High Court Kerala High Court

K.M.Achuthan vs Union Of India Rep.By Commander … on 30 July, 2008

Kerala High Court
K.M.Achuthan vs Union Of India Rep.By Commander … on 30 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

MFA.No. 954 of 1998()



1. K.M.ACHUTHAN
                      ...  Petitioner

                        Vs

1. UNION OF INDIA REP.BY COMMANDER WORKS EN
                       ...       Respondent

                For Petitioner  :SRI.V.RAJGOPAL

                For Respondent  :SRI.K.RAMAKUMAR (SR.)

The Hon'ble MR. Justice J.B.KOSHY
The Hon'ble MR. Justice P.N.RAVINDRAN

 Dated :30/07/2008

 O R D E R
          J.B.KOSHY & P.N.RAVINDRAN, JJ.
                 -------------------------------
                M.F.A.NOS.954 OF 1998
                               &
                    1093 OF 2002 (D)
               -----------------------------------
          Dated this the 30th day of July, 2008

                     J U D G M E N T

KOSHY,J.

Appellant is a registered Contractor. He undertook

contract for Provision of Residential Accommodation for DAD

Staff at Cannanore under an arbitration agreement

No.CWE/Cochin/8 of 1984-85 was signed. While the work

was in progress, appellant raised disputes, as according to

him, he is entitled to the amounts on the basis of the

escalation actually occurred and O.S.No.213/1985 was filed

before the Additional Sub Court, Thalassery. He also prayed

that an arbitrator may be appointed to decide that question.

A written statement was filed by the respondents to the effect

that the delay was caused due to the act of the appellant.

They are not liable to pay any escalation and they also

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

2

contended that the stage has not come for raising arbitration

dispute as contract was not yet completed. So the main

contention was that the suit itself was premature as the stage

for arbitration has not reached. The civil court considered the

matter, allowed the suit and directed to appoint the

arbitrator. The court by its judgment dated 31.1.1989,

directed that the disputes should be referred to the Sole

Arbitrator to be appointed by the Chief Engineer, Cochin

Zone, Cochin, of the appellant as provided in the agreement.

Hence, Sri.H.K.Nagaraja, Additional Chief Engineer, was

appointed as the Sole Arbitrator. In the general conditions of

the contract, there was a specific provision to refer all

disputes to the Sole Arbitration to the Engineer/Officer to be

appointed by the Chief Engineer, Cochin Zone, Cochin, whose

decision shall be final, conclusive and binding. The agreement

further provides as follows:

“The Arbitrator shall give his award on all
matters referred to him and shall indicate his
findings, along with sums awarded, separately
on each individual items of disputes.”

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

3

It shows that both the parties agreed that the disputes are to

be referred to arbitration, to the Engineer/Officer appointed

by the Chief Engineer. In fact, arbitrator was appointed at

the request of the appellant. The order appointing the

arbitrator was not challenged. Accordingly, arbitrator was

appointed and both parties participated in the proceedings.

Claims and counter claims were filed. Evidence was adduced.

Documents were filed and some of the claims of the petitioner

amounting to Rs.63,798/- were allowed. Among the counter

claims also, two claims were allowed amounting to

Rs.5,42,680/-. Both claims are awarded with 18% interest.

Appellant filed O.P.(Arb).No.11/1991 with the following

prayers:

“a) this Honourable Court may be pleased
to direct the 4th respondent, Sole Arbitrator
to file the original award with all the
documents taken by him into this Court and
thereafter pass an order and consequently
a decree in terms of the award on the
claims preferred by the petitioner and to
set aside the award in so far s it relates to

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

4

the claims preferred by the respondents 1
to 3.”

The respondents also filed O.P.No.129/1995 for passing the

decree in terms of the award. The court below passed the

judgment and decree in terms of the award making it a rule of

the court. In other words, O.P. was filed by the respondent

was allowed and O.P filed by the claimants in so far as to set

aside the award in the counter claims were rejected. Hence,

these appeals were filed.

2. Three main contentions are raised by the appellant.

First contention raised is that as a Sole Arbitrator,

Sri.H.K.Nagaraja, should not have been appointed as he is an

Engineer connected with the works. We are unable to accept

the above contention because petitioner himself filed the suit

and as per the decree, Chief Engineer was directed to appoint

the arbitrator in terms of the agreement and terms of the

agreement itself provides for appointing an Engineer/Officer.

So the arbitrator was appointed in terms of the agreement.

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

5

After agreeing for such a clause, this contention cannot be

raised. Secondly, even though it is stated that an oral

objection was filed, no written objections were filed and the

petitioner as well as the respondent participated in the

proceedings, filed claims and counter claims, adduced

evidence without any murmur and the award was passed.

When the award is against the appellant, appellant cannot

question the appointment of the sole arbitrator. Therefore,

the above contention fails. Next contention is that arbitrator

travelled beyond the terms of the reference, and therefore,

award was passed without jurisdiction and therefore, it is

liable to be set aside. According to the appellant, he only filed

the suit for claiming escalation benefits because of the delay

of the contract. On his application, arbitrator was appointed,

and therefore, arbitrator can decide only the question

regarding escalation etc. raised in the suit. We are unable to

accept that point. Under the agreement, arbitrator can

decide the entire disputes. In the written statement,

respondents had clearly contended that appellant was himself

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

6

responsible for the delay. Other contentions raised was that,

at that stage, no arbitral dispute has arisen and claim was

premature. The court after considering the above objections,

found that in view of the arbitration clause, matter can be

referred to the arbitrator with regard to the disputes arising

out of the agreement. If there was no arbitration clause and

petitioner filed a suit claiming some amounts before the civil

court, respondent would be free to file his counter claim also.

Here, when arbitration clause is there and arbitrator is

appointed and the counter claims were filed as the term of

reference as per the court order, he has to decide all disputes

arising out of the contract. Therefore, it cannot be stated that

arbitrator travelled beyond the scope of reference or his

award is without jurisdiction. Next contention is that interest

awarded is very high. 18% interest awarded was as per

commercial practice. Under the provisions of the agreement,

there was no obligation for the arbitrator to pass a speaking

award but arbitrator only should give findings in each issue

with amounts. That was devised on him and therefore,

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

7

reasons for the findings of the arbitrator for awarding the

amount need not be detailed by him and such award cannot be

interfered by the court unless the arbitrator has committed

misconduct or on the specific ground mentioned in the Act.

Such grounds are not made out. However, considering the

facts and circumstances of the case, we are of the opinion that

instead of 18%, 9% interest from the date of the award for the

claims and counter claims will serve the ends of justice and

after deducting the amount payable to him as per the award,

balance amount as decreed in the counter claim should be

paid by the appellant with 9% interest from the date of award

till the date of deposit. Appeals are accordingly allowed to the

above limited extent. In the circumstances of the case,

parties have to bear their costs.

J.B.KOSHY, JUDGE

P.N.RAVINDRAN, JUDGE
prp

J.B.KOSHY & P.N.RAVINDRAN, JJ.

——————————————————–

M.F.A.NOS.954 OF 1998
&
1093 OF 2002 (D)

———————————————————

J U D G M E N T

———————————————————

30th July, 2008