presumption

under Section 85 of Evidence Act that the Power of Attorney

was executed by the person by whom it purports to have

been executed and the person who executed the power of

attorney was fully competent in this regard.

8. In Jugraj Singh and Anr. Vs. Jaswant Singh and

Ors., AIR 1971 SC 761, the Power of Attorney attested by a

Public Notary was disputed on the ground that it did not

show on its face that the Notary had satisfied himself about

the identity of the executant. Supreme Court held that there

was a presumption of regularity of official acts and that the

Notary must have satisfied himself in the discharge of his

duties that the person who was executing it was the proper

person. In Rajesh Wadhwa vs. Sushma Govil, AIR 1989,

Delhi 144, it was contended before this Court that till it is

proved that the person who signed the said power of

attorney was duly appointed attorney, the court cannot

draw a presumption under Section 57 and 85 of the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 10 of 37
Evidence Act. Repelling the contention, it was held by this

Court that the very purpose of drawing presumption under

Sections 57 and 85 of the Evidence Act would be nullified if

proof is to be had from the foreign country whether a

particular person who had attested the document as a

Notary Public of that country is in fact a duly appointed

Notary or not. When a seal of the Notary is put on the

document, Section 57 of the Evidence Act comes into play

and a presumption can be raised regarding the genuineness

of the seal of the said Notary, meaning thereby that the said

document is presumed to have been attested by a

competent Notary of that country.

In Punjab National Bank vs. Khajan Singh, AIR

2004 Punjab and Haryana 282, the Power of Attorney in

favour of a bank, which had been duly attested, was

rejected by the learned District Judge on the ground that

the presumption under Section 85 of Evidence Act was

available to a particular class of Power of Attorneys

described in the section and was confined to its execution

and authenticity alone. The High Court, however, rejected

the view taken by the learned District Judge holding that

absence of proof of resolution authorizing the executant to

CS(OS)No.864/1999, 865/1999, 985/1999 Page 11 of 37
execute the Power of Attorney could not be sustained and a

presumption in favour of the attorney would arise under

Section 85 Act. In United Bank of India v. Naresh Kumar

& Ors. (1996) 6 SCC 660, which was a suit instituted by a

bank, the issue which came up for consideration before the

Supreme Court was as to whether the plaint was duly

signed and verified by a competent person or not. The suit

in that case was instituted by one Mr. L.K.Rohatgi. The

Supreme Court noted that the suit had been filed in the

name of the appellant bank; full amount of the Court fee

had been paid by the bank; documentary as well as oral

evidence had been led on behalf of the appellant bank and

the trial of the suit had continued for about 02 years.

Supreme Court found it difficult in these circumstances,

even to presume that the suit had been filed and tried

without the appellant having authorized the institution of

the same. The Court felt that the only conclusion which it

could come to was that Shri L.K.Rohtagi must have been

authorized to sign the plaint and in any case it must be held

that the bank had ratified the action of Shri L.K.Rohtagi in

signing the plaint and therefore it continued with the suit.

During the course of the judgment, the Court inter alia

CS(OS)No.864/1999, 865/1999, 985/1999 Page 12 of 37
observed as under:

Reading Order 6 Rule 14 together with
Order 29 Rule 1 of the Code of Civil
Procedure it would appear that even in the
absence of any formal letter of authority or
power of attorney having been executed a
person referred to in Rule 1 of Order 29
can , by virtue of the office which he holds,
sign and verify the pleadings on behalf of
the corporation. In addition thereto and
dehors Order 29 Rule 1 of the Code of Civil
Procedure, as a company is a juristic
entity, it can duly authorize any person to
sign the plaint or the written statement on
its behalf and this would be regarded as
sufficient compliance with the provisions
of Order 6 Rule 14 of the Code of Civil
Procedure. A person may be expressly
authorized to sign the pleadings on behalf
of the company, for example by the Board
of Directors passing a resolution to that
effect or by a power of attorney being
executed in favour of any individual. In
absence thereof and in cases where
pleadings have been signed by one of its
officers a corporation can ratify the said
action of its officer in signing the
pleadings. Such ratification can be
express or implied. The Court can, on the
basis of the evidence on record, and after
taking all the circumstances of the case,
specially with regard to the conduct of the
trial, come to the conclusion that the
corporation had ratified the act of signing
of the pleading by its officer.

