High Court Punjab-Haryana High Court

Punjab State Electricity Board vs M/S Bombay Conductors And … on 6 November, 2008

Punjab-Haryana High Court
Punjab State Electricity Board vs M/S Bombay Conductors And … on 6 November, 2008
 IN THE HIGH COURT OF PUNJAB AND HARYANA
               AT CHANDIGARH

                                             F.A.O. No. 1097 of 1985
                                           Date of Decision : November 06, 2008


Punjab State Electricity Board, Patiala
                                                                .....Appellant
                                  Versus

M/s Bombay Conductors and Electricals Ltd.
                                                              .....Respondent


CORAM : HON'BLE MR JUSTICE T.P.S. MANN


Present :   Mr. J.P.S. Sandhu, Advocate
            for the appellant

            Mr. I.K. Mehta, Senior Advocate with
            Mr. M.S.Kohli, Advocate
            for the respondent.


T.P.S. MANN, J.

Against the award dated 29.8.1983 delivered by Shri S.N.

Khosla, sole Arbitrator, the appellant filed its objections, which were

dismissed by learned Additional Senior Sub Judge, Patiala on 11.6.1985

and the aforementioned award made rule of the Court. The appellant is

now before this Court in an appeal under Section 39 of the Indian

Arbitration Act, 1940.

Vide purchase order-cum-contract agreement dated

11.9.1978, the appellant-Board placed an order for manufacture and
F.A.O. No. 1097 of 1985 -2-

purchase of 1300 K.Ms. of A.C.S.R. Zebra Conductors etc. at the rate of

Rs.23,820/- per K.M. F.O.R. destination with the respondents, M/s

Bombay Conductors and Electricals Limited, Ahmadabad. Clause 2 of

the agreement provided that the price of the material to be supplied by the

respondent was subject to variation depending upon the base price, there

being no ceiling to the price variation. The supply was to commence

within two months from the date of receipt of purchase order by the

respondent and to be completed at the rate of 300 K.Ms per quarter.

When the respondent could not supply the contracted material in time, the

date for supply of the same was extended for a period of six months by

the appellant-Board. All other terms and conditions remained unchanged.

The respondent, however, could not supply the material by the extended

date and again applied for extension of time for completion of its part of

the agreement. On 27.4.1981, the appellant-Board again extended the time

for supply of the material upto 30.6.1981 without levy of any penalty. It

was, however, mentioned in the letter issued on 27.4.1981 that the rate of

conductors to be supplied shall be as prevelent during March, 1981 before

the price rise. The respondent fulfilled its part under the agreement within

stiuplated period. The appellant-Board claimed that vide its letter dated

27.4.1981 the respondent was entitled to the price of the material supplied

as was prevalent during March, 1981 and not entitled to any further price

increase. However, the respondent felt that the price of raw material was

enhanced by the Government of India on 27.3.1981 and in view of Clause
F.A.O. No. 1097 of 1985 -3-

2 of the agreement, it was entitled to the enhanced rate from the appellant-

Board. In view of the arbitration clause in the agreement dated 11.9.1978,

the matter was referred to the sole Arbitrator to be appointed by the Board

and consequently Shri S.K. Khosla was appointed as such, who entered

upon the arbitration reference on 30.10.1982. On the basis of the material

placed before him by the parties, the Arbitrator held that the respondent

was entitled to recover a sum of Rs. 9,42,214.08 p. from the appellant-

Board in lieu of the price increase in the raw material. This amount was

calculated on the basis of the stipulation contained in Clause 2 of the

agreement regarding the price variation. The appellant-Board was ordered

to pay the aforementieond amount to the respondent within a period of

two months from the date of the award, failing which future interest at the

rate of 12% per annum was also liable to be paid.

The stand of the appellant-Board while filing its objection

was that the award was against the law and facts and had been announced

after the expiry of the period of limitation. The Arbitrator had ignored

various clauses of the agreement. It was pleaded that the extension of

delivery schedule was made by the appellant-Board on the specific

condition that variation in price rise would not be allowed and the

respondent would have no right to claim any increase due to price rise of

the material.

The respondent opposed the objection petition by filing its
F.A.O. No. 1097 of 1985 -4-

reply stating therein that the impugned award was perfectly just and valid.

It was also pleaded that the delay in submission of the award was due to

unreasonable attitude adopted by the Board and its officials.

Learned Additional Senior Sub Judge, Patiala vide order

dated 24.7.1984 framed the following issues :-

1. Whether the award is liable to be set aside on
the ground as alleged in the objection
petition? O.P. Objector.

2. Whether the respondent is entitled to interest
as adjudicated in the award and also future
interest till the recovery of the amount ?
O.P.R.

3. Relief.

On the basis of the evidence and the material placed on the

record, learned Additional Senior Sub Judge, Patiala held that the award

was perfectly just and valid and the objections raised by the appellant-

Board were totally misconceived. Accordingly, the objections were

dismissed and the award made rule of the Court.

Learned counsel for the appellant has submitted that when the

request of the respondent for extension of time was granted by the

appellant-Board on 27.4.1981, it was specifically stated in its letter of the

even date that there would be no additional financial liability and the rates
F.A.O. No. 1097 of 1985 -5-

as prevalent during March, 1981 before the price rise announced by the

Government of India shall be applicable for the supply of the raw

material. Therefore, the respondent was not entitled to charge the price of

the material as per its own whims or fancies.

Initially in the agreement dated 11.9.1978 it was stipulated

between the parties, that the price of the material to be supplied by the

respondent was subject to variation depending upon the base price of the

raw material and there was to be no ceiling to the price variation. When

the respondent failed to supply the contracted material even by the

extended date and again applied for extension of time for completion of

its part of the agreement, its requests was accepted by the appellant-Board

on 27.4.1981 by extending the time for supply of the contracted material

upto 30.6.1981. At that time, it specified that such an extension was

without levy of any penalty and also without any additional financial

liability and the rates applicable for the supply of conductors was to be as

prevalent during March, 1981 but before the price rise as announced by

the Government of India. All other terms and conditions of the original

purchase order-cum-agreement were to remain the same. This implied

that any increase in the price of the raw material, was to be borne by

the appellant-Board in view of the specific mention made in Clause 2

of the agreement, which specified that there was to be no ceiling

to the price variation in case of any increase in the price of the raw

material within the extended time as granted by letter dated 27.4.1981.
F.A.O. No. 1097 of 1985 -6-

Even before the extension of time, as granted by appellant-Board on

27.4.1981, there was sharp increase in the price of the raw material in

view of Central Government notification dated 27.3.1981. Once the

appellant-Board had undertaken to bear any price esclation of the raw

material, it could not later on, on its own discretion, avoid paying higher

price to the respondent and, that too, in view of the Central Government

notification. The clause incorporated by the appellant-Board in its letter

dated 27.4.1981 regarding the price to be paid as prevalent during March,

1981, was an arbitrary and one sided step taken by it to the determinent of

the respondent. There was no clause in the original agreement that the

appellant-Board could change the terms and conditions of the same

without taking the respondent into confidence. Initially, it was agreed

between the parties that the price of the material was subject to variation

depending upon the base price of the raw material and there was to be no

ceiling to the price variation. None of the parties could unilaterally change

the said term and condition. On the other hand, the request made by the

respondent-Board for extension of time was duly entertained and accepted

by the appellant-Board. To that an extent, the original agreement could

be valid but no terms and conditions as relating to the price of the material

to be supplied. The stipulation regarding avoidance of financial

implication so made by the appellant-Board in its letter dated 27.4.1981

was, thus, rightly found to be not justified.

Another argument on behalf of the appellant is that the award
F.A.O. No. 1097 of 1985 -7-

was delivered by the Arbitrator after the expiry of the period of limitation,

therefore, the same could not have been made the rule of the Court.

As is apparent from the records, the Arbitrator entered upon

arbitration reference on 30.10.1982 when the first arbitration meeting took

place. The period for giving award was extended from time to time. Last

of all, on 6.2.1983, it was extended upto June, 1983. However, on

16.6.1983, the appellant-Board sought an adjournment of the case to

July, 1983. The proceedings were adjourned to 3.7.1983 when, once

again, similar request was made for some other date. It is, thus, made out

that the Arbitrator had to post-pone the proceedings on the basis of the

various requests made by the appellant-Board from time to time. No

material is available on the file to show that the respondent delayed the

proceedings pending before the Arbitrator.

No other point arises for consideration. The appeal is without

any merit and, therefore, dismissed.





                                                          ( T.P.S. MANN )
November 06, 2008                                             JUDGE
satish




                 Whether to be referred to the Reporters : YES / NO