High Court Kerala High Court

Peermohammed P.S. vs The Special Tahsildar on 28 August, 2008

Kerala High Court
Peermohammed P.S. vs The Special Tahsildar on 28 August, 2008
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

WP(C).No. 35776 of 2007(H)


1. PEERMOHAMMED P.S., PARAKKAVETTY,
                      ...  Petitioner

                        Vs



1. THE SPECIAL TAHSILDAR,
                       ...       Respondent

2. THE EXECUTIVE ENGINEER,

3. THE CHIEF ENGINEER (ROADS AND BRIDGES),

                For Petitioner  :SRI.SIBY MATHEW

                For Respondent  :GOVERNMENT PLEADER

The Hon'ble MR. Justice PIUS C.KURIAKOSE

 Dated :28/08/2008

 O R D E R
                        PIUS C. KURIAKOSE, J.
               -----------------------------------------------
                       W.P.(C)No. 35776 OF 2007
               -----------------------------------------------
               Dated this the 28th day of August, 2008

                            J U D G M E N T

The writ petitioner is a person whose land was acquired for the

construction of Changanassery bye pass 3rd reach. According to him,

he was absolute owner in possession of 8.46 Ares of land in Block

No.139, Sy. No.11/1 as per schedule B to document No.471/1961 of

Sub Registry Office, Changanassery. On the basis of request from the

second respondent – Executive Engineer, PWD Roads Division,

Kottayam steps were initiated for acquisition of a total extent of

2.1831 hectares of land comprised in various survey numbers of

Changanasserry Village for the construction of Changanasserry bye-

pass road. After the publication of the initial notification under Section

4(1), necessary survey was done and finally declaration under section

6 of the Land Acquisition Act was also promulgated. Thereafter, award

enquiry was conducted and on participating in the award enquiry, the

petitioner produced documents relating to title and possession over his

property to be acquired and Ext.P1 award was passed by the Land

Acquisition Officer. As per Ext.P1 award, total amount of Rs.2,43,51/-

WP(C)N0. 35776/07
-2-

is fixed as compensation for 8.46 Ares of land at the rate of

Rs.20,646/- per Are. Thereafter, possession notice under 15(3) was

given to the petitioner and pursuant to that, the petitioner’s land was

taken possession by the first respondent. Ext.P2 is a copy of the

Mahazar prepared by the Tahsildar at the time of taking over the

possession. Sketch of the land acquired from the petitioner is also

shown in Ext.P2 Mahazar. The petitioner states that prior to the

acquisition, through out the entire stretch of the land acquired on

either side, a boundary wall having a width of 2 ft. was constructed

with rubble and concrete. In the meanwhile, the petitioner received

the award amount under protest and as requested by him a reference

under Section 18 was made to the competent Sub Court. It is

submitted that thereafter the land has been acquired upto the

Kaviyoor road for the purpose of the bye-pass and the entire stretch of

the land acquired has been filled with red earth. Though the proposed

bye-pass road has not been formally inaugurated, the public have

already started using the bye-pass road. Ext.P3 is the claim statement

filed by the petitioner before the reference court and it will be seen

there from that the petitioner has raised a claim for injurious affection

of the remaining land before the reference court. The petitioner

WP(C)N0. 35776/07
-3-

submits that to his great surprise and agony during the weeks prior to

the institution of the writ petition (during the last weeks of November

2007), some officials and staff of the office of the Special Tahsildar

came to the petitioner’s property and measured the petitioner’s land

lying adjacent to the acquired land. On enquiry, the petitioner’s son

was informed by those officials that three metres of land is taken

possession over and above the land already taken. No convincing and

sound reason has been given by the officials for their act. The specific

request to the petitioner to give written notice has invited no

response. After measurement, the personnel of the office of the first

respondent has kept two poles in the petitioner’s property, 3 metres

away from the property already taken possession from the petitioner.

The petitioner says that the present move to take possession of

additional land from the petitioner is only to help adjacent land owner.

