High Court Rajasthan High Court - Jodhpur

Krishan Vallabh vs M/S Ram Chandra Kumawat & Company & … on 29 September, 2008

Rajasthan High Court – Jodhpur
Krishan Vallabh vs M/S Ram Chandra Kumawat & Company & … on 29 September, 2008
                                              S.B.Civil Misc. Appeal No.696/2008
                                    The State of Raj. through Addl. Chief Engineer
                                    vs. M/s Ramchandra Kumawat & Co.and anr.
                                                      and another connected appeal
                              1.
 IN THE HIGH COURT OF JUDICATUARE FOR RAJASTHAN AT
                      JODHPUR.

                           JUDGMENT


       (1) S.B. Civil Misc. Appeal No. 696/2008

          The State of Raj.,        vs    M/s Ramchandra
          through Addl. Chief             Kumawat & Co.
          Engineer, & ors.                & another.

      (2) S.B. Civil Misc. Appeal No. 611/2008

          Krishan Vallab      vs.           M/s Ramchandra
                                            Kumawat & Co. And
                                            others.


                 under Order 43 Rule 1(r), CPC against the
           order dated 3.5.2008 passed by the Addl.
           District & Sessions Judge No.3, Udipuar in Misc.
           Case No.14/2008.

   Date of Judgment:                September 29th, 2008.

                          PRESENT
              HON'BLE MR. PRAKASH TATIA, J.


Mr. Rameshwar Dave, Dy.G.A. for the State in Appeal
Nos.696/08b & 611/08.
Mr. Ravi Bhansali for the appellant in Appeal No.611/08 and
for respondent no. 2 in Appeal No.696/08
Mr. Rajesh Joshi for the respondent no.1 in both the appeals.
                                                   S.B.Civil Misc. Appeal No.696/2008
                                        The State of Raj. through Addl. Chief Engineer
                                        vs. M/s Ramchandra Kumawat & Co.and anr.
                                                          and another connected appeal
                                 2.

BY THE COURT:

These two appeals have been preferred to challenge the

order dated 3.5.2008 passed by the court of Addl. District Judge

No.3, Udaipur in Civil Misc. Case NO.14/08 by which the trial court

granted injunction order against giving work to the appellant

Krishna Kumar. The Works in question are in relation to work out of

package for which notices inviting tenders NO. 28 /PMGSY/2007-

2008 was issued on 4.2.2007.

According to the plaintiff, he was competitive bidder for the

work in question and as the officers of the respondent had grudge

against the plaintiff-respondent, therefore, with malafide

intention and to blame respondent-plaintiff, the tender of the

appellant-defendant no.4 was accepted even when the appellant-

defendant’s tender was liable for rejection because of the reason

that the tender documents were incomplete as the requisite price

for the five years maintenance of the work was not mentioned by

the defendant-appellant in the tender documents and some of the

pages of tender document were not signed by him and further the

offer was non-responsive.

S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
3.
The trial court after considering Conditions No.25.1, 25.2,

25.3 as well as clause 8.3, held that the tender document of the

appellant-defendant no.4 was incomplete, as he did not give any

rates for the five years maintenance and did not sign that part of

the document and, therefore, the tender document was non-

responsive and since it has not been signed, therefore, it was liable

to be rejected as per clause 25.1, 25.2 and 25.3 of the conditions

of the tender. The trial court rejected the contention of the State

as well as the rival contractor that if any amount is not mentioned

in the document for any work, then that work cost is required to

be treated included in the rates mentioned by the contractor for

whole of the work. The learned trial court also was of the view

that contention of the defendant-appellant that main work in the

contract was construction of the roads and was not its

maintenance, also cannot be accepted. The plaintiff in addition to

relief of prohibitory injunction against the respondent, sought

mandatory injunction in its favour for grant of work order in his

favour. However, the trial court was of the view that no case is

made out by the plaintiff-respondent no.1 for issuing work order in

his favour by interim order. In view of the above reasons, the trial
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
4.
court granted the only prohibitory injunction in favour of

respondent-plaintiff and refused mandatory injunction to the

plaintiff.

The defendant-contractor has preferred Appeal no.611/08,

whereas the State has preferred Appeal no. 696/08 to challenge

the said order dated 3.5.2008.

