Facts
arising from the Complaint:
Mr. Katar Singh Tanwar had filed a RTI application with the PIO, Land &
Building department, GNCT of Delhi, B-Block, New Delhi on 09/06/2008 asking for
certain information. Since no reply was received within the mandated time of 30 days, he
had filed a complaint under Section 18 to the Commission.
The Commission issued a notice to the PIO on 26/05/2009 asking him to supply
the information by 26/06/2009 and sought an explanation for not furnishing the
information within the mandated time. The PIO has informed the Commission vide letter
dated 11/06/2009 that the information had been provided to the complainant.
Decision:
The Complaint is allowed.
The Commission condones the delay and warns the PIO to ensure that
information is given to applicants with in 30 days as mandated under Section 7 (1) of the
RTI act.
Shailesh Gandhi
Information Commissioner
June 26, 2009.