High Court Kerala High Court

K.S.E.B vs K.Vidyadharan on 17 July, 2007

Kerala High Court
K.S.E.B vs K.Vidyadharan on 17 July, 2007
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

SA No. 411 of 1994(G)



1. K.S.E.B.
                      ...  Petitioner

                        Vs

1. K.VIDYADHARAN
                       ...       Respondent

                For Petitioner  :SRI.S.RAMESH BABU, SC. KSEB

                For Respondent  :SRI.PRAKASH THOMAS

The Hon'ble MR. Justice M.SASIDHARAN NAMBIAR

 Dated :17/07/2007

 O R D E R
                 M.SASIDHARAN NAMBIAR, J.
                    ...........................................
                     S.A.No. 411              OF 1994
                    ............................................
          DATED THIS THE 17th DAY OF JULY, 2007

                               JUDGMENT

Second defendant Kerala State Electricity Board is the

appellant. First respondent is plaintiff and other respondents,

other defendants in the suit. First respondent instituted the suit

seeking a decree for mandatory injunction directing the

appellant Board to shift the 11 KV line which was drawn above

the plaint schedule property belonging to him, contending that it

was drawn without his consent or permission. According to

appellant, the Board has shifted the reallignment from its

original place and drawn above the plaint schedule property

without seeking consent of first respondent and without

complying with the provisions of Electricity Act. In the suit, first

respondent impleaded apart from the Board, the Executive

Engineer, K.S.E.B, Kundara and the District Collector as

defendants. Appellant resisted the suit contending that 3rd

defendant Executive Engineer of Kundara has nothing to do with

the KSEB Transmission Division, Adoor and the suit is bad for

his mis-joinder. It was not contended that suit was bad for non-

joinder of Executive Officer, Adoor Division. It was also

SA 411/1994 2

contended that 11 KV line connecting Mavelikkara and Punalur

sub-stations is passing through the plaint schedule property and

the 11 KV line was drawn long back even before first

respondent purchased the property and it was not drawn

recently as alleged by first respondent and the allignment was

not shifted and therefore first respondent is not entitled to the

decree for mandatory injunction sought for.

2. Learned Munsiff, on the evidence of Pws 1 to4, DW1

and Exts.A1 to A10, Exts.B1 to B5 and Exts.C1 and C2 held that

the suit is not bad for mis-joinder of 3rd defendant and case of

appellant that the line was drawn long back and there was no

reallignment is not correct and evidence of Pws 1 to 4 with DW1

establish that the original of 11 KV line was shifted which was

existing after widening of M.C.Road and as a result it is now

drawn above the plaint schedule property and it was so drawn

without getting the consent or permission of first respondent and

therefore first respondent is entitled to the decree for mandatory

injunction sought for. The suit was decreed. Appellant

challenged the decree and judgment before District Court,

Pathanamthitta in A.S.33 of 1989. Before the first appellate court

SA 411/1994 3

it was contended that as the Executive Engineer of Adoor

Division was not impleaded, suit is bad for his non-joinder. First

appellate court rejected the contention holding that there was no

plea of non-joinder and therefore it cannot be raised before the

appellate court. Learned District Judge also found that as

appellant Board is the second defendant, suit is even otherwise

not bad for non-joinder. Though it was contended that suit is

barred under Section 56 of the Electricity Act, learned District

Judge did not accept the said plea also. Appreciating the

evidence, learned District Judge upheld the findings of learned

Munsiff and dismissed the appeal. It is challenged in the second

appeal.

3. The second appeal was admitted formulating the

following substantial questions of law:-

1)Whether the suit is not bad for non-joinder of necessary

parties.

2)Whether the Section 56 of Indian Electricity Act is a bar to the

suit.

3)Whether a suit notice issued in 1981 will give rise to a cause

of action to institute a suit in 1985.

SA 411/1994 4

4. Learned counsel appearing for the appellant and first

respondent were heard.

