High Court Kerala High Court

K.S.E.B vs P.Madhavan Nair on 10 June, 2009

Kerala High Court
K.S.E.B vs P.Madhavan Nair on 10 June, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

AS.No. 199 of 1997()



1. K.S.E.B.
                      ...  Petitioner

                        Vs

1. P.MADHAVAN NAIR
                       ...       Respondent

                For Petitioner  :SRI.P.V.KUNHIKRISHNAN

                For Respondent  :SRI.THOMAS ANTONY KALLANPALLY

The Hon'ble MR. Justice V.RAMKUMAR

 Dated :10/06/2009

 O R D E R
                                                         "CR"
                     V. RAMKUMAR, J.
                 = = = = = = = = = = = = =
                    A.S. No.199 of 1997
                 = = = = = = = = = = = = = =
            Dated this the 10th day of June, 2009

                         JUDGMENT

Defendants 1 and 2 (namely Assistant Executive

Engineer, Kerala State Electricity Board, Electrical Major

Section, Koyilandi and the Kerala State Electricity Board,

Thiruvananthapuram) in O.S.No.167 of 1994 on the file of the

Subordinate Judges Court, Koyilandi are the appellants in this

appeal. The said suit, instituted by the respondent herein,

was one for a declaration that Ext.A6 demand notice dated

25.8.1994 is null and void and not legally enforcible and for a

perpetual injunction restraining the defendants from

enforcing payment under the said demand notice.

2. The fact that the plaintiff installed a 1 HP electric

motor with pump set in his house was admitted. The main

contention raised by the plaintiff was that by installing the

pump set he was not committing breach of any of the

provisions of law or the Regulations issued by the Kerala

A.S.No.199 of 1997
2

Electricity Board (KSEB for short). The KSEB on the other

hand contended that by installing the pump set, the plaintiff

was increasing the sanctioned connected load of 400 watts

thereby attracting the penalty under Clause 42(d) of the

Regulations Relating to Conditions of Supply of Electrical

Energy (” Regulations” for short) issued by the KSEB in

exercise of the powers conferred on it by Section 79(j) of the

Electricity (Supply) Act, 1948.

3. The learned Subordinate Judge was of the view that

since the pump set installed by the plaintiff, although without

permission, was used for domestic purpose only, Clause 42(d)

of the Regulations was not attracted. According to the

learned Subordinate Judge, the said provision would be

attracted only if the consumer exceeded the contracted load

for a purpose different from the specific purpose

contemplated under the contract for that tarif. Accordingly,

the suit was decreed granting the declaration as well as

injunction prayed for. Hence this appeal.

4. After hearing both sides, I do not think that the view

A.S.No.199 of 1997
3

taken by the court below is sustainable. The specific case of

the defendants is that by installing the 1 HP pump-set

without the permission of the KSEB and without notice under

Clause 24 of the Regulations, the installation itself was

unauthorised. According to the KSEB, the authorised load for

the plaintiff’s premises was only 400 watts.

5. If Clause 42(d) of the Regulations is attracted, then

there is no dispute that the plaintiff will be treated as having

committed misuse of energy and liable to be billed at three

times the rate applicable to the respective tariff for the

previous six months from the date of detection of the misuse

as provided under Clause 42(d) of the Regulations.

Admittedly, the KSEB has billed the plaintiff at the above

rate for a period of two years which is not sanctioned by the

said Clause 42(d).

6. Ext.B12 is a true copy of the relevant page of the

Consumer’s Personal Deposit Register pertaining to the

plaintiff . It shows that a single phase connection to the

plaintiff’s house was given on 21.5.1977 with Consumer

A.S.No.199 of 1997
4

No.902 under Tariff I(a). It also shows that connected load

was 400 watts. The said load of 400 watts was fixed after

taking into account 6 light points and 2 plug points only.

Clause 24 of the Regulations reads as follows:-

” Should the consumer, at any time after the

supply of energy has been commenced, desire to

increase the number of wattage or capacity of

lights, fans or motors etc., on his premises on a

temporary or permanent basis or in any way alter

the position of his wiring therein, notice thereof

must be sent by the consumer in writing to the

Board whose representative will call and inspect

the alteration and, if necessary change meters and

fuses and alter the service line. For this purpose if

a single phase service line is to be converted to

three phase or change of size of conductor to meet

increased maximum demand is necessitated, the

work shall be done at the cost of consumer on

deposit work basis. A test report signed by a

licensed wiring contractor should also be produced

by the consumer along with his application for

extension and alteration. The consumer should

remit the testing fee. Failure to give such notice

A.S.No.199 of 1997
5

may derange the supply system and will render the

supply liable to be summarily discontinued.

