High Court Kerala High Court

K.D.Antony vs K.Venugopalamenon on 6 December, 2010

Kerala High Court
K.D.Antony vs K.Venugopalamenon on 6 December, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

RCRev..No. 368 of 2010()


1. K.D.ANTONY, S/O.KURUTHUKULANGARA
                      ...  Petitioner

                        Vs



1. K.VENUGOPALAMENON,
                       ...       Respondent

                For Petitioner  :SRI.M.UNNIKRISHNA MENON

                For Respondent  : No Appearance

The Hon'ble MR. Justice PIUS C.KURIAKOSE
The Hon'ble MR. Justice P.S.GOPINATHAN

 Dated :06/12/2010

 O R D E R
       PIUS C.KURIAKOSE & P.S.GOPINATHAN, JJ.
                   ------------------------
                  R.C.R.No. 368 OF 2010
                   ------------------------

        Dated this the 6th  day of December, 2010




                         O R D E R

Gopinathan , J.

The tenant/respondent in RCP No.86/2001 on the file

of the Rent Control Court, Thrissur has come up in revision

under Section 20 of the Kerala Lease Buildings (Lease and

Rent Control) Act (hereinafter referred to as ‘the Act’)

assailing the judgment of the Rent Control Appellate

Authority in RCA No.27/2004, whereby the eviction

granted under Section 11 (4)(ii) by the Rent Control Court

was confirmed. The respondent/landlord filed the above

petition seeking an order of eviction under Section 11 (2)

(b) and 11(4)(ii) of the Act. It is submitted by the learned

counsel appearing for the revision petitioner that the rent

RCR.No.368/2010 2

arrears were cleared and eviction order under Section 11

(2)(b) is no more live. That submission is recorded. The

respondent alleged in his petition that the revision petitioner

had made damages and alterations whereby the value and

utility of the petition schedule building were materially and

permanently reduced. The revision petitioner denied the

damages and reduction of utility and value of the petition

schedule building. He contended that because of some

alterations and constructions made by the revision

petitioner, the value and utility of the petition schedule

building were increased.

2. The Rent Control Court enquired the rent control

petition along with RCP No.87/2010. During the course of

the enquiry, on the side of the respondent, PWs 1 to 3

were examined. On the side of the revision petitioner,

himself and another witness were examined as RWs1 and 2.

Exts.A1 to A3 were marked on the side of the respondent.

On the side of the revision petitioner Exts.B1 to B5 series

RCR.No.368/2010 3

were marked. On appraisal of the evidence, the rent

control court arrived at a finding in favour of the

respondent. Consequently, the revision petitioner was

directed to put the respondent in possession of the petition

schedule building under Section 11(4)(ii). The above order

was confirmed in appeal. Now the revision.

3. We heard Sri.K.M.Jamaludheen, learned counsel

appearing for the revision petitioner and perused the

judgment impugned as well as the order of the Rent Control

Court.

4. The learned counsel for the revision petitioner fairly

conceded that the revision petitioner had made some

constructions. According to him, it only enhanced the

value and utility of the petition schedule building and for

that construction, the revision petitioner is not liable to be

evicted under Section 11(4)(ii) as no damage was caused to

the building so as to reduce its value an utility. It was also

argued that the respondent had acquired citizenship in

RCR.No.368/2010 4

Canada and therefore, he is not entitled to get an order of

eviction in respect of the petition schedule building.

Though it was contended by the learned counsel for the

revision petitioner that the respondent had acquired

citizenship in Canada, no evidence was let in to that

effect. The learned counsel would argue that it is admitted

in the witness box that the respondent had been residing in

Canada for the last 30 years on employment, so it could be

presumed that he had acquired citizenship there.

Curiously we notice that the revision petitioner had not

dared to depose that the respondent has citizenship in

Canada. We find no merit in this argument as it is not

supported by pleadings or evidence. To PW1, there is not

even a suggestion that he had acquired Canadian

citizenship. In the above circumstances, we find that the

revision petitioner had not succeeded to establish that the

respondent had Canadian citizenship. Going by the

judgment impugned, we find that the said argument was

RCR.No.368/2010 5

considered by the appellate authority in the light of the

decision reported in Sebastian E.J. and others v.