CS(OS)No.864/1999, 865/1999, 985/1999 Page 13 of 37

This suit filed on behalf of Indian Bank has been

pending in this Court for the last about 12 years and no one

from the bank has come forward to repudiate this suit

which Mr. M.S.Parthasarthy has filed on behalf of the bank.

In these circumstances, it cannot be said that Mr.

M.S.Parthasarthy was not competent to institute the suit on

behalf of the plaintiff bank.

The issue is decided against the defendants and in

favour of the plaintiff.

Issue No. 2

9. The agreements for construction and sale of the

flats have been executed between plaintiff and defendant

No.1. Hence, the plaintiff has no cause of action against the

other defendants. The suits are bad for mis-joinder of other

defendants. The names of defendants other than defendant

No. 1 are therefore liable to be struck off from the array of

defendants.

The issue is decided accordingly.

Issue No.3

10. The plaintiff bank has paid the requisite Court fee.

No arguments on this issue were advanced. The issue is

decided against the defendants and in favour of the plaintiff.

CS(OS)No.864/1999, 865/1999, 985/1999 Page 14 of 37
Issues No. 5, 6, 8, 9, 10 & 11

11. These issues are inter connected and can be

conveniently decided together.

The main dispute between the parties is with

respect to the amount of Rs 41,38,901/- for which a

counter claim has been filed in CS(OS) No. 864/1999. The

break up counter-claim is a under:

(a) Interest deducted by the plaintiff on the payments

which it had made to defendant No. 1 for

construction of flats in Property No. C-40, Inder

Puri, New Delhi: Rs. 11,77,765/-

(b) Interest on the aforesaid amount of Rs 11,77,765/-

for the period from 27th December, 1992 to 30th

August, 1999: Rs 19,94,765/-




(c)          Interest       on     delayed   payments    made     by     the

             plaintiff-bank:                             Rs 7,91,927/



(d)          Amount payable to defendant No. 1 in respect of

Property No. C-12, Inder Puri along with interest

CS(OS)No.864/1999, 865/1999, 985/1999 Page 15 of 37
on that amount: Rs 50,944/-

(e) Amount to defendant No. 1 in respect of Property

No. C-17, Inder Puri along with interest on that

amount: Rs 1,23,500/-

12. Defendant No.1 had entered into an agreement

with the plaintiff-bank for construction of flats on property

No. C-40, Inder Puri and sale of those flats to it. The case of

the plaintiff, as set out in the counter claim and affirmed in

affidavit by Mr Vipin Gwari, director of the defendant No. 1-

company by way of evidence in this regard, is that the

plaintiff-bank made payment of Rs 22.35 lakh to it for

construction of flats on Property No. C-40, Inder Puri. This

is also the case of defendant No. 1 that construction up to

basement stage was completed by it and the plans for

raising further construction were submitted to the bank for

approval, but the bank failed to take action in this regard

for more than 11 months, despite request by defendant No.

1. Since defendant No. 1 had taken a loan of Rs 1 crore

from Citi Bank to complete the construction, it requested

the bank either to approve the plans or to cancel the

agreement. The bank acceding to the request of defendant

No. 1, cancelled the agreement for construction of flats on

CS(OS)No.864/1999, 865/1999, 985/1999 Page 16 of 37
Property No. C-40, Inder Puri, New Delhi, subject to

