High Court Kerala High Court

M.N.B.Nair vs The Fact Engineering And Design on 1 February, 2008

Kerala High Court
M.N.B.Nair vs The Fact Engineering And Design on 1 February, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

AR No. 19 of 2007()


1. M.N.B.NAIR,
                      ...  Petitioner

                        Vs



1. THE FACT ENGINEERING AND DESIGN
                       ...       Respondent

                For Petitioner  :SRI.K.L.VARGHESE

                For Respondent  :SRI.A.M.SHAFFIQUE

The Hon'ble MR. Justice PIUS C.KURIAKOSE

 Dated :01/02/2008

 O R D E R
                         PIUS C. KURIAKOSE, J.


                         A.R. NO. 19   OF 2007


                DATED THIS THE 1st February 2008


                                    ORDER

This application has been filed under Section 11(6) of the

Arbitration and Conciliation Act, 1996 seeking appointment of

an Arbitrator in accordance with law by a Contractor to the

respondent company in respect of the work of “Implementation

of Hazardous Waste landfill for FACT – Primary and Secondary

Leachate Collection Layers” under Work Order No.32180-C0506

dated 13-12-2005 which was followed by execution of a formal

agreement. It is submitted that as per the contract, the work

costing Rs.13,55,000/- had to be completed within four months

from the date of handing over the site, whereas the respondent

was not able to handover the site for more than an year. In the

meanwhile whatever materials to be supplied had been supplied

by the applicant. Undisputedly, the respondent could not hand

over the site or give facilities to do the work since another

agency who had to do part of the job had not done so. In the

A.R.NO. 19/2007 -2-

meanwhile, the cost of construction increased disproportionately

high and the applicant sought for enhancement of rates. Though

the respondent convened a meeting and gave an impression that

enhancement of rates would be recommended ultimately, the

request for enhancement of rates was turned down and the

contract was terminated followed by encashment of Bank

Guarantee amount of Rs.1,35,500/- and withholding of final bill

amount of Rs.5,83,060/-. The disputes having thus arisen are

liable to be settled in arbitration. Article 41 of the Proforma

Contract is an arbitration clause. Article 41 which is extracted in

the application would show that the Chairman & Managing

Director of the respondent Company is the nominated

Arbitrator. Since the respondent was not prepared to refer the

dispute in arbitration in that regard, the applicant has invoked

the appointment procedure contemplated by Section 11(6) of the

Arbitration and Conciliation Act. Even though several chances

were given to the respondent for filing counter affidavit, till this

moment the counter affidavit has not been filed. The averments

in the application stand established.

A.R.NO. 19/2007 -3-

The result is that the Arbitration Request will stand

allowed. Sri. S.Sainudheen, the retired District & Sessions Judge

is appointed as Arbitrator to settle the disputes between the

parties which are subject matters of Annexure-A1 claim notice.

The Arbitrator will also settle the counter claims, if any, which

were raised by the respondent through their claim statement.

The Arbitrator will enter on reference at his earliest and pass

award without undue delay.

PIUS C. KURIAKOSE, JUDGE

ks

A.R.NO. 19/2007 -4-

This application has been filed under Section 11(6) of the

Arbitration and Conciliation Act, 1996 to appoint an Arbitrator in

accordance with law by the applicant, who is Contractor to the

respondent company in respect of the work of “Implementation

of Hazardous Waste landfill for FACT – Primary and Secondary

Leachate Collection Layers” under Work Order No.32180-C0509

dated 19-1-2006 which was followed by execution of a formal

agreement. It is submitted that as per the contract, the work

costing Rs.14,93,500/- had to be completed within four months

form the date of handing over the site, whereas the respondent

was not able to handover the site for more than a year. In the

meanwhile whatever materials to be supplied had been supplied

by the applicant. Undisputedly, the respondent could not hand

over the site or give facilities to do the work since another

agency who had to do part of the job had not done so. In the

meanwhile, the cost of construction increased disproportionately

A.R.NO. 19/2007 -5-

high and the applicant sought for enhancement of rates. Though

the respondent convened a meeting and gave an impression that

enhancement of rates would be recommended ultimately, the

request for enhancement of rates was turned down and the

contract was terminated followed by encashment of Bank

Guarantee amount of Rs.1,49,3,50/- and withholding of final bill

amount of Rs.1,46,296/-. The disputes having thus arisen are

liable to be settled in arbitration. Article 41 of the Proforma

Contract is an arbitration clause. Article 41 is extracted in the

application which would show that the Chairman & Managing

Director of the respondent Company is nominating Arbitrator.

Since the respondent was not prepared to refer the dispute in

arbitration in that regard, the applicant has invoked the

appointment procedure contemplated by Section 11(6) of the

Arbitration and Conciliation Act. Even though several chances

were given to the respondent for filing counter affidavit, till this

moment the counter affidavit has not been filed. The averments

in the application stands established.

The result is that the Arbitration Request will stand

A.R.NO. 19/2007 -6-

allowed. The retired District & Sessions Judge…….. is appointed

as Arbitrator to settle the dispute between the parties which is

subject matter of Annexure-A1 claim notice. The Arbitrator will

also settle the counter claims, if any, which were raised by the

respondent through in their claim statement. The Arbitrator will

enter on reference at his earliest and pass the award without

undue delay.

PIUS C. KURIAKOSE, JUDGE

ks

A.R.NO. 19/2007 -7-