IN THE HIGH COURT OF KERALA AT ERNAKULAM
CRP.No. 469 of 2004()
1. POWER GRID CORPORATION OF INDIA LTD.,
... Petitioner
Vs
1. DIVAKARAN, S/O. RAMAN,
... Respondent
For Petitioner :SRI.K.P.DANDAPANI (SR.)
For Respondent : No Appearance
The Hon'ble MR. Justice HARUN-UL-RASHID
Dated :05/06/2008
O R D E R
HARUN-UL-RASHID, J.
------------------------------------------
C.R.P No. 469 of 2004
-------------------------------------------
Dated this the 5th day of June 2008
ORDER
This revision petition is filed by the petitioner challening the order
in O.P(EA) No. 56/2002 on the file of the Additional District Judge
Kottayam , awarding additional compensation of a sum of Rs. 13593/-
with interest at the rate of 6% per annum. The revision petitioner is the 1st
counter petitioner in the above said O.P. The court below on a detailed
evaluation of the evidence on record, granted a nominal enhancement
finding that the compensation fixed by the Electricity Board is not
adequate. I find no reason to interfere with the order awarding nominal
enhancement of compensation in this case.
This Civil Revision Petition is without any merit; it is accordingly
dismissed. There will be no order as to costs.
HARUN-UL-RASHID, JUDGE