Central Information Commission Complaint No.CIC/SM/C/2009/000365 Right to Information ActÂ2005ÂUnder Section (18) Dated: 4 August 2010 Name of the Complainant : Shri Vimal Chandra Azad Bhawan, Sahabganj Chowk, Farrukhabad - 209 625. UP. Name of the Public Authority  : CPIO, State Bank of India, Local Head Office, Moti Mahal Marg, Lucknow - 226 001. On behalf of the Respondent, Shri Mitra, CPIO was present.
2. We heard this case through videoconferencing. The Complainant wasÂ
not present. The Respondents were present in the Lucknow studio of the NIC.Â
The CPIO had already sent his written explanation to us on 11 November 2009.Â
In our order dated 15 October 2009, we had directed the CPIO to provide theÂ
desired information to the Complainant as well as to explain the reasons for theÂ
delay.  The  Respondents  submitted  that  the  RTI  application  had  not  beenÂ
received at all in the office of the CPIO. They came to know about this onlyÂ
when our order reached them. The  CPIO has since provided the  availableÂ
information to the Complainant.
3. In view of the above, the case is disposed of without any further directionÂ
or orders.
4. Copies of this order be given free of cost to the parties.
(Satyananda Mishra)
CIC/SM/C/2009/000365
Information Commissioner
Authenticated true copy.  Additional copies of orders shall be supplied againstÂ
application and payment of the charges prescribed under the Act to the CPIO of thisÂ
Commission.
(Vijay Bhalla)
Assistant RegistrarÂ
CIC/SM/C/2009/000365