High Court Kerala High Court

R.George Pereira vs St.Joseph’S International … on 8 May, 2009

Kerala High Court
R.George Pereira vs St.Joseph’S International … on 8 May, 2009
       

  

  

 
 
  IN THE HIGH COURT OF KERALA AT ERNAKULAM

AR.No. 25 of 2007()


1. R.GEORGE PEREIRA,
                      ...  Petitioner

                        Vs



1. ST.JOSEPH'S INTERNATIONAL ACADEMY,
                       ...       Respondent

                For Petitioner  :SRI.K.L.VARGHESE

                For Respondent  :FR.JOHNY THOTTAM

The Hon'ble MR. Justice PIUS C.KURIAKOSE

 Dated :08/05/2009

 O R D E R
                   PIUS C. KURIAKOSE, J.
          -----------------------------------------------
                      A.R. No. 25 OF 2007
          -----------------------------------------------
           Dated this the 8th day of May, 2009

                           O R D E R

This is an application under section 11(6) of the

Arbitration and Conciliation Act, 1996 and the Scheme for

Appointment of an Arbitrator by the Chief Justice of the

Kerala High Court. The application seeks appointment of an

independent and impartial arbitrator for adjudicating upon

the various claims of the applicant against the respondent

The applicant was contractor of the respondent for the

construction of an school building at Kumbalam in Kollam

under the name and style “St. Joseph International

Academy”. It is alleged that disputes and differences arose

between the parties on account of what is described as the

recalcitrant attitude of the respondent to allow the applicant

to complete the work which had neared completion. It is

claimed that the applicant has carried out works worth

Rs.68,57,616/- in seven part bills whereas the respondent

A.R. N0. 25/07
-2-

has paid only Rs.45,68,712/-. The balance amount due

under the part bill is Rs.22,88,904/-. Since the balance

amount remained unpaid, the windows which had been

supplied by the applicant to the respondent had to be taken

back and deducting the value of those windows, the balance

amount due to the applicant is Rs.22,12,087/-. According

to the applicant, in order to avoid payment of the above

amount the respondent sought to terminate the contract.

The disputes and differences which was thus arisen are to

be settled by resorting to arbitration proceedings.

Annexure A8 is copy of the agreement between the

applicant and the respondent for construction of St. Joseph

International Academy and clause 17 thereof is quoted as

follows:

“(17) If there is any dispute relating to any matter
regarding the construction of the building or any matter
related to this contract, the Manager, St.Joseph’s
International Academy, Kollam will be the sole
Arbitrator for this purpose and his decision shall be
final, and the second party will have no right to

A.R. N0. 25/07
-3-

challenge this decision in the court of law”.

It is submitted that as per clause 17, the Manager of the

respondent is to be the sole arbitrator. But since disputes

have arisen on account of the actions and inactions of the

Manager, he is not entitled to function as arbitrator since

the same will be against the fundamental principle of

natural justice, nemo debet esse judex in propria causa (no

one shall be a judge in his own cause). It was under such

circumstances that the applicant sent Annexure A4 letter

indicating a panel of three names for selection of one among

them as arbitrator by the respondent. To Annexure A4, the

respondent’s Advocate sent Annexure A5 reply without

selecting any of the nominee arbitrators but suggesting for

appointment of two Civil Engineers, one to be appointed by

each party who could jointly verify the records and files and

assess the quantity and quality of the work done in order to

avoid a litigation and to come to a fair settlement. The

A.R. N0. 25/07
-4-

applicant obliged and appointed his nominee under

Annexure A6. The respondent also appointed its Engineer.

By Annexure A7, the applicant requested both the Engineers

to take up the assignment and pave way for a settlement.

Though the applicant called for nominee Engineer of the

respondent and furnished all measurement books and

connected records and made necessary follow up, nothing

materialized. In the meanwhile, the applicant’s nominee

Engineer met with an accident and passed away. Hence no

useful purpose will be served by waiting further and that is

the circumstances under which the applicant has filed this

application under section 11(6) of the Arbitration and

Conciliation Act, 1996 invoking the statutory appointment

procedure of arbitrators.

2. On the basis that no counter affidavit was filed the

A.R. was allowed by order dated 11-10-2007. Later R.P. No.

233 of 2008 was filed and the above order was recalled.