payment of interest at the rate of 18% per annum and

adjusted the amount which it had paid to defendant No. 1

along with a sum of Rs 11.77 lakh towards interest. The

adjustment was made out of the amount which had to pay

to defendant No. 1 for construction of other flats. In his

affidavit by way of evidence, Shri Vipin Gwari, Director of

defendant No. 1-company has stated that defendant No. 1

was forced to agree to the adjustment of illegal demand of

interest because original documents of the property were

with the bank, which was not ready to part with them

unless the aforesaid amount was adjusted. Ex.PW-3/D-10

is the letter dated 05th March, 1991, written by defendant

No. 1 to the plaintiff-bank, requesting that either the bank

may get the building constructed as per the sanctioned

plan or it may get the building constructed as per their own

design, at its own risk. It was further requested that in the

event of the bank failing to give an early reply, they suggest

that the bank may cancel the agreement and take back the

amount paid so far. This letter was followed by a reminder

dated 30th March, 1991 which is Ex-PW-3/D-11. Vide

letter dated 22nd June, 1991, Ex.PW-3/D-26, the plaintiff-

CS(OS)No.864/1999, 865/1999, 985/1999 Page 17 of 37
bank, with reference to defendant No. 1’s letter dated 19th

May, 1991, informed defendant No. 1 that its Head Office

had permitted cancellation of the agreement for C-40, Inder

Puri, New Delhi after recovery of the amount paid to it

along with interest. Defendant No. 1 was accordingly

requested to pay back the amount which it had received

from the plaintiff for this project along with interest at the

rate of 18% per annum. Admittedly, defendant No. 1

agreed to adjustment of not only the principal sum which it

had received from the plaintiff-bank for this project, but

also for the interest on that amount. It appears from the

letter dated 16th September, 1992 (Ex.DW-1/8), written by

defendant No. 1 to the plaintiff that it wanted to pay

interest at the rate of 18% per annum from the date of the

cancellation of the agreement, i.e., 22nd June, 1991 to 22nd

September, 1992, which worked out to Rs 5,02,875/-.

Thus, defendant No. 1 at that time made no protest about

payment of interest though it wanted to pay it only from the

date the agreement came to be cancelled. As noted earlier,

the agreement in respect of the flats to be constructed on

Property No. C-40, Inder Puri, New Delhi was cancelled by

the plaintiff-bank on the specific request of defendant No.

CS(OS)No.864/1999, 865/1999, 985/1999 Page 18 of 37

1. The bank cancelled the agreement subject to defendant

No. 1 paying interest at the rate of 18% per annum on the

amount which it had received from the bank. If the

condition imposed by the plaintiff-bank for cancellation of

the agreement, on the request of defendant No. 1, was not

acceptable to it, defendant No. 1 could very well have

refused to accept the cancellation on payment of interest

and could have decided to go ahead with the agreement

which it had executed with the plaintiff-bank. If defendant

No. 1 was suffering any loss on account of the delay on the

part of the bank in approving the building plans, defendant

No. 1 could have sued the plaintiff-bank for damages. If

defendant No. 1 felt that bank had committed breach of the

by not approving the building plans within a reasonable

time, it could have rescinded the agreement between the

parties, instead of requesting the bank to cancel the

agreement and then accepting that cancellation on the

condition imposed by the bank. But, having accepted the

conditional cancellation of the agreement, defendant No. 1

cannot deny its liability to pay interest on the amount

which it had received from the plaintiff-bank. As regards

the stand taken by defendant No. 1 in its letter dated 16th

CS(OS)No.864/1999, 865/1999, 985/1999 Page 19 of 37
September, 1992 (EX-DW-1/8), I am of the view that the

bank was justified in seeking interest from the date it had

made payment to defendant No. 1 towards construction on

Property No. C-40, Inder Puri, New Delhi. In any case, if

this was not acceptable to defendant No. 1, it ought to have

rejected the conditional cancellation, instead of accepting

the adjustments made by the bank. A perusal of Ex.D-A,

which is the letter dated 28th November, 1992 from the

plaintiff-bank, would show that the amount paid by the

plaintiff-bank to defendant No. 1 towards construction of

Property No. C-40, Inder Puri, New Delhi was adjusted in

the following manner:

Date                           Particulars            Amount

21.09.90           By 5% payment on C-15 flats at   3,72,500/-
                   Inderpuri.

19.11.92            By 5% payment towards C-17      2,98,500/-
                   flats Inderpuri.

27.11.92            By adjustment of balance        1,00,000/-
                   of payment towards C-15 flats
                   Inderpuri.


