High Court Kerala High Court

K.Pramod vs State Of Kerala on 2 June, 2008

Kerala High Court
K.Pramod vs State Of Kerala on 2 June, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 13865 of 2008(A)


1. K.PRAMOD, S/O.KORAN, ASST.ENGINEER,
                      ...  Petitioner
2. K.SOMAN, S/O.KUNHAN, OVERSEAR GR:3,

                        Vs



1. STATE OF KERALA, REPRESENTED BY THE
                       ...       Respondent

2. THE ASST.EXECUTIVE ENGINEER,

                For Petitioner  :SRI.C.K.ABDUL RAHIM

                For Respondent  :GOVERNMENT PLEADER

The Hon'ble MR. Justice V.GIRI

 Dated :02/06/2008

 O R D E R
                           V.GIRI, J
                         -------------------
                     W.P.(C).13865/2008
                        --------------------
            Dated this the 2nd day of June, 2008

                        JUDGMENT

First and second petitioners are working as

Assistant Engineer and IIIrd Grade Overseer respectively,

in the Water Resources Department. They are aggrieved

by Ext.P8 order passed by the Government suspending

them from service, pending enquiry. The order of

suspension has been passed by the Government taking

note of the recommendations made by the enquiry

committee, constituted to enquire into the incident at

Padinjarethara in the Banasura Sagar Project.

Apparently, there was a landslide mishap which occurred

at the site of the said project on 26.1.2008. Taking note of

the gravity of the situation, a committee was appointed to

look into the same. First petitioner, the Assistant

Engineer, was posted in the present place at BSP

(Banasura Sagar Project) Section 3/1 at Padinjarethara in

Wayanad District, on 1.12.2007. He assumed charge in

the said office on 1.12.2007. According to him, the work

of “BSP – Pandinjarethara Branch Canal – construction of

W.P.(C).13865/2008
2

covered and open Flume from CH 2100 to 2690″ was a

work being executed under BSP Section 1/1 since

February 2007 onwards. But after the first petitioner

took charge as Assistant Engineer in BSP Section 3/1,

through an order dated 28.12.2007, the Executive

Engineer transferred the said work from BSP Section 1/1

to BSP Section 3/1. Specific case of the petitioner is that

in spite of the said order, Ext.P1, Assistant Engineer,

who was in charge of BSP Section 1/1, did not hand over

any records pertaining to the said work, to the first

petitioner. By Ext.P2 dated 8.1.2008, the second

respondent issued a note to the first petitioner pointing

out that the contractor is not executing the work as per

the approved profile. First petitioner replied vide Ext.P3

and the same reads as follows:-

“As per the reference 1st cited, it is

ordered that the above work has been

transferred from section 1/1

Padinjarethara to Section 3/1

Padinjarethara. But the connected

W.P.(C).13865/2008
3

records such as files, drawings, M.Books,

work memorandum etc, are not handed

over to me by the Assistant Engineer

Section 1/1 Padinjarethara till date. So I

cannot follow up the direction issued by

the Assistant Executive Engineer BSP Sub

division Padinjarethara. This is for your

information and necessary action.”

2. It therefore, seems to be the specific case of the

first petitioner that though a direction was issued vide

Ext.P1, to see that the charge of the project is handed

over to the first petitioner namely the Assistant

Engineer in Section 3/1, the same was not implemented.

Reference is made to Ext.P4 by which the Assistant

Executive Engineer issued a specific communication to

the Assistant Engineer, Section 1/1, wherein he was

directed to transfer the file and all connected documents

regarding the subject work to the Assistant Engineer,

Section 3/1, Padinjarethara. Ext.P4 would prima facie

indicate that Ext.P1 had not really been given effect to,

in the sense that the first petitioner did not get charge

W.P.(C).13865/2008
4

of the work in question at any point of time prior to

26.1.2008. First petitioner is aggrieved that in spite of

the same, he has been put under suspension, as if there

was a lapse on his part in relation to the landslide mishap

which occurred on 26.1.2008. The order of suspension

is therefore, challenged on the ground that the first

petitioner has no connection at all to the incident in

question and therefore, the Government had committed

an error in not ascertaining the concerned incumbents,

who were in charge of the work in question on the date

of mishap or during the relevant time.

3. Learned senior Government Pleader

Mr.Nandakumar had made available a copy of the

enquiry report submitted before the Government. I have

gone through the same. Paragraph 33 of the said report,

no doubt, affirms that the Assistant Engineer and

Overseer were responsible for the work in question and

it is therefore, that recommendation was made to place

both the Assistant Engineer and Overseer under

W.P.(C).13865/2008
5

suspension. It seems that the Government had

proceeded to place the first petitioner under suspension

on the premise that Ext.P1 had taken effect and the first

petitioner was in charge well before 26.1.2008. I do not

find any material to clearly indicate whether the

Government had really gone into the question before

passing the order of suspension. In my view, this is an

aspect which has to be engaged the serious attention

of the Government.

4. In so far the second petitioner is concerned, he

also has a contention that though he was an Overseer,

Section 1/1, he was in the administrative Office and was

not in charge of the site as such. In my view, that is a

matter which has to be considered by the appropriate

authority, if the second respondent files an application

under Rule 10(6) of the Kerala Civil Services

(Classification, Control and Appeals) Rules. In the

result, writ petition is disposed of in the following

terms:-

W.P.(C).13865/2008
6

(i). Government shall specifically

consider the case of the first petitioner

that Ext.P1 had not been give effect to

and therefore, the first petitioner had

never been put in charge of any operation

of the work dealing with BSP,

Padinjarethara Branch Canal and

construction of covered and open Flume

from CH 2100 meters to 2690 meters.

(ii). If the first petitioner’s contention on

the basis of Exts.P1, P3 and P4 are found

to be correct, then the suspension of the

first petitioner is liable to be revoked and

necessary orders shall be passed by the

Government in that regard. To enable the

Government to do so, first petitioner may

file a representation pointing out these

aspects and also produce the relevant

materials in support of the contention.

This shall be done within a period of one

week from the date of receipt of a copy of

this judgment and the Government shall

pass orders on the same within a period of

four weeks from the date of receipt of

W.P.(C).13865/2008
7

such representation. Ext.P8 order of

suspension shall not be given effect to in

so far as the first petitioner is concerned,

till such fresh orders are passed by the

Government.

(iii). If the second petitioner files an

application for revocation of suspension in

so far as he is concerned, in terms of Rule

10(6) of the Kerala Civil Services

(Classification, Control and Appeals)

Rules, it shall be considered and

appropriate decision taken thereon, within

a period of four weeks from the date of

receipt of such application, along with the

copy of the judgment. Both the petitioners

shall be heard, if there is a proposal to

pass an order adverse to them.

V.GIRI,
Judge

mrcs