High Court Kerala High Court

National Insurance Company Ltd vs Sarasu on 18 June, 2009

Kerala High Court
National Insurance Company Ltd vs Sarasu on 18 June, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

MACA.No. 809 of 2003()


1. NATIONAL INSURANCE COMPANY LTD.
                      ...  Petitioner

                        Vs



1. SARASU D/O. PALLIPADY,
                       ...       Respondent

2. M.Y.BABY, MANJEERAN HOUSE,

3. SURAJ K.S. S/O. SREEDHARAN, KADAYATH

                For Petitioner  :SRI.RAJAN P.KALIYATH

                For Respondent  :SRI.M.V.SABU

SHRI K.J.THOMAS STANLEY(RETD.ADDL.DIST.JUDGE)

 Dated :18/06/2009

 O R D E R
                       SRI.M.R.RAJENDRAN NAIR
        (SENIOR ADVOCATE, HIGH COURT OF KERALA)
                                   &
                            SRI.M.T.BALAN
                        (RETD. DISTRICT JUDGE)
      =================================
                         M.A.C.A.No.809 of 2003
      =================================
                  Dated this the 18th day of June, 2009

                                AWARD

      Appellant - Insurance Company and counsel are present. 1st

respondent and counsel are also present. Both parties agreed that out

of the Award amount of Rs.1,19,500/-(Rupees one lakh nineteen

thousand and five hundred only) a sum of Rs.15,000/-(Rupees fifteen

thousand only) can be reduced and the Award can be limited to

Rs.1,04,500/-(Rupees one lakh four thousand and five hundred only)

together with interest at the rate of 9% per annum from the date of

petition till realisation.

      Award accordingly modified by consent. The balance amount

with interest can be withdrawn by the claimant.




                                   M.R.RAJENDRAN NAIR
                    (SENIOR ADVOCATE, HIGH COURT OF KERALA)




                                       M.T.BALAN
                                (RETD. DISTRICT JUDGE)
dvs


? IN THE HIGH COURT OF KERALA AT ERNAKULAM

+OP.No. 7109 of 2003(U)


#1. M/S. HI-TECH ELECTOTHERMICS (P) LTD.,
                      ...  Petitioner

                        Vs



$1. STATE OF KERALA, REPRESENTED BY
                       ...       Respondent

2. KERALA STATE ELECTRICITY BOARD,

3. SPECIAL OFFICER (REVENUE)

4. EXECUTIVE ENGINEER, KERALA STATE

!                For Petitioner  :SRI.J.JULIAN XAVIER

^                For Respondent  :SRI.P.SANTHALINGAM, SC, KSEB

*Coram
 The Hon'ble MR. Justice V.K.MOHANAN

% Dated :15/06/2009

: O R D E R

V.K.MOHANAN, J.

———————————————

O.P.No. 7109 of 2003 – U

———————————————
Dated this the 15th day of June, 2009

J U D G M E N T

The petitioner is a consumer of electrical energy

under H.T.Tariff with consumer No.19/2030. He challenges

Exts.P5, P6, P8 and P9 orders. Admittedly, the meters

installed in the petitioner’s premises were defective and the

same was intimated to the consumer vide Ext.P1. In Ext.P1,

it is stated that the meter was to be replaced within one month

after testing at T.M.R. Division, Pallom. It is beyond dispute

that as per the rules and procedures, only the Board officials

can remove the meter and accordingly, the meter was

removed only on 12.4.2002 even though Ext.P1 is dated

4.4.2002. According to the petitioner, after curing the defect,

he handed over the same to fourth respondent on 2.5.2002

for calibration, but according to the Board, it was handed over

only on 4.5.2002. However, according to the petitioner, after

calibrating the repaired meter, the same was given back to

the petitioner only on 29.5.2002. Hence, with a covering letter

dated 30.5.2002, the petitioner again entrusted the same with

the Board authorities for installation, but finally, the meter was

OP NO.7109 OF 2003

:-2-:

reinstalled only on 3.6.2002. In the mean while, Ext.P2 bill was

issued for the electrical energy used by the petitioner for the

month of April,2002 and the same was remitted in time.