-do-               By payment Recd. From SIDBI by 26,41,765/-
                   Cheque No. 644731 dt. 27.11.92


It is thus evident that defendant No. 1 had

CS(OS)No.864/1999, 865/1999, 985/1999 Page 20 of 37
accepted the adjustments made by the plaintiff-bank. If a

plaintiff-bank was unreasonably withholding the documents

of title of C-40, Inder Puri, defendant No. 1 could have

taken appropriate legal proceedings against the bank for

recovery of those document from it, but, having accepted

the term offered by the plaintiff-bank for cancellation of the

agreement, defendant No. 1 cannot now avoid payment of

interest to the bank on the ground that it was forced to

accept the condition of the bank on account of the original

documents of the property being in possession of the bank.

13. It has come in evidence that the plaintiff-bank has

charged compound interest on the amount which it had

advanced to defendant No. 1 towards construction of flats

on Property No. C-40, Inder Puri at the rate of 18% per

annum. The letter of the plaintiff-bank Ex.PW-3/D-26 does

not stipulate payment of compound interest though it does

stipulate payment of interest at the rate of 18% per annum.

It has also come in evidence that for another project the

bank charged simple interest and not compound interest on

the amount which it had advanced to the builder. A perusal

of the letter dated 08th January, 1993 (EX.PW-3/D-18) sent

by defendant No. 1 to the plaintiff-bank would show that the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 21 of 37
difference between the compound interest and the simple

interest comes to Rs 2.18 lakh. I, therefore, hold that

defendant No. 1 is entitled to payment of Rs 2.18 lakh from

the plaintiff-bank.

14. As regards payment of interest on the aforesaid

amount of Rs 2.18 lakh, the only provision under which

defendant No. 1 can claim interest on this amount is

Section 3 of Interest Act, 1978, which to the extent it is

relevant, provides that in any proceedings for the recovery of

any debt or damages or in any proceedings in which a claim

for interest in respect of any debt or damages already paid is

made, court may, if it thinks fit, allow interest to the person

entitled to the debt or damages or to the person making

such claim, as the case may be, at a rate not exceeding the

current rate of interest: from the date mentioned in this

regard in a written notice given by the person entitled or the

person making the claim to the person liable that interest

will be claimed, to the date of institution of the proceedings.

EX-DW1/10 is the letter dated 22 nd March, 1993

sent by defendant No. 1 to the plaintiff-bank, whereby

defendant No. 1 reiterated the demands which it had been

making to the plaintiff-bank for payments of the amounts

CS(OS)No.864/1999, 865/1999, 985/1999 Page 22 of 37
due to it in respect of the projects at residential flats in

Inder Puri. Regarding payment of interest by the bank, this

letter reads as under:

“Since this period is already over we
demand the Bank to pay the same rate of
interest on all delayed payments since
the signing of the agreement as charged
by the Bank in cases of delayed
possession.”

This letter fulfils the requirement of a notice under

Section 3 of Interest Act. In the facts and circumstances of

the case, I am of the view that plaintiff-bank should pay

interest at the rate of 12% per annum on the aforesaid of Rs

2.18 lakh to defendant No. 1 w.e.f. 8th January, 1993 till

30th August, 1999 which comes to Rs 1,73,819/-

Therefore, defendant No. 1 is entitled to recover

Rs1,73,819/-

15. The case of defendant No. 1 is that the plaintiff-

bank did not make payments as per the schedule fixed in

the agreements and, therefore, it is entitled to interest on

that amount as per the calculations made in the chart

Ex.DW-1/2. I have carefully gone through the agreements

executed between the plaintiff and defendant No. 1. There

is absolutely no provision in the agreements for payment of

CS(OS)No.864/1999, 865/1999, 985/1999 Page 23 of 37
any interest by the plaintiff in case delay in payment on its

part. Since there is no agreement between the parties for

payment of interest on delayed payments, defendant No. 1 is

not entitled to recover any amount from the plaintiff-bank in

this regard.

