Gujarat High Court High Court

Rinabhai vs Range on 11 February, 2010

Gujarat High Court
Rinabhai vs Range on 11 February, 2010
Author: S.R.Brahmbhatt,&Nbsp;
   Gujarat High Court Case Information System 

  
  
    

 
 
    	      
         
	    
		   Print
				          

  


	 
	 
	 
	 
	 
	 
	 
	 
	 
	


 


	 

SCA/7233/2009	 4/ 4	ORDER 
 
 

	

 


IN
THE HIGH COURT OF GUJARAT AT AHMEDABAD
 


 


 


SPECIAL
CIVIL APPLICATION No. 7233 of 2009
 


 
 
=========================================
 


RINABHAI
M SINGHAL - Petitioner(s)
 


Versus
 


RANGE
FOREST OFFICER - Respondent(s)
 

========================================= 
Appearance
: 
MS
TRUSHA H MEHTA for Petitioner(s) : 1, 
MR NEERAJ SONI,
ASSTGOVERNMENT PLEADER for Respondent(s) : 1, 
NOTICE SERVED for
Respondent(s) : 1, 
=========================================
 
	  
	 
	  
		 
			 

CORAM
			: 
			
		
		 
			 

HONOURABLE
			MR.JUSTICE S.R.BRAHMBHATT
		
	

 

 
 


 

Date
: 11/02/2010 

 

 
 
ORAL
ORDER

1. The
petitioner, a second party workman in Reference (L.C.J.) No.118 of
1996 has approached this Court under Article 227 of the Constitution
of India, challenging the award impugned dated 27.1.2009 passed by
the Presiding Officer, Labour Court, Junagadh, Camp at Porbandar
rejecting the said Reference for the reasons stated thereunder.

2.
The workman had to raise industrial dispute as his services came to
be terminated in the year 1986 without any rhyme or reason or without
complying with the provisions of the Industrial Disputes Act,1947.
However, he was reemployed on 17.11.1986 on daily wage basis and on
20.10.1995 his services were terminated without any due procedure of
law. This termination being illegal, the dispute was raised which was
referred to the competent Court wherein it was marked as reference
stated hereinabove. The Court after recording the reasons with regard
to employee’s inability to establish that he had worked for 240 days,
rejected the same and being dissatisfied with the said judgment and
award, the present petitioner has approached this Court by filing
this petition under Article 227 of the Constitution of India.

3. Ms.

Trusha Mehta, learned advocate for the workman, relying upon the
provisions of Sections 25B, 25F of the Industrial Dispute Act,1947
and the decision of the Supreme Court in the case of Workmen of
American Express International Banking Corporation vs. Management of
American Express International Banking Corporation
reported in (1985)
4 SCC 71, especially in paras 2 and 5, contended that the operation
of law, as extended on the statute book, makes it incumbent upon the
authorities to count the days on which the workman could not work on
account of either it being public holiday or for any reason
preventing the workman from discharging his duty despite his desire
to work and if that is accepted, then looking to the Annexure-I, the
workman is said have completed the period of 240 days to attract the
provisions of Section 25F of the Industrial Disputes Act,1947 and
non-compliance therewith would result into order of reinstatement
with appropriate relief of backwages.

4. Shri Soni,
learned Assistant Government Pleader submitted that even as the
formula suggested under Section 25 is taken into consideration, then
also the workman has not completed 240 days as could be seen from the
decision of American Express International
Banking Corporation (Supra). Shri Soni, learned Assistant Government
Pleader has submitted the following chart, which is enunciated in the
affidavit-in-reply filed on behalf of the respondent with regard to
the presence of the petitioner for the periods mentioned
hereinbelow:-

Month/
Year

Worked
days

October,
1994

23(10)

November,1994

24

December,1994

26

January,
1995

26

February,
1995

21

March,
1995

26

April,1995

25

May,1995

24

June,
1995

13

July,
1995

August,1995

September,
1995

October,
1995

3

5. This
Court has heard the learned advocates for the parties and has perused
the documents submitted therewith. In the peculiar facts and
circumstances of the case, the fact remains to be noted that the law
with regard to establishing the workman’s completion of 240 days is
now clear. Initially, the burden of establishing
completion of 240 days is on the part of the workman. In the instant
case, looking to the order impugned, it can well be said that the
Labour Court has not committed any error in concluding that if the
foundation is not led in the pleadings for a particular submission,
then that submission, which has bearing upon the factual aspect,
could not be examined even at the Court of first instance, much less
at the hearing of the petition filed before this Court under Article
227 of the Constitution of India. This Court needs to be mindful of
the fact that the petition is filed under Article 227 of the
Constitution of India and therefore, the same is to be viewed from
the restrictions inherent under the exercise of jurisdiction under
Article 227 of the Constitution of India. Hence, the order impugned
may not be interfered with, as in the instant case, the findings
recorded is based upon the pleadings and material available. This
Court would not like to enter into the merits of the case as the
petition being bereft of merits, deserves rejection and is
accordingly rejected. No order as to costs. Notice is discharged.

(S.

R. Brahmbhatt, J. )

sudhir

   

Top