The respondents are not entitled to take additional land from the

petitioner without due notice and without referring to the provisions of

the Land Acquisition Act. On the above averments, the petitioner

raises various grounds and seeks following reliefs in the writ petition:

i. Issue a writ of prohibition restraining the respondents from
taking possession of any land from the petitioner other than
the land already taken possession of from the petitioner on
the basis of Ext.P1 award and Ext.P2 Mahazar.

WP(C)N0. 35776/07
-4-

ii) Issue a declaration that the respondents can take possession
of any additional land from the petitioner only after resorting
to the provisions in the Land Acquisition Act.

2. The respondent has filed a detailed counter affidavit through

the Valuation Assistant (Deputy Tahsildar) attached to his office. It is

contended therein that the acquired land was handed over to the

Public Works Department, the requisitioning authority on 25-11-2005

by observing the prevailing rules under the Act. No constructions were

made or allowed in the land acquired by the land acquisition officer

before the date of handing over. On 25-11-2005, the date of handing

over, the land stood vested with the Public Works Department and the

land acquisition officer is not responsible for any activities said to have

been done in the land acquired from the petitioner. It is further stated

in the counter affidavit that on examining the alignment of the

neighbouring plot which was handed over to the Public Works

Department as per the order in WP(C). No. 30969/06 (the case in

which one Mariamma Francis was the petitioner) the officials found

that there is encroachment in Block No.139, survey No.11/1 in the

land which had been acquired from the petitioner. On 10-12-2007 a

notice from Sri.A.A.Mohammed Nazir, Advocate of the petitioner dated

6-12-2007 was received by the land acquisition officer alleging that the

WP(C)N0. 35776/07
-5-

land acquisition officer is dumping waster materials in the land

belonging to the petitioner. On 10-12-2007 itself reply was given to

the advocate refuting the allegations since the land acquisition officer’s

office is not involved in any of the alleged activities. PWD is the

custodian of the land now and a sum of Rs.2,43,751/- has been

awarded to the petitioner as compensation for the acquired land. At

the instance of the petitioner the question of determination of the

correct compensation has been referred to the Sub Court, Kottayam

where L.A.R. No.26/06 is pending. The land acquisition officer has no

intention to acquire the balance land belonging to the petitioner and

the allegations levelled against the land acquisition officer are

baseless. On considering the prayer for interim relief this court on5-

12-2007 passed an order of “interim stay” restraining the respondents

from taking possession of any land from the petitioner other than the

land already taken possession of from him on the basis of Ext.P1

award and Ext.P2 mahazar. That interim order is continuing.

3. To the counter affidavit submitted by the land acquisition

officer the petitioner has through his power of attorney holder filed a

reply affidavit. Ext.P4 produced along with the reply affidavit is copy

of the lawyer notice dated 6-12-2007 which was issued allegedly when

WP(C)N0. 35776/07
-6-

it was noticed that waste was being dumped into the petitioner’s

property by the officials and staff of the first respondent. The reply

affidavit denies the contentions in the counter affidavit that while

examining the plot acquired from Smt.Mariamma Francis it was seen

that there was encroachment into the property which had been taken

over from the petitioner. That allegation is described in the reply

affidavit as irresponsible, vague and totally incorrect. It is stated that

when the officials of the first respondent were measuring the property

of the petitioner, petitioner’s son Zakir Hussain enquired about the

reason for the measurement and even at that time it was not alleged

that there was encroachment. If there is encroachment the same

could be verified by conducting re-measurement. It is claimed that

the petitioners residential house is situated on the southern extremity

of the remaining property. The residential plot of the petitioner is

having well defined boundaries on all the four sides. The said plot is

bounded by compound wall on all the four sides. It is from the

remaining 44 cents of the petitioner that the respondents have

acquired 8.46 ares for the construction of Changanacherry Bypass 3rd

Reach Part I. Having regard to the lie of the property of the petitioner

described above, the allegation of encroachment made in the counter

WP(C)N0. 35776/07
-7-

affidavit can only be a pigment of imagination. Rough sketch showing

the lie of the bypass road, railway station road and the petitioner’s

residential building and the remaining land belonging to the petitioner

is produced as Ext.P5. Reply affidavit reiterates the allegation that the

present attempt of the respondents is to take possession of land of the

petitioner in addition to the land already acquired under Ext.P1 award.

