Supreme Court of India

Rajkamal Builders vs Ahmedabad Municipal Corpn. & Ors on 17 September, 2008

Supreme Court of India
Rajkamal Builders vs Ahmedabad Municipal Corpn. & Ors on 17 September, 2008
Bench: R.V. Raveendran, Lokeshwar Singh Panta
                                                       1


                     IN THE SUPREME COURT OF INDIA

                     CIVIL APPELLATE JURISDICTION

                      CIVIL APPEAL NO.5728 OF 2008
             (arising out of SLP(C)No.7222 of 2006)

RAJKAMAL BUILDERS                                                 ... APPELLANT

                                VERSUS

AHMEDABAD MUNICIPAL CORPORATION & ORS.                          ... RESPONDENTS



                                ORDER

Leave granted. Heard learned counsel for the parties.

The Ahmedabad Municipal Corporation (AMC for short) decided to

construct a bridge across the river Sabarmati. In that behalf AMC sought financial

contribution from Ahmedabad Electricity Company (AEC), Oil & Natural Gas

Commission (ONGC) and Gujarat State Road Transport Corporation (GSRTC). As

the cost was estimated to be Rs.11 crores, it was agreed that AMC, AEC,

ONGC and GSRTC will bear the cost in the ratio of Rs.4 crores, Rs.1 crore, Rs.2

crores and Rs.4 crores respectively. According to AMC, it was further agreed that in

the event of the cost exceeding Rs.11 crores, the excess to the extent of Rs.1 crore

would be borne by ONGC and AEC in the proportion of 2:1. AMC appointed AEC

as its agent for construction of the bridge. The work was entrusted to the appellant

for execution. The cost of construction turned out to be Rs.11,38,06,000/-. It is stated

that the additional cost of Rs.38,06,000/- was borne by ONGC and AEC in the ratio

of 2:1 as per the earlier understanding.

2

2. Thereafter, the contractor raised certain disputes in regard to its claims

aggregating to Rs.1,33,36,200/-. The said disputes were referred to arbitration. AMC,

AEC, ONGC and GSRTC were made respondents in the arbitration proceedings.

The Arbitrator by award dated 15.6.1999, awarded a sum of Rs.20,14,860/- to the

appellant contractor and directed that AMC and AEC shall pay the said amount

with interest at the rate of 12% per annum from the date of award till date of

realisation (in the manner set out in para 24 of the award). Feeling aggrieved by the

award, AEC filed an application before the City Civil Court, Ahmedabad under

Section 34 of the Arbitration and Conciliation Act, 1996 (‘Act’ for short). The City

Civil Court by its judgment dated 15.9.2003 upheld the award directing the payment

of Rs.20,14,860/- with interest at the rate of 12% per annum to the contractor.

However, the trial court held that AMC was not liable to pay any amount. It held that

AEC was liable to pay one-third of the award amount and ONGC was liable to pay

two-third of the award amount. Consequently it directed AEC to pay RS.6,71,620/-

plus interest and ONGC to pay Rs.13,43,240/- plus interest to the contractor.

3. Feeling aggrieved by the modification of the award, ONGC filed an appeal

before the High Court of Gujarat. ONGC contended that having regard to the scope

of Section 34 of the Act, the Court ought not to have shifted the liability from AMC

to ONGC. On the other hand AMC supported the order of the trial court. The High

Court by its judgment dated 27.9.2005 allowed the appeal. It held that the ONGC

could not have been made liable to pay Rs.13,43,240/- with interest in modification of

the award of the Arbitrator. The High Court was of the view that having regard to

the nature of jurisdiction exercised under Section 34 of the Act, and as the provisions
3

of Section 96 and Order 41 Rule 33 of CPC were inapplicable, the trial court could

not have shifted the liability from AMC to ONGC. Therefore, the High Court set

aside the decision of the trial court to the extent it held that ONGC was liable to pay

Rs.13,43,240/- with interest.

4. Feeling aggrieved the contractor has filed this appeal by special leave.The

contractor submits that it is not concerned whether the AMC pays or ONGC

pays, so long as some one pays the award amount to it.The grievance of the contractor

is that the High Court while setting aside the liability of ONGC, ought to have issued

a specific direction to AMC to pay the amount or ought to have stated that the award

of the Arbitrator stood restored in full. The contractor apprehends that the judgment

of the High Court may be so interpreted that AMC may dispute its liability to pay

Rs.13,43,240/- with interest on the ground that there is no specific direction to them

by the High Court to pay the said sum.

5. On a careful consideration of the judgment, we are of the view that there is

no basis for the apprehension of the contractor-appellant. The entire judgment when

read as a whole, makes it clear that all that the High Court intended was to shift

back the liability from ONGC in regard to Rs.13,43,240/- with interest and not to

reduce the amount due to the appellant. In short the effect of the decision of the High

Court is to restore the award to its original position. It therefore follows that the sum

of Rs.13,43,240/- with interest thereon will have to be paid in terms of the award.

6. However, this leaves us with the dispute between AMC and ONGC as to

who should bear the said liability. As observed above, the appellant contractor is not

concerned with this dispute. It is unfortunate that even though the liability towards
4

the contractor for the sum of Rs.20,14,860/- with interest awarded by the Arbitrator

was not under challenge, the contractor has not been able to get the amount due to it

for nearly a decade because of the inter-se dispute in regard to liability between the

AMC and the ONGC.

7. AMC is a statutory body established under the Ahmedabad Municipal

Corporation Act and ONGC is a statutory Corporation established under the Oil &

Natural Gas Commission Act, 1959. In regard to disputes between Government

departments and public sector Undertakings, there is a mechanism for amicable

resolution of disputes by mutual negotiations or through good offices of the High

Powered Committee constituted by the Central Government, before parties approach

a court. (See: ONGC vs. CCE-1995 Supp(4) SCC 541). Though the dispute between

AMC and ONGC may not strictly fall under the category of disputes referable to the

High Powered Committee, there is no reason why an attempt should not be made by

AMC and ONGC to sort out the dispute between them by mutual negotiations or

through the High Powered Committee, before the issue is considered by the court.

There is also no reason why the appellant contractor should wait for payment till the

issue is decided as between AMC and ONGC.

8. Therefore in exercise of power under Article 142 of the Constitution, we

direct that the amount admittedly due as per the award (the sum of Rs.13,43,240/-

with interest thereon) shall be paid equally (50% each by AMC and ONGC) to the

appellant-contractor within three months from today. AMC and the ONGC shall also

pay a sum of Rs.10,000/- as costs to the appellant contractor. The appeal is disposed
5

of accordingly in so far as the appellant is concerned.

9. Such payment will be without prejudice to the rights and contentions inter

se between themselves. AMC and ONGC shall endeavour to sort out the dispute

between themselves as to who is liable, in the manner stated above. In the event of

failure, this Court will consider the question. List the matter after six months to

enable AMC and ONGC to report about the results of their efforts of negotiated

settlement.

……………………….J.

( R.V. RAVEENDRAN )

……………………….J.

( LOKESHWAR SINGH PANTA)
NEW DELHI,
SEPTEMBER 17, 2008.