According to the learned counsel for the appellant-

contractor, the appellant contractor submitted his bid knowing it

well that as per Condition No.39.3, the contractor can submit his

price for whole of the contract work by giving bids so as to cover

maintenance cost for roads for five years after completion of

construction of roads in the main work cost and which the

appellant-defendant contractor did in present transaction. The

Condition No.39.3 clearly provides that items of the works for

which no rate or price has been entered in the Bills of Quantities,

will not be paid for by the Employer and shall be deemed covered

by other rates and prices in the contract. To make this position

clear, the appellant-contractor submitted before the authorities in

writing also. As per clause 32.1, the performance security taken

from the contractor, which says that successful bidder/contractor
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
5.
shall provide to the contractor total performance security of five

percent of the contact price, for a period of five years and the

time of completion of construction work plus additional security

for unbalanced bids in accordance with clause 27.3 and 27.4 of ITB

and clause 46 Part-I General condition of contract. It is also

submitted by the learned counsel for the appellants that the

principal work is of construction of roads and maintenance for five

years is ancillary work. The trial court failed to appreciate the

distinction between two works. It is submitted that two works may

have been the part of the same contract, but at the same time,

the nature of the work cannot be ignored. The major work under

the contract is construction of roads.

The learned counsel for the appellant-State vehemently

submitted that the appellant himself got the contract for other

works from the appellant-State under the same/similar

advertisement inviting tenders by submitting tender form with

some pages without signatures of the plaintiff-respondent and yet

has challenged the act of the respondent when the bid was not

came in favour of the respondent-plaintiff. It is also submitted that

absolutely false and baseless allegations of malafide have been
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
6.
levelled by the plaintiff against the officers of the appellant-State

and that too without impleading any of the officers as party in the

suit and in the petition for grant of injunction. It is also submitted

that in a matter of mere breach of contract, adequate relief can

be obtained by filing a suit for damages and the plaintiff cannot

get the contract in his favour in present suit. Therefore, no

injunction could have been granted by the trial court. It is also

submitted that in a matter of public importance affecting the

public at large, the courts are expected to slow in granting

injunction so as to put a complete halt over the work for public

benefit. The learned counsel for the appellant relied upon several

judgments of the Hon’ble Supreme Court in support of his

contention.

The learned counsel for the respondents vehemently

submitted that this fact is not in dispute that some of the pages of

the tender document have not been signed by the appellant-

contractor and signing of the document and each page of the

document only can make the tender document a valid document of

tender. In case the documents are not signed or any of the

requirement is unfilled, then the tender document cannot be
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
7.
considered and required to be rejected. Clause 8.3 clearly provides

that the bidder is expected to examine carefully all instructions

and conditions of contract and in case bid is not substantially

responsive to the requirements of the bid documents then on this

ground alone, the document is required to be rejected. Clause

18.2. further provides that all pages of bid document shall be

signed by the persons or person signing the bid. Clause 25.1 also

specifically provides that during detailed evaluation of technical

bids, it will be looked into that the bid has been properly signed

and is responsive to the requirement of bidding document. What is

substantially responsive, has been explained under Condition

NO.25.2 and it prohibits the rectification of bid in any manner.

Clause 25.3 is specific provision for rejection of financial bid, if it

is not substantially responsive and also provides that a bid which is

not substantially responsive, may not be subsequently be made

responsive by correction or withdrawn of the nonconforming

deviation or reservation.

The learned counsel for the respondent-plaintiff relief upon

the judgment of the Delhi High Court delivered in the case of P.K.

Delicacies Pvt. Ltd. vs. Union of India (2005(2) CTLJ 134 (Delhi)
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
8.
wherein the annexed document was not filled up and signed then

the Division Bench of the Delhi High Court held that it is an

important part of tender bid and was required to be filled up and

signed by the person giving the bid. The Division Bench of the Delhi

High Court held that the failure to fill up the said document,

cannot be a technical irregularity of little or no significance and,

thereafter, it has been held that as a general rule, tender

conditions has to be strictly adhered to and the authorities

concerned have power to reject and not to consider the tender

which is incomplete and lacking any particulars.

The learned counsel for the respondent-plaintiff further

relied upon the judgment of the Gauhati High Court delivered in

the case of R.N. Ghosh vs. State of Tripura and others ( 2000(3)

Arb.LR 64 (Gauhati), wherein there was condition that the bidder

shall put his full signature on every page of rate schedule. In that

case the bidder put his initials only in place of full signatures and

that was found non-compliance of the requirement by the Gauhati

High Court. It is also submitted that in some cases where the rates

were required to be given in figure as well as in words and have

not been given so, has been considered as non-compliance of the
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
9.
conditions of the tender.

The learned counsel for the respondents also relied upon

judgment of the Hon’ble Apex Court delivered in the case of W.B.

State Electricity Board vs. Patel Engineering Co. Ltd. and others

( (2001) 2 SCC 451), wherein Hon’ble the Apex Court held that the

principle of awarding contract to lowest tenderer applies when all

things are equal and there is no obligation to award contract to

lowest bidder and in this case, according to the learned counsel for

the respondent, the respondent is prepared to do the work on the

rates given by the defendant-appellant-contractor and, therefore,

there cannot arise any question of loss to the State or public.

The learned counsel for the respondent-plaintiff vehemently

submitted that no plea was taken by the State or the appellant-

contractor that the plaintiff-respondent-contractor himself

submitted tender document with some blank pages or without

signing of the pages. This pleas has been taken for the first time in

argument before this Court, which cannot be entertained.