Dr.A.M.Mathai (ILR 2005 (4) 302). The appellate authority

had found that the respondent is not at all disqualifed for

that reason from seeking order of eviction of the revision

petitioner. It is revealed that the petition schedule

building, which is aged more than 100 years, was obtained

to the respondent by inheritance. The mere fact that the

respondent had gone abroad on employment would not dis

entitle him to hold the title of the property or seeking an

order of eviction of the tenant who was put in possession of

the petition schedule building by the predecessor of the

respondent. It is pertinent to note that the revision

petitioner has no case that the respondent is not entitled to

receive rent. On the other hand, rent is being paid to the

respondent. A person who has the right to receive the rent

has got the right to evict, of course, subject to the

provisions of the Act. Since the revision petitioner continues

RCR.No.368/2010 6

to pay the rent, in fact, he is estopped from raising a

contention that the respondent is not entitled to evict the

revision petitioner. Hence, we reject the contention that the

respondent is not entitled to an order of eviction for the

reason that he is employed in Canada.

5. As regards the constructions made by the revision

petitioner, the appellate authority had elaborately

mentioned in para 11 of the judgment impugned. To

avoid repetition, we quote herein paragraph 11 of the

impugned judgment.

“The respondent himself has filed

affidavit in accordance with the

averments in the petition. At page 2 of

the affidavit, it is alleged by the

respondent that the window on the

western side was replaced with an

aluminium window. The tenant has put

up beam by making holes through the

RCR.No.368/2010 7

wall. They extended the building

towards the front and the front elevation

was constructed without his consent. It

is also stated that he had to approach

the Munsiff’s Court, Thrissur to obtain

injunction against the alteration of the

building by the tenant. The

commissioner visited the property and

submitted a report. It is also alleged in

the affidavit that the tenants in these

two shop rooms colluded and made the

alterations and additions without his

knowledge and consent. He has been

cross examined as PW1. According to

him, the building was about 100 years

old. According to PW1, the distance

between this building and the main road

was 10 feet and now it is reduced to one

RCR.No.368/2010 8

foot because of the front elevation

taken by the tenant. PW1 has deposed

that the tenants have made permanent

structures by using iron poles and iron

rails. According to PW1, major

alterations were done to the building.

They put up walls on the eastern side

without his consent. There was no wall

on the eastern side when it was let out

to the tenant. Similarly shutters were

put up on the eastern side in respect of

the room comprised in RCP No.86/2001.

There was a door on the eastern side.

Now the door is shifted to western side.

Rails were put up at the place of the

door. Similarly, shutter was put up on

the eastern side. A new door was put

up on the western side. A leanto was

RCR.No.368/2010 9

put up by using iron rails and the two

poles. PW1 has denied the suggestion

that the alterations made to the

existing building have only increased the

value. PW1 has denied that except

putting up a leanto on 4 poles, no other

construction was done by the tenant. He

has deposed that the ceiling was

removed. ………”

6. PW2, a retired Superintendent Engineer, also had

given supporting evidence that because of the construction

made by the revision petitioner, the elevation of the building

was changed and the value and utility of the building was

reduced. True, that it was put to PW2 in cross

examination that because of the additional construction,

the value of the building has been increased and he had

given affirmative answer. But, we notice that the petition

schedule building had got 10 feet wide road frontage. The

RCR.No.368/2010 10

revision petitioner had made construction leaving only one

foot from the road there by parking area was reduced.