A.R. N0. 25/07
-5-

3. The contentions of the respondent as discernible

from the RP. 233/08 filed by him and also the reply affidavit

filed by him in the said RP are as follows: The arbitrator

who has been appointed by this court under the order dated

11-10-07 (Sri.E.K.Muraleedharan, Retired District and

Sessions Judge) is incapable of acting as arbitrator between

the parties in the light of the legal bar under the provisions

of the Arbitration and Conciliation Act, 1996. It is submitted

that contrary to what has been projected in the A.R. the

Manager envisaged under clause 17 of the arbitration clause

who is to act as the sole arbitrator in the event of disputes

and the signatory to the agreement are one and the same

person. In order to convince this court that the Manager of

St.Joseph ‘s International Academy and the executant to the

agreement are one and the same, the applicant has

produced Annexure A8, but Annexure A8 does not contain

the last page of the agreement. The last page of the

A.R. N0. 25/07
-6-

agreement will disclose that the Manager was not the

executant of the agreement. On the contrary the executant

of the agreement was the General Manager. Annexure B1

full text of the agreement is produced. It is pointed out that

it will be seen from Annexure B1 last page that there was a

typing mistake where the 1st party was indicated and

instead of General Manager the word Manager was

mistakenly used. Since the party noticed the mistake at

the time of execution of the agreement, the first party to

the agreement, the General Manager, St.Joseph’s

International Academy did not sign and instead he signed as

the General Manager only where the first party was

indicated. This was deliberately and intentionally done in

order to avoid confusion as the Manager, St.Joseph’s

International Academy was appointed as the arbitrator

under clause 17 of the agreement. It is submitted that

there is absolute consensus with regard to the arbitrator by

A.R. N0. 25/07
-7-

both parties to the agreement. It is then contended that

the General Manager and the Manager of St.Joseph’s

International Academy are two different persons. Annexure

B2 certificate issued by Mr.Joseph J. who was the Manager

of St.Joseph Academy during the period from 1st June 2002

to May 31, 2007 is produced. The present Manager of

St.Joseph Academy is one S.Sundaresan and Annexure B3

certificate issued by him is produced.

4. Annexure – B4 dated 22-11-2004 was caused to the

applicant by the respondent claiming Rs.39,43,330/- from

the applicant on various counts and requested that if the

claim was disputed the matter be referred to the Manager,

St, Joseph’s International Academy who alone is the

arbitrator. Again Annexure B5 dated 30-8-2005 was issued

on behalf of the respondent by way of reply to a lawyer

notice dated 16-10-2005 sent at the instance of the

applicant. Once again by Annexure B6 lawyer notice dated

A.R. N0. 25/07
-8-

1st December 2005 the respondent’s lawyer informed the

applicant’s lawyer in reply to applicant’s notice dated 19-11-

2005 that the Manager of the St. Joseph’s International

Academy is to be appointed as arbitrator and that it was not

the Manager of the St. Joseph’s International Academy who

had signed the agreement. In the reply affidavit filed by the

respondent to the counter filed by the applicant to

RP.233/08, it is submitted that the respondent has never

acted in a capacity as the Manager of St. Joseph’s

International Academy at any stage. The respondent has

been styled as General Manager or as Managing Director or

Director. This is on account of the fact that at the time of

construction of the school, the organization was at a very

nascent stage and therefore the respondent was styled as

General Manager and later as Managing Director/Director.

Similarly the then Manager Joseph John was styled as

Manager and subsequently he continued as Manager who

A.R. N0. 25/07
-9-

was also styled as Administrator. He continued to be the

Manager as well as Administrator. It is submitted that the

respondent in the RP (applicant) is trying to take advantage

of a typing mistake made in the agreement wherein the

word Manager was used in the last page instead of General

Manager. However, it is submitted that there is no scope

for such confusion as in the last page, it is the General

Manager who had signed at the portion where the first party

is indicated. In the agreement the first party is described as

General Manager. Hence there is no scope for confusion.

Referring to the correspondence produced by the

respondent it is submitted that the Manager Mr.Joseph John

had signed on behalf of the General Manager and not in his

capacity as the Manager of the school. It is pointed out that

Ext.A9 is not addressed to the General Manager or to the

institution. A10 is not addressed to the General Manager

but to Joseph John, the Manager. It is reported that Joseph

A.R. N0. 25/07
-10-

John has functioned only as Manager and that the

respondent has never styled or functioned as Manager. It

is further pointed out that the present Manager is not

Joseph John but is Mr. S. Sundareswaran and therefore

there is no question of any prejudice being caused to the

respondent.

6. I have heard the submissions of Sri. K.L. Varghese,

learned counsel for the applicant and those Sri. Madhu

Radhakrishnan, learned counsel for the respondent.

Mr.K.L.Varghese submitted that the non-production of the

last page of Annexure A8 is not fatal. The Arbitration

Scheme and the Kerala Arbitration Rules require production

of the arbitration agreement only along with the arbitration

request and not the whole contract agreement. Reference

was made to Section 7(2) of the Arbitration and

Conciliation Act in this context. According to the counsel,

this was why the applicant produced only clause 17 of

A.R. N0. 25/07
-11-

Annexure-A, which is the arbitration clause. Counsel

submitted that a reading of Annexures A4 and A5 will show

that this is not the first time that issue has cropped up. It is

submitted that on behalf of the applicant it has been made

clear that it was Sri.George Fernandez who signed the

agreement in the capacity of the Manager, first party and

disputes have arisen on account of actions and inactions on

the part of Sri.George Fernandez, the signatory which were

denied. Respondent maintained that the agreement was

signed by the Managing Director and that the arbitrator was

Manager. In Annexure A5 signatory is referred to as

Managing Director and not as General Manager which is

very significant. According to Mr.Varghese, last page of

Annexure A8 would only strengthen the applicant’s case.

He pointed out that the last page shows that the first party

is styled as Manager. The expression first party is repeated

twice. It shows that the statement that the respondent

A.R. N0. 25/07
-12-

deliberately and intentionally did not sign the first line but

only the second line is incorrect. If the signatory found that

the first party is not Manager he should have definitely

scored it off. If the Manager had signed as witness he

should have scored off the word Manager as first party when

he signed as witness, instead against the expression witness

he should have styled himself as Manager. Annexures 1

and 2 produced along with the counter to the RP will show

that there was a manager for the school and never a

General Manager. A reading of Annexures 2 and 3 together

shows that Sri. Joseph Fernandez himself was the Manager

though while issuing Annexure 3 he is styled as Director.

Mr. Varghese emphasized the words “I am happy to award”

in Annexure 3. Mr.Varghese submitted that the witness

Joseph.J. Was only the Administrator and his full name

Joseph John is indicated in Annexures A5 and A6.

Mr.Varghese highlighted that in the reply affidavit it is

A.R. N0. 25/07
-13-

admitted that Joseph. J. alias Joseph John turned to be the

administrator. The letter pad in Annexures 3 and 5 to 11

shows that he was only “administrator” and not “Manager”.

If so, his successor, the signatory to Annexure B4 also can

be only an administrator and not the Manager. If under

section 21, the commencement of arbitration proceedings is

on the date of request to refer the disputes to arbitration

then it should be deemed to be commenced after 22-11-

2004, the date of Ext.B4. B2 will show that Joseph J. /

Joseph John was working for the petitioner at that time as

administrator which means that there was no Manager to

function as arbitrator. This according to Mr. Varghese is

precisely the reason why in Annexures B4 and B5 though

repeatedly the respondent said that the matter / all

relevant papers would be placed before the arbitrator and

the matter will be decided by him. He did not do so

because there was no manager at that time. According to

A.R. N0. 25/07
-14-

Mr.Varghese it is unbelievable that certificates like B2 and

B3 could be issued by men of average intelligence and

common sense. He submitted that those documents are

fabricated and cooked up. He pointed out that the title “to

whom it may concern” (sic) is conspicuous. He submitted

that the same mistake is repeated in B2 and B3, though

created and signed on different dates. He pointed out that

the first para of both these annexures is identical. Para 2 of

Annexure B2 and Paras 2 and 3 of B3 are identical. Para 4

of B2 and para 3 of B3 are identical. He asserted that B2

and B3 are dictated by one and the same person. Though

B2 is dated 8-2-08 and B3 is 11-2-08 they are apparently

made on the same date. The reason why the signatories on

B2 and B3 had to issue such certificates is obscure,

according to Mr.Varghese . Obviously the reason is only to

help the respondent. By issuing such certificates both the

signatories to B2 and B3prove their allegiance to the

A.R. N0. 25/07
-15-

respondent, making themselves disqualified to be

independent and impartial arbitrator which is required under

section 11(8)(b) of the Act even assuming that any one of

them can be considered as arbitrator. Mr.Varghese would

fortify his submissions on the authority of a catena of

judicial precedents. He relied on paragraphs 4.030 and

4.031 of Russel on Arbitration 22nd Edition for the

commentaries on apparent bias and real possibility test. He

argued that actual bias is not necessary to be proved and

that the knowledge at the time of appointment does not

debar from applying on the ground that the arbitrator to be

appointed in terms of the agreement may not be impartial.