I considered the submissions of the learned counsel for the

parties and perused the facts of the case.

There cannot be any doubt that in the matter of award of
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
10.
the contract for public work by the Government agencies, the

Government agencies cannot act arbitrarily. The Government

agencies are required to see the compliance of all the conditions

which can certainly prevent the favoritism and avoid harm because

of the bias as well as to prevent corruption in the matter of

awarding work contact of huge amount to the contractor. It is also

true that mere offer of low price cannot be ground for grant of

award of contract and the contractor is required to full fill all

other eligibility criteria. Which condition is essential condition of

the contract, depends upon the facts of each case. In a case where

short signatures were put in place of full signatures of the bidder,

the court held that it is non-compliance of the requirement for

giving offer but that cannot be applied as a rule in all contracts. In

the case of R.N. Ghosh (supra), there was specific requirement of

signing the document with full signatures and in the facts of the

case, the court held that the initial or short signatures of the

bidder was violation of the condition. As stated above, this

proposition cannot be accepted as rule of general law in each and

every case. Here in this case, the alleged violations are that the

defendant-appellant-contractor did not mention the rates for
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
11.
maintaining the roads for five years after completion of roads. If it

is looked into without noticing the complete contract and the

conditions applicable for the contract, then it is a serious matter.

If the bid could have been rejected only on this ground, then there

was no reason for providing Condition No.39.3, which specifically

provides that in case no rate or price has been entered in the bills

of quantities for the works, no amount will be paid by the

employer to the contractor for said unquoted price and it shall be

deemed that the rates and prices are already covered by other

rates and prices given in the contract. The appellant-contractor

submitted in writing to the defendants, the government agencies

that his bid includes the maintenance price for the roads, is not

any addition, alteration or variation in the offer of defendant-

appellant so as to hit by clause 25.3. Clause 25.3 only provides that

if a bid is not substantially responsive, it cannot be made

responsive, subsequently by (a) correction or (b) withdrawal of the

nonconforming deviation or (c) reservation. The correction,

withdrawal, deviation and reservation cannot be equated with

making the position clear only by pointing out towards the real

facts and meaning of the offer. The documents, therefore, was
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
12.
inclusive of the cost or rates for maintenance of the roads for five

years.

If there can be unfilled column for cost of work and the cost

of that work stands included in the price given for other items in

the tender document and the contractor is not claiming any

benefit out of that part of the contract and, therefore, has not

signed the said page of the contract, it cannot materially affect

the document so as to say that the tender document was not

“substantially responsive” or was incomplete.

In view of the above reason, the trial court failed to

appreciate the facts of the case properly and committed error of

law in interpreting the clauses of the conditions of the tender

document and the relevant conditions. In the case of B.S.N. Joshi

& Sons Ltd. vs. Nair Coal Services Ltd. & ors. ( (1006) 11 SCC 548),

the Hon’ble Court considered issue of essential conditions and

substantial compliance with essential condition in the matter of

government contracts and also made it clear what is aims and

object of the tender conditions. Hon’ble the Apex Court held that

the tender conditions may have to be construed differently having

regard to the facts situation obtaining in each case and no hard
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
13.
and fast rule can be laid down therefor. Hon’ble the Apex Court

held that when a decision is taken by the appropriate authority

upon due consideration of the tender document submitted by all

the tenderer on their own risk and if it is ultimately found that

successful bidders had in fact substantially complied with the

purport and object for which essential conditions were laid down,

the same may not ordinarily be interfered with by the court.

In view of the above reason, there appears to be no prima

facie case in favour of the plaintiff-respondent.

If we look into the question of irreparable injury, then in

government contract of the nature which is involved in this case,

there is commercial interest of the contract but, at the same time,

the beneficiaries of the work is the public. There may be very

many reasons for challenge to giving of the contract to one of the

parties and one of the important aspect may also be that the

corruption which is required to be curbed by the courts, when the

facts are brought to the notice of the court. Here in this case, the

plaintiff even after alleging the malafide and favoritism, could not

substantiate his plea and, therefore, it appears that the plaintiff

is seeking stay against the public work only on the basis of mere
S.B.Civil Misc. Appeal No.696/2008
The State of Raj. through Addl. Chief Engineer
vs. M/s Ramchandra Kumawat & Co.and anr.

and another connected appeal
14.
technical objections which may cause greater hardship to the

public at large and loss to the State exchequer also. In contrast,

the plaintiff is not likely to suffer such irreparable injury which can

be compensated by money.

In view of the above reason, there appears to be no balance

of convenience in favour of the plaintiff.

Hence the appeals of the appellants are allowed. The

injunction order granted by the trial court dated 3.5.2008 is set

aside. The injunction application of the plaintiff is dismissed. No

order as to costs.

(PAKASH TATIA),J.

mlt