High Court Kerala High Court

K.J.Mathew vs Hindustan News Print Ltd on 3 December, 2007

Kerala High Court
K.J.Mathew vs Hindustan News Print Ltd on 3 December, 2007
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WA No. 2864 of 2007()


1. K.J.MATHEW, KUNNEAL HOUSE,
                      ...  Petitioner

                        Vs



1. HINDUSTAN NEWS PRINT LTD.,
                       ...       Respondent

2. THE GENERAL MANAGER(WORKS),

3. M/S GLASS FIBRESS , KRISHNA NIVAS,

                For Petitioner  :SRI.B.GOPAKUMAR

                For Respondent  : No Appearance

The Hon'ble the Chief Justice MR.H.L.DATTU
The Hon'ble MR. Justice K.M.JOSEPH

 Dated :03/12/2007

 O R D E R
                         H.L. DATTU, CJ. & K.M. JOSEPH, J.
                       - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
                          WRIT APPEAL No.2864 of 2007
                       - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
                     Dated this the 3rd day of December, 2007.

                                          JUDGMENT

K.M.JOSEPH,J,

The third respondent in the writ petition is the appellant before us.

The writ petition was filed by the third respondent in the present appeal challenging

the award of the work of Newsprint Handling pursuant to the notification by

respondents 1 and 2 in favour of the appellant. Two grounds were taken as can be

seen on a perusal of the judgment in the writ petition. The first ground was that the

appellant was not pre-qualified to participate in the tender. The further contention

by the writ petitioner was that the appellant had corrected the rates in the tender.

Learned Single has found favour with the first contention, namely that the appellant

was not pre-qualified to participate in the tender. For arriving at the said

conclusion, the learned Single Judge has relied on the stand of the first respondent

Company itself. The stand of the Company in relation to the question as to

whether the petitioner was pre-qualified has been extracted in the judgment and

we also refer it in our judgment.

“With regard to the averments contained in Grounds

A, B and C of the writ petition, it is submitted that they are devoid of

any merit, and hence denied. The averments in Ground A that the

3rd respondent did not qualify any of the criteria specified in Ext.P2 is

factually incorrect. While one of the pre-qualification criteria

prescribed in the tender document was that the tenderers should

have successfully completed three labour oriented works contracts of

annual value not less that 40% of the annual PAC (59.15 lakh) during

any of the preceding seven years from 31.3.2007, it was found that

the 3rd respondent had completed work of the said nature, subject to

WA.2864/2007. 2

a marginal deficit of Rs.70,000/- in the 3rd work during the stipulated

period. When the respondent Company sought clarification from its

internal audit department as to whether the third respondent could be

deemed to have complied with the pre-qualification criteria for the worK,

the internal audit department clarified that in view of the works undertaken

by the 3rd respondent in the past, and also considering the fact that the

deficit in the last work was only Rs.70,000/-, when compared to the total

value of the works undertaken, his bid could also be considered for the

purpose of awarding the work. This suggestion of the internal audit

department was accepted by the Managing Director of the respondent

Company and, accordingly, his bid also was considered along with those

of the other three tenderers, who were qualified under the tender

conditions.”

Thus the finding of the learned Single Judge would appear to be that the appellant was

not pre-qualified for the reason that the appellant had, though executed three works

within the preceding seven years from 31.3.2007, in respect of one of the works the

value fell short of the prescribed limit by Rs.70,000/-. In the light of this finding, the

learned Single Judge found it not necessary to go into the second contention as to the

alleged subsequent correction by the appellant.

2. Learned counsel for the appellant, Sri. B. Gopakumar would contend

that by Ext.R3(b) dated 20.10.2007 the appellant came to be pre-qualified. Tender of

the appellant was the lowest. He would contend that the actual complaint of the writ

petitioner was regarding the alleged subsequent correction made by the appellant,

which was by reducing the rate from Rs.18/- to Rs.16/-. He would submit that the

question relating to the pre-qualification was never contended before the learned Single

Judge and yet the learned Single Judge has proceeded to find that the appellant was

not pre-qualified. He would further point out with reference to the relevant clause that

having regard to the value of the three works which he had executed, the Company has

WA.2864/2007. 3

taken the view that he must be treated as pre-qualified and it was a view which should

have commended itself for the acceptance of the learned Single Judge. He would

commend the view taken by the Company for our acceptance. We extract the clause

relied on as hereunder:

“(c) Tenderers should have successfully completed three

labour oriented works contract of annual value not less than 40% of the

annual PAC (59.15 lakhs) during any of the preceding 7 years from

31.3.2007.”

He would further contend that the writ petitioner did not really challenge the right of the

third respondent to be pre-qualified. He would further contend that the tender of the

appellant was the lowest and the first respondent being a Public Sector Company would

lose several lakhs of rupees if the appellant’s pre-qualification is interfered with and the

work is awarded to the writ petitioner. He would further submit that it is the settled view

of the courts that the courts should not interfere with the awarding of work.

3. As far as the contention that the question whether the appellant was

pre-qualified was not an issue before the learned Single Judge is concerned, we are of

the view that the writ petitioner had called in question the pre-qualification of the

appellant. This is clear from Ground A. Ground A is extracted hereunder:

“A. There are four alternative pre-qualification criteria

stipulated in Ext.P2 for a person to participate in the Tender. The said

pre-qualification criteria are mandatory. The third respondent did not

qualify any of the said criteria in Ext.P2. Hence the 3rd respondent is not

fit and entitled to participate in the Tender and his tender is liable to be

rejected.”

WA.2864/2007. 4

It is further pointed out by learned counsel appearing on behalf of the writ petitioner that

in Ext.P5 dated 23.10.2007 the writ petitioner had specifically pointed out that the

appellant is not pre-qualified for participating in the tender as per the pre-qualification

criteria.

4. We notice that the learned Single Judge had indeed before him two

issues projected by the writ petitioner, namely whether the appellant was pre-qualfiied

and as to whether there was subsequent correction by the appellant. The learned

Single Judge, as already stated, had found that the appellant was not pre-qualified.

Therefore, we reject the contention of the appellant that the issue relating to the pre-

qualification was not present before the learned Single Judge.

5. The further question to be decided in this case is whether the view

taken by the learned Single Judge that the appellant was not pre-qualified requires to be

interfered with. We would think that the learned Single Judge was fully justified in

finding that the appellant was not pre-qualified. Learned counsel for the appellant fairly

submits that he claims the right to be pre-qualified only under the third alternate clause,

which we have extracted. We would think that the third alternate clause indeed

mandates that the tenderers should have successfully completed three labour oriented

works contract, each having a value equivalent to 40% of the annual PAC. Though the

appellant has executed three works, in respect of one of the works, he fell short by

Rs.70,000/-. It is evident on a perusal of the clause in question that the employer

contemplated that the contractor should have executed three labour oriented works,

each having a value of 40% of the PAC. We would think that no other view is possible.

If that be so, it is clear that the appellant was not eligible to be pre-qualified and that has

been found by the learned Single Judge. The learned Single Judge thereafter has

quashed the award of contract to the appellant and directed respondents 1 and 2 to

WA.2864/2007. 5

consider the matter afresh in accordance with law. We find that there is no merit in this

appeal.

Accordingly, the writ appeal is dismissed.

Consequently, I.A. No.968 of 2007 is dismissed.

H.L. DATTU,
CHIEF JUSTICE

K.M. JOSEPH,
JUDGE

sb.