Petitioner does not want even an inch of land acquired from the

petitioner. At the same time respondents are not entitled to take

additional land from the petitioner without due notice and without

resorting to the provisions in the Land Acquisition Act.

4. Considering the pleadings and on hearing initial submissions

of the counsel for the petitioner and the learned Govt.Pleader,

K.Padmanabhan Nair, J. passed the following interim order on 10-3-

2008.

“The operation of interim order is extended by three months.

In the nature of the contentions raised by the counsel for
the petitioner, I am of the view that a joint inspection has to be
conducted, by the District Collector or an officer not below the
rant of ADM/RDO, with the superintendent of roads and Bridges,
on the land acquired from the petitioner and near the
neighbouring area.

Hence, there will be a direction to the District Collector,
Kottayam, and also to the Superintendent, Roads and Bridges,
who is in charge of this particular area, to physically supervise,

WP(C)N0. 35776/07
-8-

to conduct inspection and to file a report, with due notice to the
petitioner, and file a report with sketch countersigned by both
sides. It is made clear that work shall not be entrusted to lower
staff and the actual measurement shall be conducted either by
the Superintendent of survey and land records or the senior
officer attached to that office in the presence of District Collector
or the Superintending Engineer.

Inspection shall be conducted within three weeks from
today with due notice to the petitioner and file a report.

Post after three weeks.”

Pursuant to that order inspection and measurement were conducted

and the Govt. Pleader has filed Annexure-A report and Annexure-B

sketch. It is reported in Annexure-A that the District Collector,

Kottayam, the Superintendent of Survey, Kottayam, the Assistant

Executive Engineer PWD (Roads) Changanacherry and the Special

Tahsildar LA (General) Kottayam, the power of attorney holder of the

petitioner and son of the petitioner were present at the time when

inspection and survey were conducted. Total extent of land acquired

from the petitioner as per the award is 8.46 ares. After acquisition of

the land in Sy. No. 11/1 the property was divided into three parts.

The western part which takes in the balance land in the possession of

the petitioner including the site of his house – 25.61 ares, the middle

part which is the acquired land – 8.46 ares and the eastern part which

is balance property of the petitioner – 4.64 ares. At the time of the

WP(C)N0. 35776/07
-9-

inspection it was noticed that the petitioner had encroached into 0.074

ares which was already acquired and handed over to the PWD in the

northern side. The retaining wall constructed by the PWD at the

eastern side was moved to 3.4 metres into the property of the

petitioner, i.e. 0.35 ares at the south eastern end. It is further

reported that the petitioner has encroached into another 0.80ares of

PWD purambokku land and attached the same to the property of the

petitioner. Apparently the petitioner has stealthily replanted the

boundary stones fixed by the land acquisition authorities in order to

retain a good front yard for his residential building situated at the

western side of the road. The department unaware of the secret plans

of the petitioner, was on the wrong notion that the boundary stones

planted by the land acquisition authorities were kept intact and

constructed retaining walls at one side. The contentions of the

petitioner are found to be incorrect. The above points were explained

to the petitioner. It is pointed out in the report that survey was done

in the presence of the surveyor who had been arranged by the

petitioner and that surveyor was also convinced of the above facts.

5. Along with the above report a sketch prepared by the

Surveyor attached to the District Superintendent of Survey and Land

WP(C)N0. 35776/07
-10-

Records, Kottayam is produced. To the report and the sketch the

petitioner has filed a statement of objections taking exception to the

allegation in the report that the petitioner had encroached into 0.74

Ares of land already acquired and handed over to the P.W.D. on the

northern side. According to the objections, serious mistakes have

crept into the report. Exception is taken to the allegation that the

retaining wall constructed by the PWD at the eastern side was moved

3.4 metres into the property of the petitioner. It is pointed out that no

details are given in the report indicating the correctness of the above

allegation. Exception is taken to the allegation in the report that 0.80

Ares of PWD Purambokku has been further encroached upon and to

the allegation that the petitioner had stealthily replanted the boundary

stones fixed by the land acquisition authorities for the purpose of

retaining a good front yard for his residential building situated at the

western side of the road. It is submitted that in between the

residential building of the petitioner and the railway station road on the

eastern side there is a compound wall made of hard laterite stone with

rubble foundation. It is further submitted that there is a mud wall on

the northern boundary of the residential property. This laterite stone

wall and the mud wall are more than 50 years old. It is pointed out

WP(C)N0. 35776/07
-11-

that the advocate commissioner deputed from the reference court has

reported on these aspects. It is claimed that there is no Purambokku

land in the area and the old survey records such as O.M. sketch, blue

print measurement of the entire area, co-relation statement from the

Village Officer, settlement register etc. will clearly show that there is

no Purambokku land in the area. It is then submitted that the records

produced by the L.A. Officer before the Sub Court in the reference case

under section 18 will not tally with the sketch and report now produced

by the respondent in this case.

6. Very strenuous arguments were addressed before me by the

learned counsel for the petitioner Sri.A.A.Mohammed Nazir and

Mr.Basant Balaji, learned senior Government Pleader. My attention

was drawn by Mr.Nazir to the pleadings and to the documents. He

submitted that the report and the sketch submitted before this court

on the basis of the joint inspection conducted cannot be correct since

there is considerable variation between the sketch prepared in

connection with passage of award and taking over of possession which

is available in the land acquisition file produced before the land

acquisition reference court in L.A.R. No. 26/06 and the present sketch.

Counsel submitted that it is a very innocuous prayer which has been

WP(C)N0. 35776/07
-12-

made in the writ petition and that there is every justification for

confirming the interim order which was issued by this court on 5-12-

2007.

7. The prayers in the writ petition would certainly look

innocuous. But granting those prayers will pre-suppose a finding by

this court that the respondent Government has attempted to take

possession of properties belonging to the petitioner not covered by the

acquisition without recourse to the provisions of the Land Acquisition

Law. I am not convinced on the basis of the materials produced in this

case and the submissions addressed at the Bar that the apprehension

voiced by the petitioner in this writ petition that there is an attempt on

the part of the respondents to dispossess the petitioner of his property

not covered by the award. The joint inspection and measurement was

conducted with notice to the petitioner and it is not disputed that the

measurement was conducted in the presence of the power of attorney

holder of the petitioner, the son of the petitioner and a private

surveyor who had been arranged by the petitioner. I am prima facie

convinced that Annexure-B sketch produced along with the report of

the District Collector has been prepared on the basis of the

measurement and facts revealed on the inspection and discloses the

WP(C)N0. 35776/07
-13-

state of affairs existing as of now. This court under Article 226 of the

Constitution is not expected to resolve complicated disputes regarding

title and possession over immovable property which is raked up by the

petitioner through the objections filed by him to the report and the

sketch. The question which arises in this writ petition is only whether

it can be stated on the basis of the available materials in this case

whether there is warrant for interdicting the respondents from

dispossessing the petitioner of his properties. The said question

according to me, can only be decided in the negative.

8. The writ petition will stand dismissed. However, it is made

clear that this judgment does not decide finally regarding the

correctness of the allegations in the report submitted by the District

Collector that the petitioner is an encroacher of Purambokku nor does

it foreclose petitioner’s remedy before a regular civil court in the

event of accrual of any genuine cause of action against the

Government or public officers. The parties will suffer their costs.

(PIUS C.KURIAKOSE, JUDGE)
ksv/dpk