During such time as alterations, additions or

repairs are being executed, the supply to the

circuit, which is being altered, added to or

repaired, must be entirely disconnected and it

shall remain disconnected until the alterations,

additions or repairs have been tested and passed

by the Board. In the event of any unauthorised

extensions, alterations or repairs resulting in any

damage to the system of the Board, the consumer

will have to pay the Board all expenses on account

of such damages also.

Note:-

i. Supply taken from the existing plug

point/mains to connect up any appliance

installed within the same premises, shall be

treated as additional load irrespective of

length of the connecting lead, if the

appliances installed are for bonafide

purpose.

ii. Supply taken from an existing plug

point/mains to any appliance situated

outside the premises will be treated as an

extension. Such extension should be taken

A.S.No.199 of 1997
6

only for temporary purposes.

iii. Supply taken from an existing plug point

for temporary film shows in Government

recognised Educational Institutions is

exempted from payment of testing fee, even

if it will be an extension vide Note (i) and (ii)

above. However, prior intimation should be

given to the local K.S.E.Board office about

this extension.

iv. If the installation remains disconnected for

a period exceeding one year the same shall

be reconnected to the distribution mains

only after conducting the tests prescribed

above.”

7. Thus, if the consumer at any time after supply of

energy has been commenced desires to increase the load on

his premises either on a temporary basis or on a permanent

basis, he has to give a notice in writing to the KSEB. As

already noticed, at the time of giving connection to the

plaintiff and fixing the connected load at 400 watts, 6 light

points & 2 plug points alone were sanctioned. If so, before

installing a 1 HP motor and pump-set, the plaintiff was bound

A.S.No.199 of 1997
7

to give notice under Clause 24 of the Regulations. Sub Clause

(d) of Clause 42 of the Regulations reads as follows:-

“If the consumer exceeds the contracted load

without prior permission of the Board or energy

supplied for a specific purpose under a particular

tariff is used without the Board’s knowledge and

approval for a different purpose not contemplated

in the contract for supply and for which higher

tariff is applicable coming under misuse of energy

within the meaning of the I.E.Act 1910. Misuse of

energy will be billed at three times the rate

applicable to the respective tariff for the previous

six months from the date of detection of misuse

unless there are convincing reasons for adopting

different periods and supply disconnected without

notice. The imposition of this higher rate will not

relieve the consumer from any penalties imposed

by law.”

8. This was a case in which the above clause was

squarely attracted since the plaintiff, who is the consumer,

had exceeded the contracted load without obtaining

permission of the Board under Clause 24. He thereby

A.S.No.199 of 1997
8

became liable to be billed at three times the rate applicable to

the respective tariff for the previous six months from the date

of detection. Merely because the factum of installation of the

pump-set came to the notice of the Board from the plaintiff

himself, the same does not absolve the plaintiff from his

liability to pay the penalty as provided under Clause 42(d) of

the Regulations. The argument advanced on the side of the

plaintiff that as long as he uses the pump-set only for

domestic purposes and consumes electricity within Slab III

(upto 30 units per month) which was allotted to him cannot

be sustained. The slab III in which the plaintiff was put all

these years was changed to Slab VIII (upto 100 units per

month) in the year 1994 consequent on noting the increased

consumption of power beyond Slab III after the unauthorised

installation of the motor and pump set.

9. The judgment and decree passed by the court below

overlooking the above vital aspects of the matter, are set

aside and the suit will stand dismissed. It is, however, made

clear that since under Ext.A6 invoice the defendants have

A.S.No.199 of 1997
9

billed the plaintiff for a period of 2 years as against the

maximum period of six months permissible under Clause 42

(d) above, the said bill cannot be enforced without rectifying

the mistake thereunder. Hence, the defendants will be

entitled to enforce payment against the plaintiff only after

issuing a revised bill in terms of Clause 42(d) of the

Regulations calculating the dues for a period of six months

only. It goes without saying that the defendants will be

entitled to charge interest on the amounts in the revised bill

to be issued hereinafter at the rates specified under sub-

clause (e) of Clause 32 of the Regulations, but only from the

date of the revised bill till realisation.

In the result this appeal is allowed to the limited extent

as indicated above. No costs.

Dated this the 10thday of June, 2009.

V. RAMKUMAR, JUDGE

sj