High Court Kerala High Court

Ivrcl Infrastructures And … vs Bharat Sanchar Nigam Limited on 2 March, 2009

Kerala High Court
Ivrcl Infrastructures And … vs Bharat Sanchar Nigam Limited on 2 March, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 4895 of 2009(G)


1. IVRCL INFRASTRUCTURES AND PROJECT
                      ...  Petitioner

                        Vs



1. BHARAT SANCHAR NIGAM LIMITED,
                       ...       Respondent

2. THE KERALA WATER AUTHORITY,

3. THE PROJECT MANAGER, JBIC ASSISTED

4. THE DISTRICT COLLECTOR, ALAPPUZHA.

5. THE DEPUTY TAHSILDAR (R.R), CHERTHALA.

6. THE VILLAGE OFFICER, THANNIRMUKKAM

7. STATE OF KERALA, REPRESENTED BY THE

                For Petitioner  :SRI.K.K.CHANDRAN PILLAI

                For Respondent  :SRI.MATHEWS K.PHILIP,SC, BSNL

The Hon'ble MR. Justice K.M.JOSEPH

 Dated :02/03/2009

 O R D E R
                       K. M. JOSEPH, J.
                --------------------------------------
                W.P.C. NO. 4895 OF 2009 G
                --------------------------------------
                Dated this the 2nd March, 2009

                          JUDGMENT

Petitioner challenges Exts.P40 and P41 as evidenced by

Clause 4 of Ext.P38. The prayers, inter alia, are as follows:

“ii. Issue a writ in the nature of certiorari or

such other appropriate writ, order or directions

quashing Exts.P40 and P41 and the decision

evidenced by Clause 4 of Ext.P38.

iii) Issue a writ in the nature of mandamus

or such other appropriate writ, order or direction

commanding the 1st respondent to co-operate for

the joint inspection on the basis of Exts.P20, P25

etc. and abide by the results of such inspection.

iv) Declare by issuance of appropriate writ,

order or direction that the petitioner is not liable

to pay any compensation to the 1st respondent on

the basis of the agreement between the petitioner

and the 2nd respondent.”

There are further prayers relating to the irrecoverability under

the Revenue Recovery Act, including without deciding actual

WPC. 4895/09 G 2

damage.

2. Petitioner Company entered into an agreement with the

second respondent for the laying of pipes in the area covered by

Phase II and III from Thaikkattukara to different villages of

Cherthala Taluk. The Project is intended to give drinking water

to more than six lakhs of people. It is the case of the petitioner

that digging is to be done by the petitioner by using JCB. The

first respondent BSNL is alleged to have interfered stating that

the cables were damaged, meetings were convened and

decisions were taken. Ext.P2 is a tripartite agreement between

the petitioner, the BSNL and the Kerala Water Authority.

Clauses 3 and 4 being relevant, they are extracted below:

“3. If local/OF cable is damaged on course

of the work, IVRCL has to settle all the dispute

regarding the claim in consultation with BSNL.

BSNL will prepare the estimate in consultation

with M/s. IVRCL (BSNL has to ensure the

correctness of the estimate before sending it to

IVRCL for making (4) payment) and raise demand

note as per BSNL HQ instructions for damage vide

WPC. 4895/09 G 3

letters No:110-7/2002-Regin dated 5th October,

2004 and No:110-7/2002-Regin dated 16-01-2003

of Jt. DDG (Regulation-1, BSNL HQ.Delhi (copies

attached) to M/s. IVRCL, if M/s. IVRCL is not

paying the bill within 30 days, KWA JBIC project

will pay the amount to BSNL within 30 days by

recovering the amount from Running bill at KWA

Office, Tvm.”

The revenue recovery notices, in short, are raised at the instance

of the first respondent claiming compensation for the alleged

damage done by the petitioner. A Counter Affidavit is filed on

behalf of the first respondent BSNL.

3. I heard the learned counsel for the petitioner, learned

standing counsel appearing on behalf of respondents 1 and 2,

and also the learned Government Pleader. Exts.P37 and P39 are

the Minutes of the District Collector. Ext.P44 is the Minutes of

the Meeting held by the Additional Secretary, Water Resources

Department. In short, it is contended that there may be a joint

inspection. Of course, according to the learned counsel for the

WPC. 4895/09 G 4

first respondent BSNL, as also the Kerala Water Authority, a

joint inspection was already commenced on 20.9.2008.

4. After having heard the parties, I am of the view that

interest of justice will be subserved, if a joint inspection is

ordered to be conducted in the presence of the representatives of

the petitioner, the first respondent and the Water Authority and

under the watchful eyes of the representative of the District

Collector, Alappuzha. In this regard, I take note of clause 3 of

Ext.P2 tripartite agreement which, undoubtedly, contemplates

the first respondent taking the petitioner into confidence in the

matter of raising a claim for damage, if any, caused by the

petitioner. Accordingly, the Writ Petition is disposed of as

follows:

A joint inspection will be conducted in regard to the

various demands of the first respondent in the presence of the

representatives of the petitioner, the first respondent and also the

second respondent Water Authority. The fourth respondent

District Collector will convene a meeting of the representatives

WPC. 4895/09 G 5

of the petitioner, and respondents 1 and 2. No notice need be

issued to them and in view of the urgency of the matter, the

representatives as aforesaid will be present in the office of the

fourth respondent at 11 AM on 10.03.2009. The fourth

respondent District Collector will, after deliberations with the

representatives, fix a schedule of the dates on which the

inspections in regard to the various demands are to be held.

The representatives of the petitioner and respondents 1 and 2

will be present, so that the joint inspection is carried on

smoothly. The schedule of dates shall be so arranged that the

joint inspection should be completed within ten weeks from

10.03.2009. The representative of the fourth respondent will be

present at the time of all the joint inspections. Should there arise

any dispute during the carrying out of the joint inspection, the

representative of the District Collector shall immediately bring it

to the notice of the fourth respondent and further steps will be

taken as directed by the fourth respondent. The costs will be

defrayed by the party who was meeting the costs earlier. I also

WPC. 4895/09 G 6

make it clear that the joint inspection which was already

completed need not be reopened. The revenue recovery

proceedings against the petitioner will be kept in abeyance

unless and until the inspections are completed as directed.

Provided the second respondent will ensure that there are

sufficient funds to meet the demands due to the first respondent

from the petitioner, it will be open to the second respondent to

release monthly payments.

Sd/=
K. M. JOSEPH, JUDGE

kbk.

// True Copy //
PS to Judge