16. Admittedly, a sum of Rs 1108.71/- is payable by

the plaintiff to defendant No. 1 in respect of flats

constructed on Property No. C-40, Inder Puri, New Delhi, a

sum of Rs 19,032.90 is payable towards balance amount for

the construction of flats on Property No. C-12, Inder Puri

and a sum of Rs 50,000/- is payable to defendant No. 1

being the balance sale consideration towards purchase of

flats constructed on Property No. C-17, Inder Puri, New

Delhi. Defendant No. 1 is entitled to recover these amounts

from the plaintiff-bank. However, no interest is payable by

the plaintiff-bank on these amounts, firstly because there is

no agreement between the parties for payment of interest

on account of delayed payments by the plaintiff-bank and

secondly because as per the agreements between the

parties, 5% of the balance sale consideration was to be paid

on handing over possession along with completion

certificates and though possession has been handed over to

CS(OS)No.864/1999, 865/1999, 985/1999 Page 24 of 37
the plaintiff-bank, there is no evidence of defendant No. 1

having obtained the completion certificate at any time prior

to filing of this suit. I, therefore, hold that defendant No. 1 is

not entitled to interest on these amounts and can recover

only a sum of Rs 70,141.61/- being the aggregate of the

aforesaid sums of Rs 1108.71/-, Rs 19,032.90/-, and Rs

50,000/-.

17. In Suit No. 864/1999, the plaintiff has also

claimed a sum of Rs 5.2 lakh which it had paid to MCD

towards arrears of property tax for the period prior to its

receiving possession of the flats from defendant No. 1. In

this regard, the agreement between the parties provided that

defendant No. 1 shall pay and discharge all rates, taxes,

levies, etc, levied by any other local authority and any other

competent authority on the property subject matter of the

sale, till the possession of the same was handed over to the

bank as stipulated in the agreement. After taking

possession, these charges were to be borne by the plaintiff-

bank. The plaintiff claims to have paid Rs 39,920/- for the

year 1988-89, Rs 50,148 for the year 1989-90, Rs

2,42,140/- for the year 1990-91 and Rs 1,87,640/- for the

year 1991-92 towards arrears of property tax. EX-P-D is

CS(OS)No.864/1999, 865/1999, 985/1999 Page 25 of 37
the notice issued by MCD to defendant No. 1, requiring it to

show-cause why penalty of Rs 1,06,968/- be not imposed

on it on account of its failure to pay arrears amounting to

Rs 6,66,819/-. Vide this notice, defendant No. 1 was

informed that on account of failure on its part to pay the

arrears, by due date, it was being treated as a defaulter

under Section 155 of Delhi Municipal Corporation Act. It

was further informed that in case the amount was not

received by prescribed date along with reply to the notice,

the penalty shall be levied and further action as per Section

156(2), 158 and 162(1) of DMC Act shall follow for effecting

the recovery of the tax, including the amount of penalty.

EX-P-E is the letter dated 09th March, 1998, written by the

plaintiff-bank to MCD informing it that they had purchased

the property from defendant No. 1 in the year 1992 and had

paid property tax from 01.04.1992 to 31.03.1998. MCD

was requested to recover arrears prior to 01.04.1992 from

defendant No. 1. A writ petition being, CW No. 1381/1998,

was also filed by the plaintiff-bank against the MCD,

challenging the show-cause notice dated 04th March, 1998.

In the writ petition, the plaintiff-bank claimed that no action

had been taken by MCD on its representation dated 09th

CS(OS)No.864/1999, 865/1999, 985/1999 Page 26 of 37
March, 1998. The plaintiff-bank undertook to pay the

amount which was found legitimately due and payable to

MCD on account of house tax. The writ petition was

disposed of with the direction to MCD to dispose of the

representation made by the plaintiff-bank after affording

opportunity of hearing to it. It was also directed that if after

hearing the plaintiff-bank, any amount was found due and

payable by the bank, the same would be paid within four

weeks from the date of the order. The entire amount

demanded by MCD was deposited by the plaintiff-bank vide

receipts Ex. P-B along with forwarding letter Ex.P-C.

