High Court Kerala High Court

Kerala State Electricity Board vs Sri.Shanmughan on 17 March, 2010

Kerala High Court
Kerala State Electricity Board vs Sri.Shanmughan on 17 March, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

CRP.No. 916 of 2007()


1. KERALA STATE ELECTRICITY BOARD,
                      ...  Petitioner
2. SRI. SHANMUGHAN,

                        Vs


1. SRI.SHANMUGHAN
                       ...       Respondent

                For Petitioner  :SRI.C.K.KARUNAKARAN, SC FOR KSEB

                For Respondent  : No Appearance

The Hon'ble MR. Justice S.S.SATHEESACHANDRAN

 Dated :17/03/2010

 O R D E R
              S.S.SATHEESACHANDRAN, J.
             ---------------------------------------
               C.M.Application No.1007 of 2007
                    & C.RP.No.916 of 2007
             ---------------------------------------
           Dated this the 17th day of March, 2010

                          O R D E R

Revision is directed against the order dated

15.10.1995 in O.P.(Ele)No.180/97 which was disposed of by a

common judgment with other petitions by the learned

Additional District Judge, Ad hoc-I, Ernakulam, awarding

enhanced compensation to the petitioner in the above

original petition. The respondent in the original petition, the

Kerala State Electricity Board [hereinafter referred to as ‘the

Board’] has filed the revision contending that the enhanced

compensation awarded by the court is excessive and

unreasonable. The revision was filed with a petition to

condone the delay of 144 days. Though notice was ordered

on the delay petition, till date, steps have not been taken by

the Board. The learned counsel appearing for the Board

sought for one more opportunity for taking steps on the delay

petition.

C.R.P.No.916 of 2007

:: 2 ::

2. Considering the fact that the revision has been

filed as early as in 2007 and steps have not been taken taken

so far, I find it necessary to examine the merit of the order

impugned to consider whether a fresh opportunity is to be

given to the Board for taking steps against the respondent

warranting a disposal of the revision on merits after hearing

the respondent.

3. I heard the learned counsel for the Board.

4. From the impugned order and also from the

submissions made by the learned counsel, it is seen that 110

KV electric lines from Bhrahmapuram to Panampilly Nagar

were drawn through the property of the respondent/claimant,

and the claim had been raised in respect of the loss sustained

by him.

5. It is seen from the order that the claimant had

possession of only 2.5 cents of land situated in Vyttila, a most

prominent place in the Kochi city. Towards the value of the

trees cut and removed, the Board had paid a sum of Rs.421/-.

C.R.P.No.916 of 2007

:: 3 ::

The claimant had claimed compensation for the injurious

affection over his land by the drawing of the line. The court

below, considering the market value of the land and taking

into account the injurious affection on account of the drawing

of the line, determined such compensation and awarded a

sum of Rs.39,375/- to the claimant. The land value was

fixed at Rs.45,000/- per cent and diminution of the land

value was determined at 35%. The learned District Judge

found that the entire extent of 2.5 cents owned and

possessed by the claimant suffered injurious affection by the

drawing of the line. The learned counsel for the Board

impeaches the correctness of the assessment of centage value

and also the percentage of diminution of value fixed by the

learned District Judge contending that both are excessive.

6. I do not find any merit in the submission. It is

seen that the centage value was fixed on the basis of a

commission report collected by deputing an advocate

commissioner and also examining other relevant materials

C.R.P.No.916 of 2007

:: 4 ::

produced in the case. Electric lines were drawn over the

property of the petitioner for drawing of 110 KV line. In the

case of 110 KV line and 220 KV line, it goes without saying

that not only the area through which the lines passed, but

also sufficient area on both sides have to be kept unhindered

for facilitating the free flow of energy. A clearing area has to

be provided to see that no obstruction is caused to the flow

of energy though such lines.

7. Having regard to the fact that the claimant

had only 2.5 cents over which 110 KV electric line has been

drawn, I find no impropriety or illegality in the conclusion

formed by the learned District judge that the entire area was

injuriously affected by the lines drawn over that property.

Over that small plot, the claimant is now prevented from

putting up any structure or growing any high yielding trees.

Practically, the whole property, so far as the claimant is

concerned, has been rendered useless.

C.R.P.No.916 of 2007

:: 5 ::

8. Viewed in the back drop that the land is

situated in a prominent place in the Kochi city, I find, the

compensation awarded by the court below cannot be

considered as excessive or unreasonable. In such

circumstances, I find that there is no merit in the revision.

Petition for condonation of delay and the revision

are dismissed.

Sd/-

(S.S.SATHEESACHANDRAN)
JUDGE
sk/-

//true copy//