5. Learned counsel appearing for appellant argued that as

the Executive Engineer, Adoor Division within whose jurisdiction

the disputed 11 KV line is drawn was not impleaded, the suit is

bad for his non-joinder and the finding of first appellate court is

not correct. Learned counsel further argued that the suit should

have been dismissed as barred under Section 56 of the

Electricity Act as the line was drawn bonafide. Finally, it was

argued that notice was sent in 1981 and therefore cause of

action for the suit could only be of 1981 and the suit instituted

in 1985 is not maintainable. Learned counsel appearing for first

respondent argued that as there was no plea of non-joinder

before the trial court, appellant is precluded from raising that

plea in the second appeal and as the Board is a party to the suit

the suit is not bad for non-joinder and in any case it is not a

substantial question of law. Relying on the decision of Apex

Court in M.P Electricity Board V. Vijaya Timber Company

(1997(1) SCC 68) learned counsel argued that when the line was

drawn without complying with the provisions of Electricity Act,

SA 411/1994 5

the suit is maintainable and as there is no exclusion of

jurisdiction the suit is not barred under Section 56 of the

Electricity Act. It was further argued that the cause of action

for the suit was the failure of the appellant Board to shift the 11

KV line drawn illegally without obtaining consent of the

appellant in spite of Ext.A2 notice sent on 23.8.1985 and the

cause of action is not that of 1981 as stated in the appeal

memorandum and therefore none of the questions formulated

are substantial questions of law involved in the appeal.

6. Though the appeal was admitted and substantial

questions of law were formulated, as provided under sub-section

5 of Section 100, when the appeal is heard on the questions of

law formulated under sub-section 4 of Section 100, respondent is

entitled to argue that the case does not involve the substantial

questions formulated. Therefore the fact that substantial

questions of law were formulated will not preclude first

respondent from contending that none of those questions are

substantial questions of law involved in the appeal.

7. As rightly pointed out by learned counsel appearing for

first respondent, in the absence of a plea before the trial court

SA 411/1994 6

that suit is bad for non-joinder of necessary parties, appellant is

not entitled to raise it in the second appeal. Even if it was

raised before the trial it cannot be a substantial question of law

involved in the appeal. Even otherwise when the Kerala State

Electricity Board itself is a defendant in the suit, the fact that the

concerned Executive Engineer was not impleaded in the suit will

not make the suit bad for non-joinder.

8. Section 56(1) of the Electricity Act 1910 reads:

” No suit, prosecution or other proceedings

shall lie against any public officer, or any

servant of a local authority, for anything

done, or in good faith purporting to be done,

under the Act”.

Sub-section 2 provides that :

“No court shall take cognizance of an

offence under the Act, by a public officer

except with the sanction-

a) in the case of a person employed in

connection with the affairs of the Union, of

the Central Government; and

SA 411/1994 7

b) in any other case, of the (State

Government).

Section 56 is a usual section inserted in similar enactments for

the protection of public servants, administrative or judicial

officers and is based upon the principle of public policy that an

officer entrusted with the responsibility of discharging certain

duties should be able to do so untramelled by the consideration

of his acts being called in question in a Court of law, or his

being liable to be sued for damages, should his action be legally

or technically erroneous. Section 56 confers immunity to a

public officer from a suit, prosecution or other proceedings not

only in respect of anything done in good faith but also where

they were done purporting to be in good faith. The protection

provided under Section 56 is to the public officer from personal

liability. It has nothing to do with a suit of this nature. The

Apex Court in M.P Electricity Board’s case (supra)

considered the plea of bar raised by the Board against a suit

directing the removal of electric line with poles situated in the

land belonging to a private party, on the allegation that it was

drawn against the provisions of the Act. The Apex Court held

SA 411/1994 8

that the remedy of the plaintiff was not taken away expressly or

impliedly and therefore the suit is maintainable. That exactly is

the position herein also.

9. The trial court and first appellate court on appreciating

the evidence, entered a factual finding that appellant Board had

shifted 11 KV line from its original position and drawn the line

over the property of respondent without the consent or

permission of first respondent and that too without complying

with the provisions of the Act. That factual finding cannot be

interfered in exercise of the powers of this court under Section

100 of Code of Civil Procedure. Courts below found that when

appellant contended that there was no shifting evidence of DW1

establish that there was a shifting of the allignment after

widening of M.C road and construction of a bridge. In such

circumstances, there is no merit in the appeal. It is dismissed.

M.SASIDHARAN NAMBIAR, JUDGE

lgk/-