High Court Kerala High Court

Muhammed vs The Deputy Collector on 9 July, 2008

Kerala High Court
Muhammed vs The Deputy Collector on 9 July, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

CRP.No. 370 of 2005()


1. MUHAMMED, S/O. PAREETHM,
                      ...  Petitioner

                        Vs



1. THE DEPUTY COLLECTOR,
                       ...       Respondent

2. THE PETRONET C.C.K.LIMITED REPRESENTED

                For Petitioner  :SRI.P.K.MOHAMMED PUZHAKKARA

                For Respondent  :SRI.M.PATHROSE MATTHAI (SR.)

The Hon'ble MR. Justice M.SASIDHARAN NAMBIAR

 Dated :09/07/2008

 O R D E R
                  M.SASIDHARAN NAMBIAR, J.
                    ...........................................
                     CRP.No. 370              OF 2005
                    ............................................
         DATED THIS THE             9TH        DAY OF JULY, 2008

                                   ORDER

Petitioner filed O.P.33 of 2001 before Additional District

Court, North Parvur, claiming enhanced compensation for

drawing of pipe line of Petroleum products under C.C.K.Karur –

Kochi Petronet Project. The total extent acquired is 0.726

hectares. Petition was not filed within the period provided

under Petroleum and Minerals Pipe Lines (acquisition of right of

user in land)Act, 1962(hereinafter referred to as ‘the Act’).

Under Section 10 of the Act, a person interested in the land

under which pipeline is proposed to be laid or is being or has

been laid, is entitled to such damage, loss of injury, the amount

of which shall be determined by the competent authority in first

instance. Under Rule 5, an application for determination of

compensation by any party aggrieved by the determination of the

amount of compensation, is to be filed not later than 90 days

from the date of receipt of intimation from the competent

authority as provided under sub-rule 3 of Rule 4. Petitioner filed

the petition before Additional District Court only 303 days from

that day. Hence a petition was filed under Section 5 of the

CRP 370/2005 2

Limitation Act to condone the delay. Learned District Judge, as

per the impugned order, dismissed the petition to condone the

delay and consequently dismissed the petition. It is challenged in

this revision petition filed under Section 115 of Code of Civil

procedure.

2. Learned counsel appearing for petitioner and the

respondent were heard at the admission stage itself.

3. The respondent is not disputing the power of the court to

condone the delay in filing the petition as provided under Rule 5

of the Petroleum Pipelines (acquisition of right and user in land)

Rules, 1963(hereinafter referred to as ‘the Rules’). The only

question is whether petitioner has satisfactorily explained the

delay and if so, whether delay is liable to be condoned. Learned

counsel appearing for petitioner argued that petitioner was

informed that his claim for enhanced compensation would be

referred to the court as in the case of Land Acquisition cases and

he never knew that there is a period of 90 days provided for

filing a petition. It was contended that petitioner bonafide

believed that he could file a petition as provided under the

Telegraph Act and it is in such circumstances, petition was not

filed within the period provided under Rule 5 of the Rules and

CRP 370/2005 3

therefore learned District Judge should have condoned the

delay.

4. Learned counsel appearing for respondent argued that

ignorance of law is not an excuse and for that reason delay

cannot be condoned. It was also argued that when delay was not

properly explained and reason shown is not satisfactory, learned

District Judge was justified in not condoning the delay and

therefore there is no illegality or irregularity warranting

interference.

5. It cannot be disputed that petitioner is not to gain

anything by purposely protracting the filing of the petition.

Delay is not to the advantage of the petitioner to any extent. In

such circumstances, it cannot be said that delay was caused

wilfully. At best, it could be said that petitioner was negligent.

The question is whether for that negligence, petitioner is to be

denied the benefit provided under the Act, if the delay could be

compensated by cost.

6. In such circumstances, in the interest of justice, I.A.200

of 2001 filed by petitioner to condone the delay will stand

allowed on petitioner paying a cost of Rs.1000/- to respondent,

within two weeks from today. If the cost is paid, revision petition

CRP 370/2005 4

will stand allowed and delay, as sought for in I.A.200 of 2001,

will stand condoned. In that event, Additional District Judge,

North Paravur shall dispose O.P 33 of 2001 in accordance with

law. If the cost is not paid, CRP will stand dismissed, confirming

the order passed by learned District Judge.

M.SASIDHARAN NAMBIAR, JUDGE

lgk/-