According to the petitioner, even in Ext.P2, by way of remark as

warning was given to the petitioner that 50% extra would be

charged in the next bill if the rectification of meter is not made

before the issue of next bill. Ext.P2 is dated 10.5.2002 and

therefore, the next bill means, bill dated at least 10.6.2002. Thus,

according to the petitioner, the meter was installed on 3.6.2002

and therefore, the meter was installed within one month even

from the date of Ext.P2 that is, 10.5.2002. Therefore, it is the

contention of the petitioner that the Board has no authority to

realise the penal charge from the petitioner.

2. The Board has filed a detailed counter affidavit

justifying Exts.P5,P6,P8 and P9. According to the learned

counsel for the Board, the consumer is liable to pay the penal

charge if there is laches or default on his part in installing the

meter after curing the defect, if once the defect is brought to his

notice. Learned counsel also very much relied upon the

provisions of the Kerala State Electricity Board Extra High

Tension Tariff Revision Order (for short ‘the Tariff Revision

OP NO.7109 OF 2003

:-3-:

Order) , 2002.

3. I have heard both counsel for the petitioner as well

as the respondents.

4. Learned counsel for the petitioner submits that one

month’s time is incorporated in the Tariff Revision Order 2002

which came into force with effect from 1.10.2002 whereas Ext.P1

is dated 4.4.2002 and the meter was re-installed after curing the

defect on 3.6.2002. Therefore, the provisions of Tariff Revision

Order 2002 would not be applicable in the present case. Learned

counsel also invited my attention to Tariff Revision Order, 2001

which was relied on by the Board while filing the counter affidavit.

There is no provision in the Tariff Revision Order,2001 fixing the

time limit for reinstalling the meter after curing the defect. If that

be so, absolutely there is no provision enabling the Board to

realise the penal charge from the consumer. In the present case,

it is relevant to note that though Ext.P1 is dated 4.4.2002, the

Board officials removed the defective meter only on 12.4.2002

and handed over the same to the petitioner on that date.

Thereafter, the petitioner, after curing the defect, again entrusted

the meter with the fourth respondent for calibrating the meters, on

4.5.2002. But the said meter was returned to the petitioner only

OP NO.7109 OF 2003

:-4-:

on 29.5.2002 and there is a delay of 25 days from the part of the

Board authorities in returning the meter to the petitioner. Again

with a covering letter dated 30.5.2002, the Board Officials were

requested to install the meter, but the same was done only on

3.6.2002. There is no material or evidence to show that the

petitioner was requested or intimated regarding the completion of

the work relating to the calibration of the meter before 29.5.2002.

Therefore, it cannot be said that there is any failure or lapse on

the part of the petitioner. As there is no time limit in the Tariff

Revision Order, 2001 and the meter has already been installed

on 3.6.2002, there is no justification for realising the penal charge

from the petitioner.

5. When Ext.P6 was issued, the petitioner approached

this Court by filing O.P.No.20648 of 2002 , which was disposed of

directing the Board authorities to reconsider the matter and thus,

the petitioner had preferred Ext.P7 before the second respondent

and he issued Ext.P8 order. As per Ext.P8, it is seen that he had

asked the Special Officer (Revenue), K.S.E.B,

Thiruvananthapuram to revise Ext.P6 bill and to effect

proportionate reduction in the penal charges for the period from

4.5.2002 to 15.5.2002 (11 days) in the penal bill for

OP NO.7109 OF 2003

:-5-:

Rs.3,45,438/-. Thus, Ext.P9 was issued for an amount of

Rs.1,60,814/-, which is not in accordance with rules and

regulations which were in force during the relevant time.

6. In the light of the above discussion, it can be seen

that the Board is not entitled to realise penal charges from the

petitioner in the given facts and circumstances of the present

case and therefore, Exts.P5,P6,P8 and P9 are legally and

factually not sustainable and the same are liable to be quashed.

In the result, Exts.P5,P6,P8 and P9 are quashed and

the Original Petition is allowed.

V.K.Mohanan,
Judge

MBS/

OP NO.7109 OF 2003

:-6-:

V.K.MOHANAN, J.

——————————————–

O.P.NO. 7109 OF 2003

——————————————–

J U D G M E N T

DATED: 15-6-2009

OP NO.7109 OF 2003

:-7-: