Judgements

Power Grid Corporation Of India … vs Karnataka Power Transmission … on 23 March, 2007

Central Electricity Regulatory Commission
Power Grid Corporation Of India … vs Karnataka Power Transmission … on 23 March, 2007
Bench: A Basu, B Bhushan


ORDER

1. The petition has been filed (a) for approval of transmission tariff for 40% Fixed Series Compensation on Gooty-Neelmangala 400 kV S/C transmission line-II at Gooty (hereinafter referred to as the transmission asset-I) and (b) for revision of transmission tariff for 40% Fixed Series Compensation on Gooty-Neelmangla 400 kV S/C transmission line-I and on Nagarjunasagar-Cuddapah 400 kV S/C transmission lines (hereinafter referred to as the transmission asset-II) in Southern Region from the date of commercial operation of the respective transmission asset to 31.3.2009, based on the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2004, (hereinafter referred to as the 2004 regulations) after accounting for additional capitalization during 2004- 05 and 2005-06. These assets are collectively referred to as the transmission scheme. The petitioner has also prayed for the reimbursement of expenditure incurred towards publication of notices in the newspapers and the petition filing fee by the beneficiaries.

2. The investment approval for the transmission scheme was accorded by the Board of Directors of the petitioner company vide letter dated 22.10.2002 at an estimated cost of Rs. 5793 lakh, including IDC of Rs. 443 lakh. The dates of commercial operation of the respective transmission asset are as stated below:

 Name of the transmission assets         Date of commercial operation
Transmission asset-I                        1.5.2005
Transmission asset-II                       1.11.2004

 

3. The provisional transmission charges for the transmission asset-I were approved by the Commission in its order dated 13.2.2006 in Petition No. 96/2005.

4. The Commission by its order dated 16.11.2006 had allowed tariff for the transmission asset-II for the period 1.11.2004 to 31.3.2009. The Commission in its said order dated 16.11.2006 had not considered additional capital expenditure beyond the date of commercial operation and the tariff was worked out on the basis of gross block of Rs. 4003.22 lakh as on 1.11.2004. The transmission tariff approved was as under:

(Rs. in lakh)
2004-05 2005-06 2006-07 2007-08 2008-09
(1.11.2004
to 31.3.2005)
Depreciation 58.93 141.42 141.42 141.42 141.42
Interest on Loan 104.51 242.42 227.59 208.85 189.14
Return on Equity 53.08 127.38 127.38 127.38 127.38
Advance against Depreciation 0.00 0.00 64.72 93.42 93.42
Interest on Working Capital 6.39 15.37 16.58 17.12 17.16
O & M Expenses 35.15 87.75 91.26 94.89 98.70
Total 258.05 614.35 668.96 683.09 667.23

5. The petitioner has claimed the transmission charges as under:

 

Transmission asset-I 
                                                                (Rs. In lakh)
                            2005-06     2006-07     2007-08     2008-09
                           (Pro rata)
Depreciation                  46.93       52.61       52.61       52.61
Interest on Loan              69.95       78.38       72.73       66.76
Return on Equity              54.75       61.38       61.38       61.38
Advance against Depreciation   0.00        9.01       18.87       18.87
Interest on Working Capital    5.00        5.81        6.01        6.04
O & M Expenses                26.81       30.42       31.63       32.90
Total                        203.44      237.61      243.23      238.55


 

Transmission asset-II 
                                                                     (Rs. in lakh)
                             2004-05    2005-06     2006-07    2007-08    2008-09
                            (Pro rata)
Depreciation                  60.13      146.21      147.93     147.93     147.93
Interest on Loan             106.62      255.39      254.15     233.21     211.20
Return on Equity              54.18      132.25      134.26     134.26     134.26
Advance against Depreciation   0.00        0.00        0.00       0.00     101.15
Interest on Working Capital    6.50       15.83       16.23      16.23      18.01
O & M Expenses                35.15       87.75       91.26      94.89      98.70
Total                        262.57      637.43      643.83     626.53     711.25

 

6. The details submitted by the petitioner in support of its claim for interest on working capital are given hereunder:

 

Transmission asset-I 
                                                           (Rs. in lakh)
     .                      2005-06     2006-07     2007-08    2008-09
                          (Pro rata)
Maintenance Spares          13.83        14.59       15.46      16.39
O & M expenses               2.44         2.54        2.64       2.74
Receivables                 36.99        39.60       40.54      39.76
Total                       53.25        56.72       58.64      58.89
Rate of interest           10.25%       10.25%      10.25%     10.25%
Interest                     5.00         5.81        6.01       6.04

 

Transmission asset-II 
                                                                   (Rs.in lakh)
                          2004-05       2005-06     2006-07    2007-08   2008-09
                         (Pro rata)
Maintenance Spares         40.03         41.03       43.49       46.10    48.87
O & M expenses              7.03          7.31        7.61        7.91     8.23
Receivables               105.03        106.24      107.30      104.42   118.54
Total                     152.09        154.59      158.40      158.43   175.64
Rate of interest          10.25%        10.25%      10.25%      10.25%   10.25%
Interest                    6.50         15.83       16.23       16.23    18.01

 

7. The reply to the petition has been filed by Tamil Nadu Electricity Board. No comments or suggestion have been received from the general public in response to the notices published by the petitioner under Section 54 of the Electricity Act, 2003.

CAPITAL COST

8. As per Clause (1) of Regulation 52 of the 2004 regulations, subject to prudence check, the actual expenditure incurred on completion of the project shall form the basis for determination of final tariff. The final tariff shall be determined based on the admitted capital expenditure actually incurred up to the date of commercial operation of the transmission system and shall include capitalised initial spares subject to a ceiling norm as 1.5% of original project cost. The regulation is applicable in case of the transmission system declared under commercial operation on or after 1.4.2004.

9. The petitioner has claimed the capital expenditure up to the date of commercial operation in case of the transmission asset-I. The petitioner has further claimed additional capitalisation for the year 2005-06 for the transmission asset-I and for the years 2004-05 and 2005-06 for the transmission asset-II. The petitioner has not claimed additional capitalization on account of FERV as these assets do not involve foreign currency loans. The capital expenditure on the date of commercial operation and additional capitalization on account of works claimed by the petitioner for tariff purposes are given hereunder:

(Rs. in lakh)
Name of the trans- Capital Expend- Additional Additional Total Capital
mission assets iture on the capital capital expenditure
date of comme- expenditure expenditure
rcial operation during during
2004-05 2005-06
Transmission asset-I 1382.59 N.A. 78.81 1461.40
Transmission asset-II 4003.22 10.19 95.73 4109.14
Total 5385.81 10.19 174.54 5570.54

Additional capitalization

10. Clause (1) of Regulation 53 of the 2004 regulations provides-

(1) The following capital expenditure within the original scope of work actually incurred after the date of commercial operation and up to the cut off date may be admitted by the Commission, subject to prudence check:

(i) Deferred liabilities;

(ii) Works deferred for execution;

(iii) Procurement of initial capital spares in the original scope of works subject to the ceiling norm specified in Regulation 52;

(iv) Liabilities to meet award of arbitration or compliance of the order or decree of a court; and

(v) On account of change in law:

Provided that original scope of work along with estimates of expenditure shall be submitted along with the application for provisional tariff:

Provided further that a list of the deferred liabilities and works deferred for execution shall be submitted along with the application for final tariff after the date of commercial operation of the transmission system.

11. The details submitted by the petitioner in support of its claim for additional capital expenditure are given hereunder:

 

Transmission asset-I 
   Year                      Nature of expenditure
2005-06                     Sub-station = Rs. 78.81 lakh
                            Total       = Rs. 78.81 lakh

 

Transmission asset-II 
 Year                        Nature of expenditure
2004-05                      Sub-station = Rs. 10.19 lakh
2005-06                      Sub-station = Rs. 95.73 lakh
                             Total       = Rs. 105.92 lakh

 

12. The additional capital expenditure claimed is within the original scope of work and is found to be in order as it was against the committed liability. Accordingly, the additional capital expenditure as claimed for the respective transmission asset has been allowed.

13. The Commission in its order dated 16.11.2006 in Petition No. 20/2006 had deliberated on value of initial spares to be considered. At that time the audited original project cost of the transmission asset-II was not known, but the actual expenditure on the date of commercial operation only was known. Therefore, the cost of initial spares was restricted up to 1.5% of the capital cost as on 1.11.2004. Petition No. 20/2006 covered only the transmission asset-II. Since now the petitioner has submitted the audited capital cost as on 31.3.2006 for both the assets, the cost of initial spares has been recalculated and restricted based on capital cost of the transmission scheme. This has been discussed in the succeeding paragraphs.

14. Since the dates of commercial operation of the transmission asset-I and the transmission asset-II are 1.5.2005 and 1.11.2004 respectively, the original project cost will be sum of the actual expenditure incurred up to 31.3.2007 in case of the transmission asset-I and the actual expenditure incurred up to 31.3.2006 in case of the transmission asset II. However, in case of the transmission asset- I the actual expenditure incurred is available only up to 31.3.2006, so the same has been considered for computing the original project as follows:

For the transmission asset – I, the actual expenditure incurred up to 31.3.2006 is Rs. 1461.40 lakh including initial spares of Rs. 10.47 lakh and Rs. 1450.93 lakh, excluding initial spares.

For the transmission asset – II, the actual expenditure incurred upto 31.3.2006 is Rs. 4109.14 lakh, including initial spares of Rs. 133.75 lakh and Rs. 3975.39 lakh excluding initial spares.

Thus, the original project cost excluding initial spares works out to Rs. 5426.32 lakh (Rs. 1450.93 lakh + Rs. 3975.39 lakh).

Original project cost = Original project cost excluding initial spares + 1.5% of original project cost on account of initial spares.

Original project cost = Rs. 5426.32 lakh+ 1.5% of original project cost on account of initial spares.

i.e. original project cost -1.5% original project cost = Rs. 5426.32 lakh.

i.e. 98.5% of original project cost = Rs. 5426.32 lakh.

Therefore, the original project cost is Rs. 5426.32 lakh/0.985 =Rs. 5508.95 lakh.

Therefore, the value of initial spares is restricted up to 1.5% of Rs. 5508.95 lakh

i.e. Rs. 82.63 lakh.

In case of transmission asset -I the initial spares of value Rs. 10.47 lakh have been allowed as claimed by the petitioner. The initial spares for Rs. 72.16 lakh (Rs. 82.63 lakh Rs. 10.47 lakh) are allowable in case of transmission asset II.

15. Accordingly, for the purpose of computation of tariff, the capital cost works out as follows:

The capital cost for the transmission asset – II as on 31.3.2006 = capital cost as on 31.3.2006 excluding initial spares + allowable initial spares i.e. Rs. 3975.39 lakh + Rs. 72.16 lakh = Rs. 4047.55 lakh The actual expenditure on the date of commercial operation works out to Rs. 3941.63 lakh (Rs. 4047.55 lakh Rs. 10.19 lakh Rs. 95.73 lakh).

16. Based on the above, capital cost as given below has been considered for the purpose of tariff for each of the transmission assets, after allowing additional capitalization on works as claimed by the petitioner:

(Rs. in lakh)
Name of the trans- Capital cost on the Additional capital Capital expenditure
mission assets date of commercial expenditure as on 31.3.2006
operation
Transmission asset-I 1382.59 78.81 1461.40
Transmission asset-II 3941.63 105.92 4047.55
Total 5324.22 184.73 5508.95

DEBT- EQUITY RATIO

17. Clause (2) of Regulation 54 of the 2004 regulations inter alia provides that,-

(2) In case of the transmission system for which investment approval was accorded prior to 1.4.2004 and which are likely to be declared under commercial operation during the period 1.4.2004 to 31.3.2009, debt and equity in the ratio of 70:30 shall be considered:

Provided that where equity actually employed to finance the project is less then 30%, the actual debt and equity shall be considered for determination of tariff:

Provided further that the Commission may in appropriate cases consider equity higher than 30% for determination of tariff, where the transmission licensee is able to establish to the satisfaction of the Commission that deployment of equity higher than 30% was in the interest of general public.

18. The note 1 below Regulation 53 lays down that any expenditure on account of committed liabilities within the original scope of work is to be serviced in the normative det-equity ratio specified in Regulation 54.

19. The petitioner has considered debt-equity ratio as actually deployed on the date of commercial operation of the respective asset. The petitioner has further considered the additional capitalization in the debt-equity ratio of 70:30.

20. We have considered debt-equity ratio as on the date of commercial operation as claimed by the petitioner. The additional capitalisation on works has been segregated into debt and equity in the normative debt-equity ratio of 70:30 in accordance with Note 1 below Regulation 53. Therefore, debt-equity ratio and equity considered for the purpose of tariff in each case is same as considered by the petitioner and is as under:

 Name of the trans-                 Debt-equity ratio             Equity (Rs. in lakh)
mission assets
                     As on date of com-    As on 31.3.2006  As on date of    As on 31.3.2006
                     mercial operation                      commercial
                                                            operation
Transmission asset-I            70.:30               70:30         414.79            438.43
Transmission asset-II      76.84:23.16         76.66:23.34         912.95            944.73

 

RETURN ON EQUITY 
 

21. As per Clause (iii) of Regulation 56 of the 2004 regulations, return on equity shall be computed on the equity base determined in accordance with Regulation 54 @ 14% per annum. Equity invested in foreign currency is to be allowed a return in the same currency and the payment on this account is made in Indian Rupees based on the exchange rate prevailing on the due date of billing.

22. For the reasons recorded in para 20 above, equity as given in the table under that para has been considered. However, tariff for the year 2004-05 and 2005-06 has been allowed pro rata on average equity. Accordingly, return on equity allowed each year during the tariff period is given hereunder:

(Rs. in lakh)
Name of the transmission assets Return in Equity
2004-05 2005-06 2006-09
(Pro rata) (Pro rata) (Each year)
Transmission asset-I N.A. 54.75 61.38
Transmission asset-II 53.34 130.25 132.26

INTEREST ON LOAN

23. Clause (i) of Regulation 56 of the 2004 regulations inter alia provides that,-

(a) Interest on loan capital shall be computed loan wise on the loans arrived at in the manner indicated in Regulation 54.

(b) The loan outstanding as on 1.4.2004 shall be worked out as the gross loan in accordance with Regulation 54 minus cumulative repayment as admitted by the Commission or any other authority having power to do so, up to 31.3.2004. The repayment for the period 2004-09 shall be worked out on a normative basis.

(c) The transmission licensee shall make every effort to re-finance the loan as long as it results in net benefit to the beneficiaries. The costs associated with such re-financing shall be borne by the beneficiaries.

(d) The changes to the loan terms and conditions shall be reflected from the date of such re-financing and benefit passed on to the beneficiaries.

(e) In case of dispute, any of the parties may approach the Commission with proper application. However, the beneficiaries shall not withhold any payment ordered by the Commission to the transmission licensee during pendency of any dispute relating to re-financing of loan;

(f) In case any moratorium period is availed of by the transmission licensee, depreciation provided for in the tariff during the years of moratorium shall be treated as repayment during those years and interest on loan capital shall be calculated accordingly.

(g) The transmission licensee shall not make any profit on account of re-financing of loan and interest on loan;

(h) The transmission licensee may, at its discretion, swap loans having floating rate of interest with loans having fixed rate of interest, or vice versa, at its own cost and gains or losses as a result of such swapping shall accrue to the transmission licensee:

Provided that the beneficiaries shall be liable to pay interest for the loans initially contracted, whether on floating or fixed rate of interest.

24. The petitioner has claimed interest on loan in the following manner:

(i) Gross loan opening has been considered for 2004-05 or 2005-06 as the case may be;

(ii) Gross loans on account of additional capital expenditure is added to the gross loan up to the date of commercial operation;

(iii) On the basis of actual rate of interest on actual average loan, the weighted average rate of interest on loan is worked out for various years.

(iv) Gross loan calculated has been considered as notional loan and the weighted average rate of interest on loan for respective years has been multiplied to arrive at interest on loan. For any year, higher of the depreciation and actual repayment has been considered as repayment.

(v) Normative repayment has been worked out by the following formula:

Actual repayment of actual loan during the year

———————————————–X Opening balance of normative
Opening balance of actual loan during the year
loan during the year

(vi) On the basis of actual rate of interest on actual average loan, the weighted average rate of interest on loan is worked out for various years.

(vii) Weighted average rate of interest on loan for respective years as per above has been has been multiplied to arrive at interest on loan.

25. In our calculation, the interest on loan has been worked out as detailed below:

(i) Gross amount of loan, repayment of instalments and rate of interest as per the loan reconciliation statements of 2004-05 and 2005-06 have been used to work out weighted average rate of interest on actual loan. It includes part corresponding to additional capital expenditure.

(ii) Notional loan arising out of additional capitalization has been added in loan amount as on date of commercial operation to arrive at total notional loan. The adjusted gross loan has been considered as normative loan for tariff calculations.

(iii) Tariff has been worked out considering normative loan and normative repayments. Once the normative loan is arrived at, it is considered for all purposes in the tariff. Normative repayment has been worked out by the following formula:

Actual repayment of actual loan during the year

———————————————- X Opening balance of normative
Opening balance of actual loan during the year
loan during the year

(iv) Moratorium in repayment of loan has been considered with reference to normative loan and if the normative repayment of loan during the year is less than the depreciation during the year, it is considered as moratorium and depreciation during the year is deemed as normative repayment of loan during the year. (v) Weighted average rate of interest on actual loan worked out as per (i) above has been applied on the notional average loan during the year to arrive at the interest on loan.

(vi) In case of the transmission asset-I bridge financing of loan from IOB having a floating rate of interest 5.90% was replaced with Bond XVII having a fixed rate of interest of 7.39%. Therefore, weighted average rate of interest has been arrived at before calculating the interest pertaining to this loan, subject to mutual settlement between the parties in case of any change/resetting of the interest rate during the tariff period.

(vii) As regards the transmission asset II, The petitioner has considered funding of additional capital expenditure during 2005-06 from Bond XVIII which was drawn from 9.3.2006.The interest on Bond XVIII for working out weighted average rate of interest has been considered from 9.3.2006 on actual days basis for the remaining part of the year 2005-06 by the petitioner. However, as per methodology for the tariff block 2004-09, weighted average rate of interest has been worked out on average loan basis. Further, though the petitioner has considered Bond XVIII in opening gross loan, but as the same has been drawn during the year, it has not been considered in opening gross loan but added subsequently resulting in difference average value of loan.

26. Based on the above, the year-wise details of interest worked out are given hereunder:

 

Transmission asset-I 
                                                                      (Rs. in lakh)
Interest on Loan                      2005-06       2006-07       2007-08       2008-09
                                    (Pro rata)
Opening gross Loan                    967.80        1022.97       1022.97       1022.97
Cumulative Repayment up to
Previous Year                           0.00          46.93        108.55        180.03
Net Loan-Opening                      967.80         976.04        914.42        842.94
Addition due to Additional
Capitalization                         55.17            -             -             -
Repayment during the year              46.93          61.62         71.48         71.48
Net Loan-Closing                      976.04         914.42        842.94        771.46
Average Loan                          971.92         945.23        878.68        807.20
Weighted Average Rate of
Interest on Loan                       8.29%          8.29%         8.28%         8.27%
Interest                               73.87          78.38         72.73         66.76

 

Transmission asset-II 
                                                                           (Rs. in lakh)
Interest on Loan                  2004-05     2005-06     2006-07    2007-08   2008-09
                                 (Pro rata)
Opening gross Loan                3028.68     3035.81     3102.82    3102.82   3102.82
Cumulative Repayment up
to Previous Year                     0.00       59.20      203.19     412.16    650.23
Net Loan-Opening                  3028.68     2976.61     2899.63    2690.66   2452.59
Addition due to Additional
Capitalization                       7.13       67.01         -         -          -
Repayment during the year           59.20      143.99      208.97     238.07    238.07
Net Loan-Closing                  2976.61     2899.63     2690.66    2452.59   2214.52
Average Loan                      3002.64     2938.12     2795.14    2571.62   2333.55
Weighted Average Rate of
Interest on Loan                    8.39%       8.39%       8.38%      8.37%     8.37%
Interest                           104.99      246.50      234.21     215.20    195.22

 

27. The detailed calculations in support of interest on loan are attached an Annexure I to this order.

DEPRECIATION

28. Sub-clause (a) of Clause (ii) of Regulation 56 of the 2004 regulations provides for computation of depreciation in the following manner, namely:

(i) The value base for the purpose of depreciation shall be the historical cost of the asset.

(ii) Depreciation shall be calculated annually based on straight line method over the useful life of the asset and at the rates prescribed in Appendix II to these regulations. The residual value of the asset shall be considered as 10% and depreciation shall be allowed up to maximum of 90% of the historical capital cost of the asset. Land is not a depreciable asset and its cost shall be excluded from the capital cost while computing 90% of the historical cost of the asset. The historical capital cost of the asset shall include additional capitalisation on account of Foreign Exchange Rate Variation up to 31.3.2004 already allowed by the Central Government/Commission.

(iii) On repayment of entire loan, the remaining depreciable value shall be spread over the balance useful life of the asset.

(iv) Depreciation shall be chargeable from the first year of operation. In case of operation of the asset for part of the year, depreciation shall be charged on pro rata basis.

29. The calculations in support of depreciation allowed on the basis of capital cost as per para 16 above, are appended below:

 

Transmission asset-I 
                                                                    (Rs. in lakh)
                                   2005-06       2006-07     2007-08     2008-09
                                 (Pro rata)
Gross Block                       1382.59        1461.40     1461.40     1461.40
Addition due to Additional          78.81
Capitalization
Gross Block                       1461.40        1461.40     1461.40     1461.40
Rate of Depreciation              3.6000%        3.6000%     3.6000%     3.6000%
Depreciable Value                 1279.80        1315.26     1315.26     1315.26
Balance Useful life of the asset      -             -           -           -
Remaining Depreciable Value       1279.80        1268.33     1206.71     1135.23
Depreciation                        46.93          52.61       52.61       52.61

 

Transmission asset-II 
                                                                     (Rs. in lakh)
                                   2004-05       2005-06     2006-07     2007-08   2008-09
                                 (Pro rata)
Gross Block                       3941.63        3951.82     4047.55     4047.55   4047.55
Addition due to Additional
Capitalisation                      10.19          95.73
Gross Block                       3951.82        4047.55     4047.55     4047.55   4047.55
Rate of Depreciation              3.6000%        3.6000%     3.6000%     3.6000%   3.6000%
Depreciable Value                 3552.05        3599.72     3642.80     3642.80   3642.80
Balance Useful life of the asset     -              -           -           -          -
Remaining Depreciable Value       3552.05        3540.52     3439.61     3230.63   2992.56
Depreciation                        59.20         143.99      145.71      145.71    145.71

 

ADVANCE AGAINST DEPRECIATION 
 

30. As per Sub-clause (b) of Clause (ii) of Regulation 56 of the 2004 regulations, in  addition to allowable depreciation, the transmission licensee is entitled to Advance  Against Depreciation, computed in the manner given hereunder:    AAD = Loan repayment amount as per Regulation 56(i) subject to a ceiling of  1/10th of loan amount as per Regulation 54 minus depreciation as per schedule   
 

31. It is provided that Advance Against Depreciation shall be permitted only if the cumulative repayment up to a particular year exceeds the cumulative depreciation up to that year. It is further provided that Advance Against Depreciation in a year shall be restricted to the extent of difference between cumulative repayment and cumulative depreciation up to that year.

32. In addition to Cumulative depreciation up to 2003-04 (excluding Advance Against Depreciation) as per last tariff setting, depreciation on FERV for the period 2001-04 has been added to arrive at total cumulative depreciation amount as on 31.03.2004.

33. The petitioner has claimed Advance Against Depreciation in the following manner:

(i) 1/10th of gross loan is worked out from the gross notional loan.

(ii) Cumulative loan as well as repayment of notional loan during the year have been considered.

(iii) Depreciation as claimed in the petition.

34. In our calculation, the Advance Against Depreciation has been worked out as under:

(i) 1/10th of gross loan is worked out from the gross notional loan as per para 26 above.

(ii) Repayment of cumulative loan as well as repayment of notional loan during the year have been considered as per para 26 above.

(iii) Depreciation worked out in para 29 above has been considered.

35. The details of Advance Against Depreciation allowed for transmission scheme are given hereunder:

 

Transmission asset-I 
                                                                      (Rs. in lakh)
                                  2005-06        2006-07     2007-08      2008-09
1/10th of Gross Loan(s)             96.78         102.30      102.30       102.30
Repayment of the Loan               46.93          61.62       71.48        71.48
Minimum of the above                46.93          61.62       71.48        71.48
Depreciation during the year        46.93          52.61       52.61        52.61
(A) Difference                       0.00           9.01       18.87        18.87
Cumulative Repayment of the Loan    46.93         108.55      180.03       251.51
Cumulative Depreciation/Advance
against Depreciation                46.93          99.54      161.16       232.64
(B) Difference                       0.00           9.01       18.87        18.87
Advance against Depreciation
Minimum of (A) and (B)               0.00           9.01       18.87        18.87

 

Transmission asset-II 
                                                                      (Rs. in lakh)
                                  2004-05       2005-06      2006-07   2007-08    2008-09
1/10th of Gross Loan(s)            302.87        303.58       310.28    310.28     310.28
Repayment of the Loan               59.20        143.99       208.97    238.07     238.07
Minimum of the above                59.20        143.99       208.97    238.07     238.07
Depreciation during the year        59.20        143.99       145.71    145.71     145.71
(A) Difference                       0.00          0.00        63.26     92.36      92.36
Cumulative Repayment of the Loan    59.20        203.19       412.16    650.23     888.30
Cumulative Depreciation/Advance
against Depreciation                59.20        203.19       348.90    557.87     795.94
(B) Difference                       0.00          0.00        63.26     92.36      92.36
Advance against Depreciation
Minimum of (A) and (B)               0.00          0.00        63.26     92.36      92.36

 

OPERATION & MAINTENANCE EXPENSES 
 

36. In accordance with Clause (iv) of Regulation 56 the 2004 regulations, the following norms are prescribed for O & M expenses
Year
2004-05 2005-06 2006-07 2007-08 2008-09
O&M expenses (Rs in lakh per ckt-km) 0.227 0.236 0.246 0.255 0.266
O&M expenses (Rs in lakh per bay) 28.12 29.25 30.42 31.63 32.90

37. The petitioner has claimed following O & M expenses each asset, which haves been allowed. Accordingly, the petitioners entitlement to O & M expenses in respect of transmission asset-I has been worked out as given hereunder:

(Rs. in lakh)
2005-06 2006-07 2007-08 2008-09
(Pro rata)
Allowable O & M for 1 nos bays 26.81 30.42 31.63 32.90
Total 26.81 30.42 31.63 32.90

38. There is no change in O & M expenses approved under order dated 16.11.2006 in respect of the transmission asset-II.

39. The petitioner has submitted that the wage revision of its employees is due with effect from 1.1.2007. Therefore, according to the petitioner, O & M expenses should be subject to revision on account of revision of employee cost from that date. In the alternative, it has been prayed that the increase in employee cost due to wage revision be allowed as per actuals for extra cost to be incurred consequent to wage revision. We are not expressing any view, as this issue does not arise for consideration at this stage. The petitioner may approach for a relief in this regard at an appropriate stage in accordance with law.

INTEREST ON WORKING CAPITAL

40. The components of the working capital and the interest thereon are discussed hereunder:

(i) Maintenance spares

Regulation 56(v)(1)(b) of the 2004 regulations provides for maintenance spares @ 1% of the historical cost escalated @ 6% per annum from the date of commercial operation. In the present case, element wise capital expenditure on the date of commercial operation which has been considered as the historical cost for the purpose of the present petition and maintenance spares have been worked out accordingly by escalating 1% of the historical cost @ 6% per annum. The necessary details are given hereunder:

 Name of the Transmission  Date of Commercial  Capital Expenditure    Spares Cost
assets                    Operation           (Rs. in lakh) on the  (Rs. in lakh)
                                              date of commercial
                                              operation
Transmission asset-I      1.5.2005            1382.59                  13.83
Transmission asset-II     1.11.2004           3930.01                  39.42

 

 (ii) O & M expenses 
 

Regulation 56(v)(1)(a) of the 2004 regulations provides for operation and maintenance expenses for one month as a component of working capital. The petitioner has claimed O&M expenses for 1 month of O&M expenses of the respective year as claimed in the petition. This has been considered in the working capital.

(iii) Receivables

As per Regulation 56(v)(1) of the 2004 regulations, receivables will be equivalent to two months average billing calculated on target availability level.

The petitioner has claimed the receivables on the basis 2 months transmission charges claimed in the petition. In the tariff being allowed, receivables have been worked out on the basis 2 months transmission charges.

(iv) Rate of interest on working capital As per Regulation 56(v)(2) of the 2004 regulations, rate of interest on working capital shall be on normative basis and shall be equal to the short-term Prime Lending Rate of State Bank of India as on 1.4.2004 or on 1st April of the year in which the project or part thereof (as the case may be) is declared under commercial operation, whichever is later. The interest on working capital is payable on normative basis notwithstanding that the transmission licensee has not taken working capital loan from any outside agency. The petitioner has claimed interest on working capital @ 10.25% based on SBI PLR as on 1.4.2004 and 1.4.2005, which is in accordance with the 2004 regulations and has been allowed.

41. The necessary computations in support of interest on working capital are appended below:

 

Transmission asset-II 
                                                                   (Rs. in lakh)
                             2005-06      2006-07       2007-08         2008-09
                            (Pro rata)
Maintenance Spares            13.83        14.59          15.46           16.39
O & M expenses                 2.44         2.54           2.64            2.74
Receivables                   37.71        39.60          40.54           39.76
  Total                       53.98        56.72          58.64           58.89
Interest                       5.07         5.81           6.01           6.04

 

Transmission asset-II 
                                                                         (Rs. in lakh)
                             2004-05      2005-06       2006-07      2007-08   2008-09
                            (Pro rata)
Maintenance Spares            39.42         40.40         42.83       45.40     48.12
O & M expenses                 7.03          7.31          7.61        7.91      8.23
Receivables                  103.64        104.01        113.92      116.30    113.61
Total                        150.08        151.72        164.36      169.60    169.96
Interest                       6.41         15.55         16.85       17.38     17.42

 

TRANSMISSION CHARGES 
 

42. A summary sheet showing basic details of capital cost and other related aspects are attached as Annexure II to this order. The transmission charges being allowed for the the transmission assets covered under transmission scheme are summarized below.

 

Transmission asset-I 
                                                                (Rs. in lakh)
                             2005-06      2006-07       2007-08     2008-09
                            (Pro rata)
Depreciation                  46.93         52.61         52.61       52.61
Interest on Loan              73.87         78.38         72.73       66.76
Return on Equity              54.75         61.38         61.38       61.38
Advance against Depreciation   0.00          9.01         18.87       18.87
Interest on Working Capital    5.07          5.81          6.01        6.04
O & M Expenses                26.81         30.42         31.63       32.90
  Total                      207.43        237.61        243.23      238.55
 

Transmission asset-II 
                                                                (Rs. in lakh)
                            2004-05     2005-06     2006-07     2007-08     2008-09
                           (Pro rata)
Depreciation                  59.20      143.99      145.71      145.71      145.71
Interest on Loan             104.99      246.50      234.21      215.20      195.22
Return on Equity              53.34      130.25      132.26      132.26      132.26
Advance against Depreciation   0.00        0.00       63.26       92.36       92.36
Interest on Working Capital    6.41       15.55       16.85       17.38       17.42
O & M Expenses                35.15       87.75       91.26       94.89       98.70
Total                        259.09      624.05      683.55      697.81      681.67

 

43. In addition to the transmission charges, the petitioner shall be entitled to other charges like income-tax, incentive, surcharge and other cess and taxes in accordance with the 2004 regulations. These transmission charges shall be included in the regional transmission tariff for Southern Region and shall be shared by the regional beneficiaries in accordance with the 2004 regulations.

44. The petitioner has sought approval for the reimbursement of expenditure of Rs. 90, 553-/incurred on publication of notices in the newspapers. The petitioner shall claim reimbursement of the said expenditure directly from the respondent in one installment. The petitioner has also sought reimbursement of filing fee of Rs. 5 lakh paid. A final view on reimbursement of filing fee is yet to be taken by the Commission for which views of the stakeholder have been called for. The view taken on consideration of the comments received shall apply in the present case as regards reimbursement of filing fee.

45. The petitioner is already billing the respondents on provisional basis in accordance with the order dated 13.2.2006 in Petition No. 96/2005 in respect of the transmission asset-I. The provisional billing of tariff shall be adjusted in the light of final tariff now approved by us. In case of the transmission asset-II, the revised transmission charges as now approved shall be claimed in supersession of the transmission charges approved under order dated 16.11.2006.

46. This order disposes of Petition No. 129/2006.