High Court Kerala High Court

M.S.Arvind vs The Additional District … on 18 January, 2010

Kerala High Court
M.S.Arvind vs The Additional District … on 18 January, 2010
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 36425 of 2009(W)


1. M.S.ARVIND, AGED 46 YEARS,
                      ...  Petitioner

                        Vs



1. THE ADDITIONAL DISTRICT MAGISTRATE,
                       ...       Respondent

2. THE DEPUTY CHIEF ENGINEER,

3. ASSISTANT EXECUTIVE ENGINEER,

4. CORPORATION OF COCHIN,

5. WATER FRONT ENCLAVE RESIDENTS ASSN.,

6. C.K.VIJAYAN, S/O.KUNHIKRISHNA MENON,

7. P.K.THANKAM, D/O.KUNHIKRISHNA MENON,

                For Petitioner  :SRI.SANTHEEP ANKARATH

                For Respondent  :SRI.P.P.THAJUDEEN, SC, K.S.E.B

The Hon'ble MR. Justice P.R.RAMACHANDRA MENON

 Dated :18/01/2010

 O R D E R
                   P.R.RAMACHANDRA MENON, J
                  -----------------------------
                       W.P(C) No.36425 of 2009 -W
                 ------------------------------
              Dated this the 18th day of January, 2010.

                        J U D G M E N T

The issue involved in this Writ Petition is whether the first

respondent is right in keeping the dispute with regard to the

shifting of the transformer in abeyance, while the authorities under

the Kerala State Electricity Board are proceeding with the steps for

laying the cables so as to connect the same to the transformer

where it exists as on date.

2. The sequence of events as projected by the petitioner

shows that the transformer was installed on the southern side of the

properties, which was close to the petitioner’s house by about 1.5

meters. Subsequently, the petitioner took up the matter before the

Board for shifting the transformer to another convenient place as

suggested.

3. After considering the facts and figures, the petitioner

was directed to pay a sum of Rs.53,000/- for shifting the

transformer to the alternate site. It is stated that the petitioner has

remitted the amount. But subsequently, the residents association of

W.P(C) No.36425 of 2009 -W 2

the locality approached this Court challenging the order passed by

the first respondent for shifting the transformer; whereupon the

same was set aside and the matter was directed to be considered

afresh by the Additional District Magistrate, after hearing all the

parties concerned within six weeks as specified therein. It is the

case of the petitioner that, despite the specific direction given by

this Court, the matter is still kept in cold storage by the Additional

District Magistrate and in the meanwhile, the KSEB has started laying

the underground cables. It is contended that, once the cables are

connected with the transformer, the petitioner would not be in a

position to enjoy the fruits of the order likely to be passed by the

first respondent in favour of the petitioner.

4. The learned standing counsel appearing for the Board

submits with specific reference to the statement filed on behalf of

the Board, that the work has to be completed in a time bound

manner, as it comes within the project of the Kochi City Automation

Scheme, whereby nearly 200 Kms 11 KV Over Head lines in the city

will be altered to under ground cables for maintaining uninterrupted

power supply in Kochi city. The execution of the said work was

started on 5.10.2009 and targeted to be completed before

W.P(C) No.36425 of 2009 -W 3

31.3.2010. It is also stated in para 3 of the said statement that,

even if the under ground cable is connected to the transformer, the

transformer will be shifted, if the Additional District Magistrate

directs such shifting. More so, when the Board is bound to comply

with the direction of the Additional District Magistrate; who is the

statutory authority in this regard.

5. The learned Government Pleader appearing for the first

respondent submits on instructions, that the matter could not be

finalised by the Additional District Magistrate due to many a reason

including for want of some clarification to be furnished from the

Electrical Inspectorate with reference to technical aspects, which is

stated as being procured within no time. The learned Government

Pleader however submits that the matter will be considered and

finalised at any cost within one month.

6. Considering the facts and circumstances, particularly the

assertion made by the respondent Board in para 3 of the statement

as to the feasibility aspect in removing the cables subject to the

orders to be passed by the Additional District Magistrate, the

apprehension expressed by the petitioner in this Writ Petition

appears to be acted upon and this Court does not find it fit and

W.P(C) No.36425 of 2009 -W 4

proper to keep the Writ Petition pending any further.

7. In the above facts and circumstances, the contents of the

statement filed on behalf of the Board and the submission made by

the learned Government Pleader on behalf of Additional District

Magistrate are recorded. The first respondent/Additional District

Magistrate is directed to finalise the proceedings forthwith, also

considering the feasibility of the alternate site now suggested by the

petitioner on the southern side of the Water Front Road Junction,

where the basement for Ring Maintenance Unit has already been

constructed.

The Writ Petition is disposed of as above.

Sd/-

P.R.RAMACHANDRA MENON
JUDGE

//True Copy//

P.A to Judge

ab