High Court Kerala High Court

M/S.Traco Cable Company Ltd vs The Asst.Commissionr on 20 November, 2009

Kerala High Court
M/S.Traco Cable Company Ltd vs The Asst.Commissionr on 20 November, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 32448 of 2009(A)


1. M/S.TRACO CABLE COMPANY LTD.
                      ...  Petitioner

                        Vs



1. THE ASST.COMMISSIONR,DEPT. OF
                       ...       Respondent

2. FAST TRACK TEAM, DEPT. OF COMMERCIAL

3. THE COMMISSIONR DEPT.OF COMMERCIAL TAXES

                For Petitioner  :SMT.S.K.DEVI

                For Respondent  : No Appearance

The Hon'ble MR. Justice C.K.ABDUL REHIM

 Dated :20/11/2009

 O R D E R
                 C.K. ABDUL REHIM, J.
              - - - - - - - - - - - - - - - - - - - - - - -
                 W.P.(C)No. 32448 of 2009
              - - - - - - - - - - - - - - - - - - - - - - -
        Dated this the 20th day of November, 2009


                        J U D G M E N T

1. Petitioner is a company fully owned by the

Government of Kerala. Assessment under the Kerala

General Sales Tax Act, 1963 (KGST Act) for the years

2002-03, 2003-04 were completed as per Exts.P3 & P5. So

also assessment under the Central Sales Tax Act (CST Act)

with respect to the same years were completed as per

Exts.P4 & P6. The said assessments were completed by

invoking Section 17 D of the KGST Act, by the 2nd

respondent. The petitioner submitted applications under

Section 23 B for payment of amounts due under the

Amnesty Scheme and those applications were allowed as

evidenced by Ext.P7 to P10. It is submitted that the

petitioner had already remitted the first installment which

pertains to 25% covered under Exts.P7 to P10 orders. Now

the petitioner is challenging Exts.P3 to P6 orders of

W.P.(C)No. 32448 of 2009
-2-

assessment issued under Section 17 D on the ground that

those assessment orders are issued in total violation of the

procedure contemplated under Section 17 D.

2. A Division Bench of this court in a batch of writ

petitions considered challenge against the validity of

Section 17 D of the KGST Act. Eventhough validity of

Section was upheld, the impugned assessment therein were

quashed with the following observations.

“Even though we have upheld the validity of

the statutory provisions, we are unable to uphold

the impugned assessments for the simple reason

that the none of the assessments challenged in

the Writ appeals or in the Writ petitions was

completed in accordance with the procedure

contemplated under section 17D. It is clear from

clause (g) of Section 17 D(2) that the team

constituted under section 17 (D) should fix the

venue and date of hearing and hold sitting to hear

the parties after issuing notice in advance to

W.P.(C)No. 32448 of 2009
-3-

dealers concerned. Further, information in this

regard should be published in local media as well.

It is provided in Sub section (3)o f Section 17 D

that all assessments under Fast Track Method

should be unanimous decision signed by all team

members. It is very clear from the scheme that all

the team members should sit together, consider

the returns filed, accounts and records produced,

hear the parties or their representatives and

suggest proposal for assessment. If an

assessment by consent can be passed, then

assessment order should be passed in accordance

with the terms agreed in first sitting itself. The

assessments that could be completed in the first

sitting are cases where team of Assessing Officers

accept the returns filed or with such additions

which the party agrees. On the other hand, if

assessment is proposed in deviation with turnover

returned or against additions over and above if

W.P.(C)No. 32448 of 2009
-4-

any agreed by the parties, then it is for the very

same team to issue pre-assessment notice

containing proposal for assessment and the same

should be signed by all of them. The party should

be given sufficient time to file objections and the

next date of public hearing by the committee

should be informed to the party. Assessment has

to be complete after hearing the party by team on

the objection filed to the pre-assessment notice

and in order to have a binding assessment, the

assessment should be one completed with

unanimous agreement of all the team members,

In fact, ex-parte assessment is contemplated only

when parties who are served notice informing the

venue and date of hearing fail to appear. Here

again, we are of the view that there is no harm in

giving one more opportunity, if the team of

officers feel that the party is not absenting

deliberately. Since in all these cases assessments

W.P.(C)No. 32448 of 2009
-5-

are completed by issuing pre-assessment notice

by individual officers, we feel that the procedure

contemplated and stated by us above is not

strictly followed and so much so, orders passed

cannot be sustained under the provision of

Section 17 D. We, therefore allow the writ

appeals and writ petitions in part by vacating the

impugned assessment orders, but with direction

to the assessment team to complete the

assessment afresh under section 17 D within a

period of three months from the date of receipt of

copy of this judgment after issuing notice to all

parties and after hearing their objections. We

make it clear that each and every objection raised

by the parties in the reply to pre-assessment

notice should be considered and unanimous

decision should be taken by the team members.

We do not want to examine the other issues

raised in some of the cases like challenge against

W.P.(C)No. 32448 of 2009
-6-

other statutory provisions, challenge against

penalty orders etc. These issues are left open. We

leave freedom to the parties to challenge the

penalty orders before statutory authorities

because those are not issued under section 17 D.

So far as challenge against other statutory

provision are concerned, we leave it open to the

parties to raise any such challenge, if required,

after completion of assessments afresh as stated

above”.

3. In view of the observations contained in the

Judgment of the Division Bench, which is quoted above, I

am of the opinion that the orders impugned in this writ

petition, Ext.P2 to P6, are unsustainable and they are liable

to be quashed. Accordingly I quash Exts.P2 to P6 orders.

The 2nd respondent is directed to issue fresh orders strictly

in compliance with the directions contained in the judgment

of the Division Bench as early as possible, at any rate within

a period of three months from the date of receipt of copy of

W.P.(C)No. 32448 of 2009
-7-

this judgment.

4. Needless to say that the amount already paid by

the petitioner by virtue of Exts.P7 to P10 orders shall be

appropriated in accordance with the outcome of the fresh

assessment to be issued.

C.K. ABDUL REHIM
JUDGE

shg/