For this proposition he relied on page 215 of the Law of

Practice of Commercial Arbitration by Mustill and Byod. To

expatiate his argument regarding the concept of

independence and impartiality of arbitrator he relied on

commentaries contained in Comparative International

A.R. N0. 25/07
-16-

Commercial Arbitration by Julian D M Lew QC and others.

He relied on the judgments of the Supreme Court in ACE

Pipeline Contracts (P) Ltd. v. Bharat Petroleum Corpn. Ltd.

(2007) 5 SCC 304, Bihar State Mineral Development Corpn.

and others. v. Encon Builders (I) (P) Ltd. ((2003) 7 SCC

418 and in Tata Cellular v. UOI (1994) 6 SCC 651 in support

of various propositions canvassed by him.

7. Sri. MadhuRadhakrishnan, learned counsel for the

respondent also did not lag behind in citing authorities. The

learned counsel relied on the judgment of the Calcutta High

Court in Pragati Engineering (P) Ltd. v. T.N.Water Supply &

Drainage Board, AIR 1992 Calcutta 139 to argue that where

the parties entered into a contract with their eyes open and

knew that the nominated arbitrator is an employee of one of

the parties, none of the parties to the agreement should be

allowed to allege that such nominated arbitrator being an

officer of one of the parties to the contract, would be biased

A.R. N0. 25/07
-17-

or is likely to be biased. Mr. Madhu Radhakrishnan relied

on the judgment of the Supreme Court in International

Airport Authority of India v . K.D.Bali, (AIR 1988 SC 1099)

to argue that the apprehension of bias must be judged from

a healthy, reasonable and average point of view and the

request for removal of the appointed arbitrator is not to be

granted lightly. Mr.Madhu Radhakrishnan placed reliance on

the judgment of the Supreme Court in Jain Studios Ltd. v.

Shin Satellite Public Co. Ltd., (2006) 5 SCC 501 also.

8. The provisions contained in sections 12 and 13 of

the Arbitration and Conciliation Act incorporate grounds for

challenge and the challenge procedure against and in

respect of arbitrators will reveal that partiality and bias or

circumstances giving rise to justifiable doubts regarding the

impartiality and independence can be valid grounds for

challenging the appointment given to a certain persons as

arbitrator. At the same time, a party should not be allowed

A.R. N0. 25/07
-18-

to wriggle easily out of agreements entered into by them

with open eyes. In the instant case it is seen that the

applicant had agreed to the appointment of a person in the

service of the opposite party as an arbitrator in the event of

disputes. That being the position I would have been

ordinarily reluctant to accept the opposition of the applicant

to the appointment of the nominated arbitrator on ground

of bias and partiality. After all, it is a quasi judicial function

which is being discharged by the arbitrator whose

proceedings will be regulated by the provisions of the

Arbitration and Conciliation Act. His award will be subjected

to judicial scrutiny though on limited grounds and to a

limited extent. But in the instant case I am not inclined to

dismiss the arbitration request and to appoint the

nominated arbitrator as the arbitrator for resolving the

disputes which have admittedly arisen between the parties

because it is seen from Annexures A4 and A5 that the

A.R. N0. 25/07
-19-

respondent also became agreeable to the idea of the

disputes between the parties being resolved by persons

other than the arbitrator nominated under the agreement.

Annexures A6 and A7 will show that the parties had

nominated an Engineer each and were willing to have the

disputes between them resolved by a joint perusal of the

relevant records by these two Engineers. To this extent, in

my opinion the respondent has waived his right to insist

that the arbitrator to be appointed has to be the arbitrator

nominated under the agreement. Moreover, in my opinion

no prejudice whatsoever will be occasioned to the

respondent by appointing a Retired Judicial Officer known

for his learning and integrity as the arbitrator for resolving

the disputes which admittedly subsist. Therefore without

deciding the issue whether appointment of the nominated

arbitrator will be vitiated due to reasons of bias and

partiality I allow the arbitration request and appoint

A.R. N0. 25/07
-20-

Sri.E.K.Muraleedharan, Retired District and Sessions Judge,

presently at Ernakulam as arbitrator for settling all the

claims and counter claims raised by the applicant and the

respondent respondent as detailed in Annexures A1 to A4 as

well as in the arbitration request. The arbitrator will enter

on arbitration and make and publish his award without

undue delay.

(PIUS C.KURIAKOSE, JUDGE)
ksv/