This is not the case of defendant No. 1 that arrears

of property tax till the date possession was handed over to

the plaintiff-bank, come to less than Rs 5.2 lakh. The case

of defendant No. 1 in this regard is that no property tax was

payable since the building was still under construction at

the relevant time. In my view, defendant No. 1 cannot deny

its liability to pay property tax on the ground that it was not

payable at all to MCD. Since the property in question at the

relevant time stood in the name of defendant No. 1, it was

for defendant No. 1 to challenge the demand raised by MCD.

This is more so when the demand was raised on defendant

CS(OS)No.864/1999, 865/1999, 985/1999 Page 27 of 37
No. 1 and not on the plaintiffs, as is evident from the notice

dated 04th March, 1998. It was not for the plaintiff-bank to

dispute and contest the liability of defendant No. 1 for the

period up to the date possession of the flats was received by

it. In fact, the plaintiff-bank did not have locus standi to

challenge the demand of property tax for the period prior to

receiving possession of the flats from defendant No. 1.

Neither the plaintiff bank was under a legal obligation to

dispute and contest the demand of property tax raised by

MCD against defendant No. 1 nor did it have legal

competence to challenge that demand.

Section 69 of Contract Act, to the extent it is

relevant, provides that a person who is interested in the

payment of money which another is bound by law to pay,

and who therefore pays it, is entitled to be reimbursed by

the other. Therefore, if it can be said that the plaintiff was

interested in payment of property tax, demanded by MCD

and defendant No.1 was bound by law to pay that money to

MCD, it will be entitled to reimbursement of the amount

which it paid to MCD on behalf of defendant No. 1. Since

the bank had agreed to purchase the flats constructed on

these properties from defendant No. 1, the construction of

CS(OS)No.864/1999, 865/1999, 985/1999 Page 28 of 37
the flats was financed by it and the possession of the flats

had also been taken by it from defendant No. 1, it is difficult

to dispute that the plaintiff-bank was interested within the

meaning of Section 69 of Contract Act, in a payment of

property tax to MCD. The payment of property tax is a

charge on the property and MCD is entitled in law to attach

that property to recover the arrears of property tax. Section

156(1) of DMC Act, to the extent it is relevant, provides that

if the person liable for payment of tax does not pay the

amount within 30 days from the service of notice of

demand, the amount may be recovered by sale of immovable

property of defaulter.

Since MCD could have attached these properties to

recover the arrears of property tax from defendant No. 1,

attachment of the properties would have adversely affected

the interest of the plaintiff-bank which had not only

financed from construction, but had also received

possession from defendant No. 1.

In the record of MCD, the properties stood in the

name of defendant No. 1 and it was the person primarily

responsible for payment of property tax in respect of those

properties to MCD, it cannot be disputed that defendant No.

CS(OS)No.864/1999, 865/1999, 985/1999 Page 29 of 37
1 was legally bound to pay the arrears of property tax,

demanded by MCD. Section 69 of Contract Act is based

upon the doctrine of unjust enrichment so that a person,

who is unjustifiably enriched at the expense of another is

made to make restitution. In fact, Section 69 of Contract

Act does not require that a person, to be interested in

payment, should at the same time have a legal proprietary

interest in the property in respect of which the demand is

made. The interest envisaged in Section 69 of Contract Act

is an interest in order to avert some loss or to protect some

interest which would otherwise be lost to the person making

the payment. Moreover, defendant No. 1 was legally bound

to pay arrears of property tax up to the date it handed over

possession of the flats to the plaintiff in terms of the

agreements, executed between the parties. This contractual

obligation would also be covered within the expression

“bound by law to pay” used in Section 69 of Contract Act.