There is total change of the structure. It is not disputed

that for making alterations or additional constructions

extending to the parking area, the revision petitioner had

not obtained any permission from the local authority. The

result is that the alterations made by the revision petitioner

would canvas even penal action including demolition. The

additions made by the revision petitioner had been reported

in Ext.A3 commission report submitted by PW3 in

O.S.No.840/2001. It would also show that the revision

petitioner had fitted rolling shutters. Since the wall of the

building has no capacity to erect the rolling shutters, the

revision petitioner erected pillars in the building and fitted

the rolling shutters . These constructions and additions

made by the revision petitioner revealed by the evidence

of PWs1 to 3 and Ext.A3 would show that the revision

petitioner had made material alterations and such

RCR.No.368/2010 11

constructions had reduced the value and utility of the

petition schedule building. Even elevation of the building

was changed and the parking area in front of the building

was reduced. These alterations were made without

sanction from the local authority. If the local authority

initiates action, the respondent is liable for penal action

including demolition of the building. In the above

circumstances, overlooking the decisions cited by the

revision petitioner before the appellate authority in

Shanmugam v. Rao Saheeb (1988 (1) KLT 86),

G.Arunachalam v. Thondarperienambi ( A.I.R.1992 SC

977) , Ahammad Kanna v. Muhammed Haneef (1967 KLT

841), Om Prakash v. Ammar Singh (AIR 1987 SC 617),

B.Prabodhini v. P.Rajammal and others (1991 (1) KL J 113),

T.R.Sharma v. State of Haryana ( AIR 1988 SC 2929) and

Viswanathan v. Porichy (1985 KLT 551) the appellate

authority had confirmed eviction. In its judgment the

appellate authority had given reliance to the decision

RCR.No.368/2010 12

reported in Seethalakshmi Ammal v. Nabeesath Beevi (2003

(1) KLT 391) and Francis v. Davis (2005 (3) KLT 815). In

Francis v. Davis, it is held as follows;

“The question to be enquired

under Section 11(4)(ii) is not

whether the value or utility is

increased. Impairment of the

value or utility of the building is to

be considered in the point of the

view of the landlord. If a

stipulation is made in the lease

deed that the tenant shall not make

any additional construction or any

alteration to the tenanted building,

it is binding on the tenant. It is

true, a construction or alteration of

the building which does not attract

RCR.No.368/2010 13

the ingredients of Section 11 (4)(ii)

would not render the tenant liable

to be evicted under the Act, eve if

there is violation of the said term in

the lease deed. At the same

time, in considering whether in the

point of view of the landlord the

offending acts would destroy or

reduce the value or utility of the

building. Stipulations in the lease

deed are relevant. The prohibition

in the lease deed against the

tenant making construction has

certainly relevance while

considering question how the ‘use’

of the building by the tenant was”.

7. Going by the facts of the case and the ratio of the

above decision, we find that the above ratio is squarely

RCR.No.368/2010 14

applicable to the case on hand and we find that the

appellate authority had meticulously considered the

evidence on record in the light of the precedents. The

eviction granted by the Rent Controller and confirmed in

the appeal is in tune with the facts and law. There is no

irregularity, illegality or impropriety committed by the facts

finding authorities below so as to rectify in revision. The

revision is devoid of merits and is liable to be dismissed.

8. The learned counsel for the revision petitioner,

having failed to impress us to interfere with the

judgment impugned, sought for 10 months time to vacate

the premises. It is reported that the revision petitioner had

been running printing press in the petition schedule

building. There is no case for the revision petitioner that no

suitable building is available in the locality. However,

having taken into account that the revision petitioner had

been occupying the petition schedule building for long

time, we find that it would be just and proper to grant time

RCR.No.368/2010 15

till 31/5/2011 to vacate on the following conditions;

i).The revision petitioner shall file

an affidavit within three weeks from

today undertaking to vacate the

premises on or before 30/5/2011

without raising any objection.

ii). The arrears of rent, if any,

shall be discharged within one month

from today and shall continue to pay

occupational charges at the contract

rate of rent. In the event the revision

petitioner files an affidavit and honours

the undertakings, the Rent Control

Court/Execution Court, as the case may

be, shall keep the order of eviction in

abeyance till 30/5/2011.

iii). In the event of failure to

comply with any of the conditions, the

RCR.No.368/2010 16

respondent is at liberty to execute the

order of eviction forthwith.

There will be no order as to costs.

PIUS C.KURIAKOSE,JUDGE

P.S.GOPINATHAN, JUDGE
dpk