High Court Kerala High Court

Kerala State Electricity Board vs V.K.Moosa on 17 February, 2009

Kerala High Court
Kerala State Electricity Board vs V.K.Moosa on 17 February, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WA.No. 363 of 2009()


1. KERALA STATE ELECTRICITY BOARD,
                      ...  Petitioner
2. EXECUTIVE ENGINEER
3. ASST.EXECUTIVE ENGINEER,

                        Vs



1. V.K.MOOSA, S/O.MOIDEEN HAJI
                       ...       Respondent

                For Petitioner  :SRI.C.K.KARUNAKARAN, SC FOR KSEB

                For Respondent  : No Appearance

The Hon'ble MR. Justice V.GIRI

 Dated :17/02/2009

 O R D E R
                      J.B. KOSHY, Ag.C.J. &
                              V.GIRI, J.
             -------------------------
                       W.A.No.363 of 2009
             -------------------------
              Dated this the 17th day of February, 2009.


                           JUDGMENT

GIRI, J.

The Board challenges the judgment of the learned single

Judge, by which the levy of penalty charges, effected by the Board

consequent upon unauthorised connected load in the unit run by the

petitioner, was quashed to the extent to which penal charges was

levied on electricity charges as well.

2. The learned single Judge proceeded to observe that it

is settled law that in view of the Bench decision in W.A.No.1231/03

that penalty has to be limited to the fixed charges portion and that

there shall not be penalty by way of proportionate energy charges.

3. It is contended that in the instant case, inspection of

the premises of the consumer was effected on 6.7.2002; that the

Division Bench has upheld the right of the Board to levy penalty

charges on the electricity charges component also in respect of

cases, which have been detected prior to 18.9.2002, the date on

which the amended Board order came into force. It is, therefore,

W.A.No.363 of 2009

:: 2 ::

contended that the law laid down by the Division Bench has not been

correctly applied by the learned single Judge.

4. Learned counsel for the Board is correct in submitting

that the Bench of this court in W.A.1231/03 has held that the Board

order dated 18.9.2002, which directs the levy of penal charges to be

restricted to the fixed charges alone, does not have retrospective

operation. But, we are of the view that, notwithstanding the same,

the levy of penal charges on electricity charges also may not be

justified in the present case. We proceed to take this view, in the

facts and circumstances of this case.

5. We take note of the fact that, according to the

consumer, a 7.5 HP motor was purchased only on 10.6.2002.

6. The counter affidavit of the Electricity Board does not

refer to any attempt at tampering the meter. In fact, the

consumption patterns reveals reduction of consumption from June,

2002. The case of the consumer, that a new meter was installed,

instead of the old meter and this resulted in reduction of the

consumption, cannot be brushed aside. Further, the consumer also

has a case that the factory was facing problems and this is one of

the reasons why the consumption has come down.

W.A.No.363 of 2009

:: 3 ::

7. There is yet another crucial factor, which dissuades us

from interfering with the judgment of the learned single Judge.

According to the writ petitioner, the premises in question were not

inspected by the officials of the Electricity Board prior to the issuance

of the impugned bill.

8. Though in the counter affidavit it is stated that the

premises were inspected by the Sub Engineer, along with the line

man and reference is made to Ext.R1(a) site mahazar, we do not

find an averment in the counter affidavit that a copy of the site

mahazar was supplied to the consumer or forwarded to him. It is

significant because, according to the consumer, no inspection, as

alleged by the Electricity Board, took place on 6.7.2002 and no team

inspected the premises, as such, prior to the impugned bill. In the

mahazar, it is stated that the persons, who have found at site

refused to witness the drawing up of the mahazar. If that be so, a

copy of the mahazar could either have been affixed or later could

have been forwarded to the consumer, along with the impugned bill.

There is no case that the same has been done. We also take note of

the fact that Ext.R1(a) mahazar is seen to have been drawn up by

the Sub Engineer in charge of the vehicle section, Velanthavalam.

W.A.No.363 of 2009

:: 4 ::

9. In the facts and circumstances of the case, especially in

the absence of a significant variation in the consumption pattern, we

are of the view that it would not be appropriate to sustain the levy of

penalty charges on electricity charges as well.

10. In these circumstances, we are inclined to uphold the

directions issued by the learned single Judge, though not for the

same reasons as those which found favour with the learned single

Judge.

Writ appeal is disposed of with the above directions.

Sd/-

(J.B. KOSHY)
ACTING CHIEF JUSTICE

Sd/-

(V.GIRI)
JUDGE
sk/

//true copy//

P.S. to Judge