A similar issue came up for consideration before

Privy Council in Govindram Gordhandas Seksaria and

Another vs. State of Gonday AIR (37) 1950 Privy Council

99. In that case, the appellant company had entered into a

sub-agreement to purchase two mills, but no formal sale

CS(OS)No.864/1999, 865/1999, 985/1999 Page 30 of 37
deed had been executed in his favor. There were unpaid

municipal dues in respect of those mills. Those dues were

paid by the appellant. It was contended before Privy Council

that a person cannot be said to be interested in payment of

money within the meaning of Section 69 of Contract Act,

unless he was at the same time entitled to some legal

interest in the property in respect of which payment was

made. The contention, however, was rejected. Setting aside

the decision of the High Court, Privy Council, inter alia, held

as under:

“The learned Judges of the High Court in
appeal held that the appellant company
could not establish a right under this
section because it was not interested in
the payment of the money that it paid.

The view that it was not interested was
based on the fact that at the date of the
payment the company had no property
interest in the mills in respect of which
the taxes were claimed. And in
accordance with this view, the company’s
payment was described by the learned
Judges as a voluntary one. To their
Lordships it seems to have been very
unlike a voluntary payment. The
company had contracted to buy these
mills, and they were imminently
threatened with a forced sale which
would, of course, defeat its purchase.

Money had to be found for the taxes if the
mills were to be saved. Neither the
Maharajah nor the trustees showed any
sign of paying the Municipality. So the

CS(OS)No.864/1999, 865/1999, 985/1999 Page 31 of 37
appellant company paid. But to describe
it in those circumstances as having made
a voluntary payment appears to their
Lordships to involve some misuse of
language. Nor do they appreciate why it
should not properly be described as
interested in the payment. In any
ordinary use of language, the company
was interested in the taxes being paid at
the time when they were paid since only
through the payment could it realize the
fruit of the contract that it had entered
into. The words themselves do not
require about a person to be interested in
a payment should at the same time have
a legal proprietary interest in the property
in respect of which the payment is made.

But the general purport of the section is
reasonably clear; to afford to a person
who pays money in furtherance of some
existing interest an indemnity in respect
of the payment against any other person
who, rather than he, could have been
made liable at law to make the payment.
So interpreted, S.69 appears to their
Lordships to apply to the payment made
by the appellant company in this case.

Certainly too, there is authority in the
Courts of India for the proposition that
“bound by law” covers obligations of
contract or tort. Accepting this
interpretation, as their Lordships do, they
hold that the act of payment by the
appellant company gave to it a right of
action against the Maharajah to obtain
reimbursement of the sums so paid.
Thus, as against him, both the plaintiffs
in this suit ought to have been held to
have good, though alternative, rights of
action.”

CS(OS)No.864/1999, 865/1999, 985/1999 Page 32 of 37

I, therefore, hold that that the plaintiff-bank is

entitled to recover the aforesaid amount of Rs 5.2 lakh from

defendant No. 1. On payment of the aforesaid amounts to

it, defendant No. 1 is legally bound to execute sale deed in

favour of the plaintiff-bank in respect of the flats

constructed by it on properties No. C-10, C-12 and C-17,

Inder Puri and it has no justification in law to refuse such

execution. The issues are decided accordingly.

Issue No. 7

There is no evidence of any illegal and

unauthorized construction having been made by defendant

No. 1. Admittedly, no notice alleging any unauthorized

construction had been received by the plaintiff-bank.

Therefore, there is no question of defendant No. 1 seeking

regularization of any unauthorized construction or paying

any damages to the plaintiff for such construction. In any

case, no particular amount has been claimed as damages in

this regard.

Issue No. 4

18. Article 54 of Limitation Act provides that the period

of limitation in a suit for specific performance of a contract

is three years from the date fixed when the performance or if

CS(OS)No.864/1999, 865/1999, 985/1999 Page 33 of 37
no such date is fixed where the plaintiff has notice that

performance is refused. The Court before deciding the issue

of limitation has to find out what the terms of the contract

between the parties were and whether there was a definite

date for performing a contract. If the case is covered by first

part of Article, the period of limitation would commence

from the date fixed for performance of the contract and in

case it is covered by second part of the Article, the period of

limitation would commence from the date on which the

plaintiff has noticed of refusal of performance by the

defendant. The words “date fixed for performance” need not

be ascertainable in the face of the document and may be

ascertainable on the happening of a certain contingent event

specified in the contract. “Date fixed” would, therefore,

mean either the date fixed expressly in the contract between

the parties or a date that can be fixed with reference to a

future event which is certain to happen.

The agreement between the plaintiff and defendant

No. 1 provided for execution of the sale deed within 30 days

of defendant No. 1 obtaining completion certificate and

putting the plaintiff-bank in possession of the property

agreed to be sold to it. There is no evidence of defendant No.

CS(OS)No.864/1999, 865/1999, 985/1999 Page 34 of 37
1 having obtained completion certificates within three years

prior to institution of these suits. Had defendant No. 1

obtained the completion certificates, the last date stipulated

for execution of sale deed in favour of the plaintiff-bank

would have been a date 30 days from the date completion

certificate was obtained by defendant No. 1 and receipt of

completion certificate by defendant No. 1 was conveyed to

the plaintiff. This is not the case of defendant No. 1 that it

had obtained completion certificate more than three years

before filing of these suits and had informed the plaintiff-

bank in this regard. Therefore, computed in terms of first

part of Article 54, the period of limitation had not expired

when these suits were filed.

If the period of limitation is computed in terms of

second part of Article 54 of Limitation Act, the suits are still

within time for the simple reason that defendant No. 1 has

never refused to execute the sale deed in favour of plaintiff.

The correspondence between the parties seeking shows that

defendant No. 1 had time and again been expressing its

willingness to execute the sale deeds in favour of the

plaintiff bank. Ex. PW-2/13 is the letter of defendant No. 1

dated 28th November, 1998 seeking certain payments from

CS(OS)No.864/1999, 865/1999, 985/1999 Page 35 of 37
the plaintiff-bank and expressing willingness to execute the

sale deed in its favour. Similar willingness was shown in the

letter dated 23rd June, 1997 (EX.PW-2/11), letter dated 23rd

September, 1996 (Ex.PW-2/10), letter dated 1st January,

1996 (Ex.PW-2/9), letter dated 22nd April, 1995 (Ex.PW-2/6)

and letter dated 04th September, 1996 (Ex.DW-1/15). I,

therefore, hold that specific performance of the agreements

executed by defendant No. 1 in favour of plaintiff-bank for

construction and sale of flats in properties Nos. C-10, C-12

and C-17, Inder Puri is not barred by limitation.

As regards claim of recovery of Rs 5.2 lakh paid to

MCD towards arrears of property tax, since the plaintiff

bank made payment only on 04th May, 1998 and had no

cause of action to recover the aforesaid amount before that

date, the suit having been filed in April, 1999 is well within

limitation. The issue is, therefore, decided in favour of the

plaintiff and against the defendant No. 1.

ORDER

In view of my findings on the issues, the names of

defendants other than defendant No. 1 M/s Gawri

Constructions Udyog Ltd. are struck off from the array of

defendants. After adjustment of the amounts payable to

CS(OS)No.864/1999, 865/1999, 985/1999 Page 36 of 37
defendant No. 1, the plaintiff-bank is entitled to recover the

balance amount of Rs 58,039.39/- from defendant No. 1.

Defendant No. 1 is directed to execute sale deed in favour of

the plaintiff-bank in respect of the buildings constructed by

it on properties No. C-10, C-12 and C-17, Inder Puri, New

Delhi within 8 weeks. Defendant No. 1 is also directed to

pay a sum of Rs 58,039.39/- to the plaintiff-bank, along

with pendente lite and future interest on that amount at the

rate of 6% per annum. In the facts and circumstances of the

case, there shall be no order as to costs.

Decree sheet be drawn accordingly.

(V.K. JAIN)
JUDGE
OCTOBER 17, 2011
VN/BG

CS(OS)No.864/1999, 865/1999, 985/1999 Page 37 of 37